DATE-22/06/2023 (ENGG)

Block Slot availabe Location BLOCK PROPOSED / AVAILED


Date
SECTION Dept. Block Section/ REMARKS Progress
(Day) From To Duration Type of work From KM To KM From To
Station
22.06.2023 NMX-NQH UP
JPE-NCB (UP) Engg 19:30 22:00 2:30 Defective Glued Joint change 41/3 41/4
(Thursday) LINE
22.06.2023
JPE-NCB (DN) Engg 5:00 9:00 4:00 DTE Machine Packing SJRR-PQZ 114/0(DN) 115/3(DN)
(Thursday)
TSR at Points & Xing over Pts NOQ Yard UP/L,
Engg 21:00 23:00 2:00 145/1 145/3
No. 131,137 Line No.2
Engg 5:00 7:00 2:00 Welding work CROA-GOGH 201/6 201/7
22.06.2023
NCB-NBQ (UP) Engg 5:00 7:00 2:00 TSR work of point no. 13A CROA-GOGH 201/8 201/9
(Thursday)
Sleeper carry and Sleeper
Engg 5:00 7:00 2:00 JOQ-SRPB UP/L 173/0 176/1
Squaring and changing

Engg 5:00 7:00 02:00 UTV SMTA-KAMG 161/2-5 180/2-4 SL

Engg 4:00 8:00 4hrs CTR work FKM-CROA 212/8 213/1


22.06.2023
NCB-NBQ (DN) Engg 4:00 8:00 4hrs Duomatic FKM-CROA 209/6 207/1
(Thursday)
ENGG 16:00 18:00 2:00 Rail unloading SLKX -KOJ 223/0 224/0
BNV Yard welding of Glued
Engg 10:30 12:30 2:00 BNV Yard 99/7 99/8
joint .15

Engg 7:00 8:30 1:30 Welding MDT-HSA 127/3 127/7

22.06.2023 DDM YD,


SMTA-APDJ-SGUJ Engg 19:30 23:30 3:00 TRR (S) 49/1 49/3
(Thursday) D/END L-3

Engg 6:00 10:00 4:00 SEJ changing APDJ-SMTA 170/4 170/5

Engg 6:00 10:00 4:00 Glued joint welding APDJ yard Dead End

22.06.2023
NCB-NCBD Engg 9:30 12:30 3:00 DFWR removal CAPG-NCB 77/9 78/0
(Thursday)

22-06-2023
NCB-GKJ Engg 6:30 9:30 3:00 TFTR BXHT-AGMN 124/0 124/6
(thursday)

Engg 13:00 16:00 3 hrs DUO+DGS FKM-GKJ 49/3 51/2


22.06.2023
FKM-DBB SL
(Thursday)
Engg 13:00 16:00 3 hrs BRM FKM-GKJ 7/5, 10/0,

22.06.2023 10:30 12:30 SC sleeper insertion over Br.


APDJ-BXT Engg 5:00 NCB - DWT 30/5 30/8
(Thursday 16:00 19:00 No-25