Construction of this greenfield corridor will be financed by the Asian Development Bank (ADB) under Bharatmala Pariyojana Phase-I program with a
primary goal to improve the efficiency of freight movement and boost exports.
YONGMA Engineering Co. Ltd. – Arkitechno Consultants was appointed as the agency to prepare its Detailed Project Report (DPR).
Project’s Total Length: 464.662 km
Lanes: 6
Deadline: 2025
When ready, the distance from Raipur to Vizag will reduce from 590 km to 464 km and reduce travel time from 14 hours to about 7 hours.
Current Status
Tendering is underway for the expressway’s construction. Detailed Project Report (DPR) for a majority of the project has been completed and
acquisition of land, forest and environment clearance are in different stages of approval.
Route Map
The Raipur – Vizag Economic Corridor project starts from Abhanpur near Raipur (Chhattisgarh) and ends at Sabbavaram near Vizag (Andhra Pradesh).
The highway’s greenfield alignment will pass through the states of Chhattisgarh (124.611 km), Odisha (262.211 km) and Andhra Pradesh (99.629 km).
The following not-so-pretty map from the government’s environment clearance site displays its route:
https://themetrorailguy.com/nhai-raipur-visakhapatnam-economic-corridor-information-route-map-status/ 1/3
1/30/23, 2:12 PM Raipur Vizag Expressway: Status, Route Map & News [2023]
Package Contractor
CG2: Sargi to Basanwahi (km 42.800 to km 99.500) Dilip Buildcon Ltd. is lowest bidder
CG3: Basanwahi to Marangpuri (km 99.500 to km 124.661) KMV Projects is lowest bidder
OD3: Badakumari to Karki (km 179.000 to km 226.500) Adani Transport is lowest bidder
OD4: Karki to Kaliagura (km 226.500 to km 249.000) NKC Projects is lowest bidder
https://themetrorailguy.com/nhai-raipur-visakhapatnam-economic-corridor-information-route-map-status/ 2/3
1/30/23, 2:12 PM Raipur Vizag Expressway: Status, Route Map & News [2023]
AP Package 2: Jakkuva to Korlam (km 396.800 to km 421.100) NKC Projects is lowest bidder
AP Package 3: Korlam to Kantakapalle (km 421.100 to km 445.100) PSK Infrastructures and Projects is lowest bidder
AP Package 4: Kantakapalle to Sabbavaram (km 445.100 to km 464.662) NKC Projects is lowest bidder