Professional Documents
Culture Documents
4th FLOOR # 65 Olympic Bldg. Sen. Gil Puyat Ave. Makati City
Tel/Fax: 8887-2306
Email Add: sales-pgsc@primegroup.ph
INTRODUCTION
This Work Method Statement is to ensure the floor and wall covering is carried out in a
controlled and systematic manner that in all respect confirm to the specification.
A. Handling Material
1. Temporary Storage Area
Upon arrival of the crates at the temporary storage area, check the
quantity of the stone against the purchase order and the delivery order
to ensure that the correct quantity and crate number are delivered to
site.
Unload the crates to the specific area in the temporary storage area.
The crates shall be stored sector by sector for retrieval when they are
required to be transported to the required area.
2. Installation Location
At the respective floor, the crates will be conveyed to the respective
installation location where they are required for installation.
Open the crates and remove the crates for installation.
B. Grouting/ Pointing
1. Internal Dry Areas
Granite joints should be grouted with Fine Grout, colored, water
resistant, cement based suitable for joints up to 3mm wide.
When grouting to internal dry areas, mix grout with clean water only.
Mix until a uniform colored, thin creamy consistency is obtained.
2. Internal Wet Areas
Granite joints should be grouted with Fine Grout, colored, water
resistant, cement based suitable for joints up to 3mm wide.
When grouting to internal dry areas, mix grout with clean water only.
Mix until a uniform colored, thin creamy consistency is obtained.
Grout offers greater resistant to penetration of water, improved
durability, flexural strength, compressive strength and adhesion to side
of granites.
Allocate joints of approximately 2mm wide between granite slabs.
Apply grout with a rubber squeegee/ float and ensure that joints are
fully compacted with grouting material.
Clean excess grout promptly using a damp cloth or sponge.
Allow grout to set for at least 24-48 hours (preferably longer) before
granite slab installation are subjected to normal service condition.
General Consideration
Setting Out
Setting out shall be carried out based on reference points provided by the main
contractor.
Similarly gridlines are set out based on the control points provided by the main
contractor.
After all the levels and grid lines have been marked on each column/wall, the
position of the brackets.
Marked fabricated truss/channel position on column/wall.