You are on page 1of 22

ERECTION OF REFORMER

FURNACE PROCEDURE |
METHOD STATEMENT
1.0 PURPOSE:
1.1 This method statement shall provide minimum guidelines
in accordance with international codes, standards, project
drawings and specification to erect Reformer Furnace in
plants and Refinery.

2.0 SCOPE:
2.1 This specification covers the minimum requirements for
erection of reformer furnace to be applied in in plants and
Refinery.

3.0 APPLICABLE DOCUMENTS:


3.1 Specification and Standards
3.1.1 S-000-1630-003 Material and Equipment Protection
Program at work Site
3.1.2 S-000-1520-103 Handling Procedure
3.1.3 S-000-1640-005 Procedure for Work Release Between
Disciplines
3.1.4 S-000-1520-102 Non-Conformity Control Procedure
3.1.5 S-000-1520-101 Field QC Procedure
3.1 .6 S-000-1650-001 Safety Execution plan
3.1.7 S-000-1351-002 Installation Marking Procedure
3.1.8 S-000-3150-001 Installation of Static Equipment
3.1.9 FWBS CODE (5000) Equipment Installation

3.2 ARAMCO Project Specifications and Standard


3.2.1 SAES-W-011 Welding Requirements for On-Plot Piping
3.2.2 SAES-F-001 Design Criteria of Fired Heaters
3.2.3 SAES-H-001 Coating Selection and Application
Requirements for Industrial Plants and Equipment
3.2.4 SAES-N-100 Refractory Systems
3.2.5 SAES-N-110 Installation Requirements – Castable
Refractories
3.2.6 SAES-N-130  Installation Requirements – Fireclay
Bricks
3.2. 7 SAES-N-140 Installation Requirements – Refractory
Ceramic Fiber
3.2.8 32-SAMSS-029 Manufacture of Fired Heaters

3.2.9 SAEP-302 Instruction for obtaining a waiver of a


mandatory Saudi ARAMCO Engineering requirement.
3.2.10 Related Vendors Installation and maintenance manuals
and /or specifications.
3.2.11 SAES-Q-005 Concrete foundation
3.2.12 SAES-Q-010 Cement Based Non-shrink Grout for
Structural and Equipment Grouting.
3.2.13 SAES-L-350 Construction of Plant piping
3.2 .14 SAES-H-101V Approved Saudi Aramco Data Sheets –
Paints and Coatings.

3.3 Industry Codes and Standards:


3.3.1 AWS D1.1 Structural Welding Codes

3.4 Inspection and Testing Plan/Method


Statement
3.4.1 SATIP-D-001-01 Typical Inspection Plan Pressure Vessel
Installation
3.4.2 SATIP-Q-010-01 Cement Based Non-Shrink Grouting
3.4.3 SATIP-M-001-01 Structural Steel-Piperack, Steel
Supports & Miscellaneous* Steel Structures (* Incl. Piping
Supports per Specification)
3.4.4 SATIP-W-011-01 Welding of On-Plot Piping
3.4.5 SATIP-F-001-01 Fired Heaters – Field Installation
3.4.6 SATIP-N-110-01 Castable Refractory Installation
3.4.7 SATIP-N-130-01 Refractory System- Fireclay Bricks &
Tile Installation
3.4.8 SATI P-J-600-01 Safety Relief Valve Installation

3.5 Latest Revision of the following Documents


shall be used.
3.5.1 Vendor Drawing
3.5.2 Foundation Drawing
3.5.3 Equipment Details

3.6 Saudi ARAMCO Safety, Health and


Environmental Standard:
3.6.1 Construction safety manual – compliance with schedule
D.
3.6.2 General Instructions (G.l’s) at the work site.
4.0 RESPONSIBILITY:
4.1 Construction Manager shall be responsible for
implementing HSE, analyze and schedule all construction
activities with his department to include manpower and
equipment line up as well as other possible resources required
for the successful implementation of the construction work
activities. Study all aspects of work procedure as per Saudi
Aramco Standards.

4.2 Mechanical Superintendent/ Supervisor shall study and


review all necessary  documents for the Erection works in his
area to include, technical scope of work, specification, bill of
quantities, planned milestone dates and construction
procedure in support to his Mechanical Foreman. He shall
monitor the availability of materials in accordance with the
schedules and construction analysis. He shall be directly
reporting to the Construction Manager. He shall coordinate
with other discipline to visualize possible conflicts in the
drawings as well as in the schedules to provide other options
in preventing unnecessary delays and obstructions.

4.3 The Welding Supervisor and/or Foreman are solely


responsible to ensure that all welding works are in
conformance with applicable codes, standards, specifications
and approved procedures.
4.4 Mechanical Foreman shall be responsible for the direct
work supervision at site and ensured that the work is
performed in accordance with Saudi Aramco Standards and
latest approved for construction drawings. He shall monitor
the availability of materials in line with his required schedule.
4.5 QC Inspector shall be responsible in monitoring and
inspection of the work and ensured that the work is performed
and properly documented in accordance with Saudi Aramco
Standards.
4.6 Safety Officer/Supervisor shall be responsible in
monitoring safety aspects and ensuring that the work is done
in accordance with Saudi Aramco Safety Standard Procedure
He shall discuss to the workers the characteristics of related
materials and Status of work area giving reminders as an
additional point to work safely.

5.0 MANPOWER
5.1 The Mechanical Supervisor shall control the overall
activity of Fitter and pipe support machine Erection . The
basic manpower under him shall consist but not limited to the
following:
5.1 .1 Supervisor Mechanical
5.1.2 Foreman mechanical
5.1 .3 Rigger 1 (certified)
5.1.4 Rigger ( certified)
5.1.5 Welder
5.1.6 Millwright
5.1.7 Mechanical Fitter
5.1.8 Masons/Carpenters
5.1.9 Crane Operator (certified)
5.1.10 Safety Engineer/supervisor
5.1.11 Truck driver
5.1 .12 QC Inspector
5.1.13 Surveyor
5.1.14 Helper/ Fire watcher

5.1.15 Structural Worker


6.0 TOOLS AND EQUIPMENT;
6.1 Tools and equipment needed should be in good condition
and must be checked by Mechanical Supervisor/Safety Officer
prior to use in the construction area. These Includes but not
limited to:
6.1.1 Calibrated engineering level with calibration certificate.
6.1.2 Corrective wrenches all required range.
6.1.3 Certified sling and hoists.
6.1.4 Rigging accessories.
6.1.5 Spreader Beam (approved by ARAMCO).
6.1.6 Concrete drill.
6.1.7 Millwright Precision meter.
6.1.8 Theodolite.
6.1.9 Auto level.
6.1.10 Crawler crane
6.1.11 Tag line nylon rope
6.1.12 Welding Machine.

7.0 ERECTION OF REFORMER


FURNACE PROCEDURE |
METHOD STATEMENT:
General Requirements – Seal welding activity shall be done
for all radiant and convection connection flanges.

7.1 Job site Receiving and Inspection:


7.1.1 Upon withdrawal and receipt of equipment from
warehouse, receiving inspection shall be conducted
immediately to verify compliance with the latest revision of
vendors drawing, project requirements & SAEP-302.
7.1.2 Record of Material Receiving Inspection shall be
documented. Findings, deviations shall be documented in
Quality control Inspection Report (QCIR) and Non
Conformance Report (NCR).

7.2 Equipment Preservation/Protection:


7.2.1 Vendor’s/Manufacturer’s recommendation for
equipment preservation shall be followed, also comply with
project requirements and standard.
7.2.2 When the equipment arrived at site, shop preservation
shall be checked. Where necessary damage to preservation
shall be rectified without delay.

7.3 Preparatory Works:


7.3.1 Secure work permit prior to work commence.

7.3.2 Tools and equipment shall be made operational and


available for use. Ensure tools are color-coded accordingly.
Calibration certification where required shall be in valid dates.
7.3.3 Prior to the arrival of equipment on site, must review the
manufacturer’s requirement and the requirements of this
Project Specification regarding site storage of the equipment.
These requirements shall be incorporated with the
preservation plan in all respects.
7.3.4 Mobilize all manpower, tools and equipment needed for
the job.
7.3.5 Check the availability of material according to the
erection sequence.
7.3.6 Compliance with GI 7.025 for Heavy Equipment
Operator Testing and Certification.
7.3.7 Install barricades to confine the area for authorized
personnel only.
7.4 Foundation Preparation for Reformer Furnace:
7.4.1 Confirm acceptances & turnover of civil works
foundation/pedestals with a signed copy of works release
notice prior to installation of equipment / structure.
7.4.2 Verify the equipment/ structure seating area
requirements.
7.4.3 When the foundation released the following points shall
be checked with the latest relevant drawing:
7.4.3.1 Distinct position (centre) marking and height (level)
marking on the foundation, It will be referred for alignment
work of level and position.
7.4.3.2 Size and number of anchor bolt and nuts, position of
anchor bolts with projection.
7.4.3.3 Existence of damages and rust of threaded of buried
anchor bolts with projection.
7.4.3.4 Trace centerlines of foundation bolt holes with
reference to gridlines. Check Verticality/plumbness of anchor
bolt.
7.4.3.5 Clean the surface thoroughly by blowing with oil-free
from air compressor.
7.4.3.6 Centerlines lost due to chipping operations will retrace
anew.

7.4.4 Anchor bolts shall be protected properly to avoid


damages during chipping/padding work and keep it up to the
structure & equipment installation.
7.4.5 The elevation of the chipped top foundations shall be set
to consider the required grout thickness under the base plate
as per the design drawings.
7.4.6 The bottom of the bases shall be cleaned and free of
laitance, oil or grease.
7.4.7 Laitance shall be removed from the surface of the
foundation and boxes by chipping to ensure good adherences
of padding and grout materials to the surface preparation.
7.5 Dimensional Inspection and Checking of Foundation:
7.5.1 Using Work Transfer Sheet, following shall be done;
• Establish centerlines (Northing and Easting) of columns
reference to applicable foundation/civil drawings.
• Using an auto level, confirm Top of Concrete (T.O.C.)
elevation.
7.5.2 Compare data with reference drawings and Survey Data
Record. Note the discrepancies and unacceptable tolerances
and report through QCIR.

7.6 Padding
7.6.1 Pads and liners shall be machined flat parallel and larger
than the foot of base frame.
7.6.2 Pads material shall be in accordance with ASTM A283
Gr. C,D or equivalent.
7.6.3 Pad shall be hot dip galvanized in accordance with
ASTM A123 or coated with zinc rich epoxy primer in APCS-1C
of SAES-H-101Vas applicable.
7.6.4 In general, the distance between pads shall not exceed
800 mm. If the distance becomes more than 800 mm, an
additional pad shall be added in between.
7.6.5 Pad size shall be selected as per the anchor bolt size as
follows:
7.6.5.1 Bolt diameter M 24 or 1 inch and below Pad width 50
mm
7.6.5.2 Bolt diameter M 30-M 48 or 1-1/4 to 2 inches Pad
width 75 mm.
7.6.5.3 Bolts diameter M 56 or 2-1/4 inches and above Pad
width 100 mm.
7.6.6 Number of pads shall be determined so the load
pressure will be less than 30 kg/cm².

• The supporting load can be calculated as per following


formula.

L=W/NxAxB
L: Load supported by liner (kg/cm2)
W: Lifting load of equipment (kg)
N: Number of pads
A: Width of base plate for equipment (cm)
B: Width of liner (cm).

7.6.7 The length of pad shall be 20 mm to 30 mm longer than


the width of the equipment bases.
7.6.8 The thickness of the both taper and straight liners shall
be at least 10 mm and the minimum thickness of the tapered
ends shall be 2 mm. Adjustment allowance shall be 4 to 6 mm.
7.6.9 The wedge liners may be applied to tower and vertical
vessel, if necessary. The gradient of the wedge liners shall be
generally less than 1/30, and two wedge liners shall be used in
back to back so as to make their top and bottom faces in
parallel.
7.6.10 The wedge liners may be applied to tower and vertical
vessel, if necessary. The gradient of the wedge liners shall be
generally less than 1/30, and two wedge liners shall be used in
back to back so as to make their top and bottom faces in
parallel.
7.6.11 After finishing padding work, following points shall be
checked
7.6.11.1 Position of center and elevation line of foundation
7.6.11.2 Elevation and position of pads
7.6.11.3 Cleanliness of concrete surface
7.6.11.4  Condition of anchor bolts

7.7 Erection of Reformer Furnace


7.7.1 Prepare lifting location where the crane will be located
and positioned.
7.7.2 Prepare and set all rigging accessories according to
arrangement.
7.7.3 Checked wind condition, lift shall not proceed when
wind velocity is greater than required of crane.
7.7.4 Stabilized ground areas where crane will be located and
positioned. Crane mats shall be provided in accordance to
findings of soil bearing pressure.
7.7.5 Make sure that all rigging plans are approved prior to
erect equipments/ structure.
7.7.6 Prior to erect radiant panels; verify if all studs anchors
are in good condition or without damage. In case stud anchors
has damage, provide site instruction to and proceed to repair
work.

7.7.7 After arrival of 1st shipment (see attachment B for


illustration)
7.7.7.1 Set of 90 deg. and 270 deg. sides main columns (A-1-3,
E1-3)
7.7.7.2 Set of floor beam support stanchion (B-D-1, B-D-2, B-
D-3).

7.7.7.3 Installation of 90 deg . and 270 deg. side beams


(between A-1-3, E-1-3)
7.7.7.4 Installation of floor beam (line nos. 1-3)
7.7.7.5 Installation of Reinforcement column & beams of O
deg. side
7.7.7.6 Installation of 90 deg. and 270 deg. sides Lower/Upper
Panels (total: 24 panels) JO-F-0401, 0402. Lower panel: 12
panels and Upper Panel: 12 panels.
7.7.7.7 Installation of O deg. side lower panels (Total: 16
panels). Lower panel: 8 panels, Upper Panel: 8 panels.

7.7.8 After arrival of 2nd shipment. (see


attachment B for illustration)
7.7.8.1 Set of main columns (A-4 & 5, E-4 & 5)
7.7.8.2 Set of floor beam support stanchion (B-D-4, B-D-5)
7.7.8.3 Installation of floor beam (Line Nos. 4 & 5)
7.7.8.4 Installation of reinforcement column and beams of 180
deg . side.
7.7.8.5 Installation of 90 deg. and 270 deg. sides Lower/Upper
panels (total: 24 panels) for J10-F-0403, 0404. Lower panel:
12 panels, Upper Panel: 12 panels
7.7.8.6 Installation of 180 deg. Lower panels (total: 16 panels)
Lower panel: 8 panels, Upper panel: 12 panels.
7.7.8.7 Installation of Header support (B’-11-26, D-11-26, F-11-
26, G11-26, H-11-26, 1-11-26, J-1-26, K-11-26, L-11-26, M-11-
26)
7.7.8.8 Place floor panels on temporary location (floor panels
inside and outside section of rad. Coil).

7.7.9 After arrival of 3rd shipment (see attachment


B for illustration)
7.7.9.1 Installation and adjustment of header with radiant
coils for J1 O-F0401, 0402
7.7.9.2 Installation of remaining floor panels for J1 O-F-
0401,0402
7. 7.10 After arrival of 4th shipment (see attachment B for
illustration)
7.7.10.1 Installation and adjustment of Header with Radiant
coils for J10-F0403,0404

7.7.10.2 Installation of remaining floor panels for J10-F-


0403,0404
7.7.10.3 Installation of Radiant Arch truss frame with radiant
arch beams for column line nos. 1-5
7.7.10.4 Installation of Radiant arch structure for column Line
Nos. A&E.
7.7.10.5 Install radiant arch panel.

7.7.10.6 Installation of Transition duct block (Refractory


lining to be done on the ground)
7.7.10.7 Installation of Radiant arch structure for column line
nos. B1, B2C1, C2, 01, 02.
7.7.11 For adjustment or alignment of radiant panels and
column use dead man weight, turn buckle, wire rope/guy
wire, clamps, wire clips, survey instrument and etc.
Plumbness and alignment of radiant columns and beams to be
inspected and confirmed before seal welding of the radiant
panels. Inspection shall be done as per Saudi Aramco
Standard.
7.7.12 Final bolt tightening for the radiant arch truss frame
beams and radiant arch structure shall be commenced right
after plumbness, alignment and level check and acceptance.

7.7.13 After completion of erection until transition


duct and radiant section.
7.7.13.1 Installation of lower convection module.
7.7.13.2 Installation of convection module with breeching.
7.7.13.3 Installation of convection and piping structure ( to EL
+32200 from EL+24200).

7.7.14 After completion of erection for convection


section.
7.7.14.1 Installation of Stack bottom duct

7.7.14.2 Installation of flue gas outlet duct between flue gas x-


over duct and stack bottom duct.
7.7.14.3 Installation of flue gas x-over duct.
7.7.14.4 Installation of stack structure
7.7.14.5 Installation of stack lower block. (Stack lower/middle
sections and the damper unit to be combined on the ground
by welding.
7.7.14.6 Installation of stack upper block.
7.7.14.7 Installation of piping structure (to EL +43250 from
EL +32200)
7.7.14.8 Final bolt tightening for convection structure, stack
support structure and piping support structure shall be
commenced right after plumbness, alignment, and level check
and acceptance.
7.7.15 Installation of radiant vapor barrier, ceramic fiber,
Castable and brick (refer to refractory procedure for more
detail information). After installation it will be inspected by
ARCC QC Inspector as per Aramco Standard prior for final
checking of client.
7.7.16 Using required crane, erect FDF using the approved
rigging plan followed by IDF in accordance to approve for
construction drawing. After erection align & level as per
Aramco standard and should be within the tolerance limit.
7.7.17 Upon approval of client on erection of FDF & IDF
connect ducting such as air duct & burner duct. All ducting
should be done as per approved construction drawing and
within Aramco standard.
7.7.18 Erection of APH and APH support structure.
7.7.19 Erection of flue gas duct support structure.
7.7.20 Erection of Hot and cold flue gas duct.
7.7.21 Installation of external insulation for hot air/burner
ducting.
7.7.22 After installation, final bolt tightening for APH support
structure and flue gas duct support structure shall be
commenced right after plumbness, alignment, and level check
and acceptance.
7.7.23 For miscellaneous equipments or accessories such as
burners, access door, peep doors, expansion bellows & etc.
will be installed manually and to be inspected by client
JGC/DAEWOO & COMPANY after installation.
7.7.24 Installation of cross-over pipes, down-comer, spring
hanger/support, inlet header, outlet header & etc. will be done
as per piping installation & pipe support installation method.
7.7.25 Installation and inspection of access platforms as per
structural steel installation procedure.
7.7.26 See vendor’s erection sequence for more details.
(Attachment B).
7.8 Plumbness check:
• Take sight on the reference point at the top.
• Close the horizontal adjustment knob to lock line of sight of
equipment against horizontal movement.
• Take sight on the reference point on the bottom.
• Out-of-plumb dimension from the reference point at the
bottom can be measured from the reference point to the
survey instrument line off sight using steel tape/measuring
stick.

7.8.1 Use carbon steel shims if needed to adjust verticality and


plumbness.
Wedge blocks when nosed during adjustments shall be
removed after alignment before inspection and final
alignment acceptance.

7.8.2 Shims used for level alignment shall be:


7.8.2.1 Less than 0.0110″ (2.5 mm) thick shall be stainless
steel.
7.8.2.2 Shim thicker than 0.100″ (2.5 mm) shall be carbon
steel.
7.8.2.3 The number of shim, shall be 4 (four) plates at one
hold down bolts.
7.8.3 Using open wrench/hammer wrench, proceed to
preliminary tightening of anchor bolts nuts to bring to “snug
tight” condition.
7.9 Alignment of radiant main columns and beams, seal
welding of radiant panels and final bolt tightening of radiant
arch support structure shall be completed before grout
setting.

7.10 Setting and Alignment:


7.10.1 Horizontal equipment requiring allowance for thermal
expansion shall be installed at the correct position so as that
opening of slot holes have sufficient space for expansion
movement in accordance with the drawing.
7.10.2 Check elevation, levelness, squareness and plumbness
as per SATIP-D001-01 Typical Inspection Plan Pressure
Vessel Installation.
7.10.3 When leveling jack bolts are not provided on the
equipment shims may be used for leveling. All shims shall
straddle the hold down bolt if the machine foot mounted, the
shims shall be the size of the foot. When shims are used
directly under channel or “H” beam sub bases, the shims shall
cover the entire width of the channel “H” Beam and shall be a
minimum of 4 (four) times as the diameter of the both.
7.10.4 After any installation of the equipment and up to
grouting commencement foundation Chipped surface shall be
protected from harmful contamination for grouting with a
Suitable way.

7.11 Bolt Tightening:


7.11.1 All bolts shall be aligned to permit insertion of bolts
without undue damage to the threads.
7.11.2 Bolts shall be placed in all holes with washers
positioned and nuts threaded to complete the assembly.
7.11.3 Any abnormal wear on the equipment and parts during
installation and assembly shall be corrected by the
subcontractor. Prior to the commencement action written
work procedure shall be approve by contractor/company.

7.12 Grouting:
7.12.1 Water for mixing grout non-shrink material must be
fresh and clean, and free from Injurious of oil acid alkali, salt
or organic as per SAES-Q-010 Cement Based, Non-Shrink
Grout for structural and Equipment Grouting.
7.12.2 This grout shall meet the requirement of STS 03600
when used in high fluidity range. Compressive strength shall
be in excess of 34 .5 Mpa (5000 psi) when mixed according to
manufacturer instructions.
7.12.3 Grout shall be mixed in accordance’s with grout
manufacture’s instruction. Shall prepare sufficient quality of
grouting material, clean tools and equipment and suitable
water mixture at site to complete the job.
7.12.4 Grout inside skirt for vertical vessel must be filled with
slope, and an all opening for Drainages must be provided
under the base plate to be toward the nearest surface drain.
Instruction will be issue for item by item by
Subcontractor/Contractor.

7.13 Setting of liner:


7.13.1 Prior to the installation of liners and equipment, the
liners and grouting portion of foundation shall be chipped and
all concrete laitance shall be removed from portion.
7.13.2 Flat liners shall be installed at the positions with pads
of cement grout at least seven days before equipment
installation. lncase non-shrink grout material is used; the
curing duration shall according to the manufacture’s
recommended.
7.13.3 In case that wedges liners are used the level of padding
with a flat liners need to be adjust to meet with the final
equipment elevation.

7.14 Alignment Tolerances:


7.14.1 Vertical Tolerance
7.14.1.1 The angular variation of the working line from a
plumb line shall be equal to or less than 1/500 of distance
between working points. AISC Code of Std Practice – Steel
Bldgs & Bridges Para. 7 .13.1.1 & PIP STSO 5130, Para. 6.2.1.

7 .14.2 Plumbness tolerance for stack shall be max of 25 mm


per 15 m as per API 560 4th edition, Aug 2007.
7.14.3 Position ±3mm
7.14.3.1 Every 90 degree orientation of base plate shall be
measured with reference to the Orientation of the foundation.
7 .14.4 Elevation ±3mm
7.14.4.1 The bottom of base plate shall measure with reference
to the level marking of the foundation. At least, one point of
the base plate shall be aligned within these tolerances.
7.14.5 Levelness 1/1,000 (for horizontal equipment)
7.14.5.1 The center line of equipment shall be in alignment
with the horizontal line within the tolerances of 1/1,000. If
slope is required, the inclination shall be considered.
7.14.6 Perpendicular ±6mm for each 10m (for vertical
equipment only)
7.14.6.1 The center line of the equipment shall be in alignment
with vertical line within the tolerance of ±6mm for every 1 Om
length of the equipment, in principle, provides that such
tolerance 20m and longer equipment shall not exceed
±12mm.

7.15 Damages and Nonconformity


7.15.1 Any damages and defects and nonconformity found at
site and lay down yard shall be reported immediately.

8.0 QUALITY CONTROL


1. QC Personnel shall be assigned to ensure the quality control
and assurance requirement of the project.
2. QC Personnel well coordinate with JGC/DAEWOO inspector
to conduct inspection as required.
3. QC Inspector shall be responsible to conduct all required
inspection/documentations and to ensure that all applicable
requirements, codes, and standards are complied with
SAIC/SATIP.
4. Contractor has to utilize the applicable SAIC for every activity.

9.0 SAFETY PRECAUTION:


Obtain the approval of the work permit from the concerned
Representative before starting any work.

1. TSTI to conduct daily prior to execution of work.


2. Fire Watcher with Fire Extinguisher shall be at work area
whenever there is hot work.
3. Work execution shall be carried out in accordance with
method statement. And in compliance with Saudi ARAMCO
General Instruction G.1.7.028, Crane Lifts; Types and
Procedure.
4. Continuous monitoring and inspection shall be implemented
to detect and correct unsafe practices while performing the
work activities.
5. Provide warning sign and sufficient barricade on working area
and only assigned personnel will be allowed in the area.
6. Worker shall wear PPE’s needed for the work.
7. Install PWAS on all equipment moving in this activity.
8. All rigging equipment shall be in good condition and possess a
valuable certificate from authorized certifying and inspection
department. In compliance with Saudi ARAMCO General
Instruction G.1.7.030 Inspection and Testing Requirements
for Elevating/lifting Equipment.
9. Man lift users shall be trained and certified to operate and use
the equipment.
10. Mechanical Supervisor shall monitor the work activities
to help and to protect all assigned workers against exposure to
safety hazards. He shall ensure that Personal Protective
Equipment (PPE’s) are supplied and used and comply with
Saudi Aramco Standards.
11. Housekeeping shall be maintained and working area
shall be kept in a clean and tidy manner.
12. Job Hazard and Risk Assessment (JHRA) of this method
statement shall be disseminated and explained to workers for
safety awareness.

10.0 ATTACHMENT
Vendor Erection Sequence

You might also like