JOB SAFETY ANALYSIS

Construction of Jakarta Mass Rapid Transit Project Underground Section CP 104-CP105 ( JSA )
Job Description :
Area/Unit :
DATE ISSUED :
WO No : LAST REVIEWED DATE:
References :
PPE Required to do this Job:  Safety glasses  Dust/weldingmask  Coveralls  Safety harness/lifelines  Hard hats
 Goggles/faceshield  Cartridge-filter mask  Chemical clothing  Life vest  Welding helmet
 Earplug/Earmuff  SCBA/SABA  Leather/chemical gloves  Leather/chemical boots  Others ________________________

Machine/Equipment/Tool
JOB STEP Potential Hazard/Loss Control Statement
involved in each step
Hot Work Grinding Spark 1.1.1 Work permit system
Damaged grinding dics 1.1.2 Provide Fire extinguisher
1.1.3 Worker using PPE ( Apron, Face shield, Glove, safety
shoes)
1.1.4 Ceck Equipment RPM before Work (Disc griding and
grinding machine)

Gas Cutting
Fire, burn, spark 1.2.1 Hot work Permit
Explosion & Burning Material 1.2.2 Check Leaked equipment before work (Tube, Hose,
Regulator)
1.2.3 Installed Flashback arrestor
1.2.4 Make sure Hot work activity far form flammable materials,
fuel storage
1.2.5 Worker using PPE ( Apron, Face shield, Glove, safety shoes)
1.2.6 Fire extinguisher / Fire Blangket
Machine/Equipment/Tool
JOB STEP Potential Hazard/Loss Control Statement
involved in each step

Welding Fire, Burn, Spark 1.2.1 Hot work Permit


Electrick shock 1.2.2 Check welding equipment before work (travo, cable)
1.2.3 Make sure Hot work activity far form flammable materials,
Damage cable
fuel storage
1.2.4 Grounding at welding tools
1.2.5 Worker using PPE ( Apron, Face shield, Glove, Safety shoes,
Google)
1.2.6 Fire extinguisher and Fire Blangket

SEMUA YANG TERLIBAT DALAM PEKERJAAN HARUS MEMBACA DAN MENANDATANGANI DOKUMEN INI
NO NAMA Tanda Tangan NO NAMA Tanda Tangan

REVIEWED AND APPROVED BY SUPERVISOR :

Nama :

Tanda tangan :