DOCUMENT NUMBER
S. Keegan/ F. Meredith/
B07 Issued for use W. Xuehui 27th Dec 2015
S. Wright T. Johnston
Digitally signed by Timothy G.
This document is the property of Rumaila Field Develops Projects. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
RUMAILA PROJECT
TECHNICAL QUERY PROCEDURE
This document is the property of Rumaila Field Develops Projects. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
RUMAILA PROJECT
TECHNICAL QUERY PROCEDURE
CONTENTS
1 INTRODUCTION ................................................................................................................ 4
3 DEFINITIONS ..................................................................................................................... 5
4 ABBREVIATIONS ............................................................................................................... 6
This document is the property of Rumaila Field Develops Projects. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
RUMAILA PROJECT
TECHNICAL QUERY PROCEDURE
1 INTRODUCTION
Effective communication between all parties is an important factor in ensuring that ROO
Project requirements are clearly understood and implemented.
This Technical Query (TQY) procedure provides a formal process of submitting and
resolving any issues requiring clarification or response from COMPANY or its
CONTRACTORS and SUPPLIERS. In addition, to providing an audit trail of how any
resulting decisions and/or changes are managed and approved
1.1 Scope
The process described by this document, shall apply to the execution phase of work being
carried out by COMPANY and its CONTRACTORS and SUPPLIERS
This process shall not to be used as a tool to manage outstanding works, manage non-
conformances, interface management, or requesting missing documents and drawings.
NOTE: If any APPROVED TQY results in a commercial and/or schedule impact to the
CONTRACT, CONTRACTOR shall not implement the resolution detailed in the APPROVED
TQY until such times that he is formally authorized to do so by means of a VARIATION or
AMENDEMENT issued under CONTRACT
Where TQY is determined to require a formal Deviation Request, this shall be processed
through PMCS.
A formal Deviation Request is required for any deviation from the codes, standards and
specifications formally adopted by ROO Projects documents listed in, ROO index of
Engineering Codes and Standards, 0000RP-C-G0-G000-QA-IDX-0001
1.2 Purpose
The overall purpose of this document is to define the process for recording, managing and
responding to TQY’s.
• Provide a formal system by which TQY’s can be answered between all parties
including, COMPANY, CONTRACTOR and SUPPLIER
• Maintain an audit trail of how any resulting decisions and/or changes are managed
and approved.
• Ensure that all technical queries are answered by the appropriate authority, related to
their area of responsibility.
• Ensure that TQY’s are documented and processed in a timely and controlled manner.
• Ensure a full understanding of the process when raising, responding to and closing
out TQY’s.
This document is the property of Rumaila Field Develops Projects. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
RUMAILA PROJECT
TECHNICAL QUERY PROCEDURE
2 REFERENCE DOCUMENTS
3 DEFINITIONS
The party which carries out all or part of the described work and services
CONTRACTOR specified by the COMPANY. The CONTRACTOR may undertake all or
part of the duties of the CONTRACT
Shall mean the party that supplies services to perform the duties
SUPPLIER
specified by the COMPANY
This document is the property of Rumaila Field Develops Projects. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
RUMAILA PROJECT
TECHNICAL QUERY PROCEDURE
4 ABBREVI ATIONS
This document is the property of Rumaila Field Develops Projects. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
RUMAILA PROJECT
TECHNICAL QUERY PROCEDURE
This document is the property of Rumaila Field Develops Projects. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
RUMAILA PROJECT
TECHNICAL QUERY PROCEDURE
• Initiating TQY’s with the required information, utilising the current revision of the ROO
Technical Query Template, shown in Appendix 1 of this procedure.
• Allocating the TQY with a unique number in accordance with ROO Specifications,
- 0000RP-C-G0-G000-DM-SPC-0002, (Technical Document Numbering
Specification)
- 0000RP-C-G0-G000-DM-SPC-0007, (Supplier Document Numbering
Specification)
• Uploading the TQY at version (A1) to the ROO CIS (sharecat), for distribution and
response by the required parties.
• Advising ROO DCC of distribution.
Each TQY shall be populated with the required information, as identified below before
uploading to the ROO CIS (sharecat) at version (A1).
This document is the property of Rumaila Field Develops Projects. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
RUMAILA PROJECT
TECHNICAL QUERY PROCEDURE
This document is the property of Rumaila Field Develops Projects. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
RUMAILA PROJECT
TECHNICAL QUERY PROCEDURE
The response to TQY’s, shall be by the Engineering team within ROO or its approved
CONTRACTOR or SUPPLIER.
• Providing a response and processing TQY’s, ensuring that the relevant technical
personnel have participated in the response and/or approval of the TQY.
• Identifying any requirements for an MOC.
• Uploading the completed TQY at version (A1) to the ROO CIS (sharecat), for close
out and agreement by the Initiator. (ROO CIS (sharecat), does not accept TQ’s at
version A2).
Each TQY response shall be populated with the required information, as identified below
before uploading to the ROO CIS (sharecat) as version (A1).
This document is the property of Rumaila Field Develops Projects. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
RUMAILA PROJECT
TECHNICAL QUERY PROCEDURE
This document is the property of Rumaila Field Develops Projects. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
RUMAILA PROJECT
TECHNICAL QUERY PROCEDURE
The agreement of response and close out of TQY’s shall be by the Initiator.
Each TQY shall be populated with the required information, as identified below before
uploading to the ROO CIS (sharecat) at version (A3).
This document is the property of Rumaila Field Develops Projects. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
RUMAILA PROJECT
TECHNICAL QUERY PROCEDURE
This document is the property of Rumaila Field Develops Projects. It must not be stored, reproduced or disclosed to others without written authorisation from the Company
RUMAILA PROJECT
TECHNICAL QUERY PROCEDURE
This document is the property of Rumaila Field Develops Projects. It must not be stored, reproduced or disclosed to others without written authorisation from the Company