MONTHLY HSE REPORT

Project: B-Hub Location: Nanakramguda

EHS Statistics
A. Safety Status: Date: 26.05.2023 - 25.06.2023
Current Month Cumilative Since Inciption of the Project Safe Man-
Sr.No Type of Accident hours since last
No's Mandays No's Mandays LTI
Lost Lost
1 Near Miss (Mandatory)
2 First Aid Cases
3 Lost Time Injury
4 Fatal
5 Dangerous Occurrence
6 Fire

B. Status of Frequency and Severity Rate:

Avg. Man Power Current Cumulative Since Inciption of the


Sr. No. Remarks
Month Project.

1 Staff 38 585
2 Contractor 197 2562
3 Total Man-day’s 235 3147
Man Hours (10hours/day) 2350 31470
Frequency Rate: (As per Indian standard 3786: 1983)
Number of reportable lost time injury X 1000000
Man-hours worked
Severity Rate: (As per Indian standard 3786: 1983)
Man-days lost due to reportable lost time injury X 1000000
Man-hours worked

C. HSE Training Records:


No. of Cumulative Since Inciption
HSE trainings No of Attendees /Persons
Sessions. of the Project
HSE Induction training 0 0 41
Re-frseh HSE Induction 0 0 1
Regular Tool Box Talk (TBT) 27 197 2562
Special Safety Training 4 29 279
Any other
D. HSE Checklist Records:

Name of HSE Checklist Current Cumulative Since Inciption of the Remarks


Month Project.

Power Tools 1 20
Full Body Harness 0 0
Fire Extinguisher 1 24
Bar Bending M/C N/A
Bar cutting M/C. N/A
E. Potential Hazard observed & rectified:
Current Cumulative Since Inciption of the
Potential Hazard Identification Month Project Remarks

No of weekly HSE inspections conducted by project senior


management. (Mandatory) 3 45 0

Hazard observed 4 20
Hazard rectified 4 20
Hazard not attended
Prepard by Reviewed & Approved by

Mr. Rajat Ku. Mishra (Safety Officer)

HSEM/HSEO, PMC Project Manager, PMC