VERTICAL PROJECTS
Percentage of
TITLE LOCATION REMARK Contractor / Sub-contractor Notes
Completion
MAASIN CITY
Construction of RKK Hotel & Training Center Brgy. Mambajao, Maasin
42% On-going AC- Rivero - Alfonso Rivero
Phase II City
Construction of Lib-og Causeway Brgy. Lib-og 45% Under Suspension AC- Rivero - Alfonso Rivero Suspended since Nov. 29
CAPITOL Site, Brgy.
Construction of Capitol Building Extension 80% On-going AC- Rivero - Alfonso Rivero
Asuncion
CAPITOL Site, Brgy.
Improvement of Provincial Coliseum 55% On-going J'NER - Nerio D. Cepada, Jr.
Asuncion
St. Timothy Constructon
Construction of Combado Causeway Brgy. Combado 60% Under Suspension Suspended since Nov. 29
Corp.
Construction of Solar Powered Water Supply
Brgy. Lib-og 95% On-going J'NER - Nerio D. Cepada, Jr.
Phase II
Repair of Southern Leyte Provincial Hospital
Brgy. Dongon 85% On-going JJ Bonifacio Builders
(24M)
Establishment of Swine Multiplier & Techno
Demo Farm Brgy. Pananawan 5% On-going JQD - Joselito Q. Dolauta
(Construction of Farm Facilities-Housing)
Repair of SOYMPH (50M) Brgy. Dongon 16% On-going JQD - Joselito Q. Dolauta
Provincial Library, Brgy. Alibona Construction
Construction of Power House 50% On-going
Abgao Services
Construction of Stage & Slope Protection/Flood Notice to Proceed:
Brgy. Libertad 0% Not Yet Started JQD - Joselito Q. Dolauta
Control Dike SEPTEMBER 9, 2022
Upliftment of Vice-Governor's Office, Legislative CAPITOL Site, Brgy. Notice to Proceed:
0% Not Yet Started J'NER - Nerio D. Cepada, Jr.
Lobby and SP Session Hall Asuncion SEPTEMBER 9, 2022
Percentage of
TITLE LOCATION REMARK Contractor / Sub-contractor Notes
Completion
MACROHON
*land issue; for resurvey by
Construction of Health Station Brgy. San Isidro 50% Under Suspension J'NER - Nerio D. Cepada, Jr.
barangay
Construction of Multi-Species Marine Hatchery Brgy. San Roque 70% On-going J'NER - Nerio D. Cepada, Jr.
Multi-Species Fish Hatchery Establishment
Brgy. San Roque 65% On-going J'NER - Nerio D. Cepada, Jr.
Project: Hatchery Construction Phase I
Construction of Multi-Purpose Livelihood & Notice to Proceed:
Brgy. Asuncion 0% Not Yet Started J'NER - Nerio D. Cepada, Jr.
Training Center SEPTEMBER 9, 2022
MALITBOG
Construction of Multi-Purpose Livelihood & Notice to Proceed:
Brgy. Candatag 0% Not Yet Started JQD - Joselito Q. Dolauta
Training Center SEPTEMBER 9, 2022
Construction of Multi-Purpose Livelihood &
Sitio Bliss, Brgy. Abgao 0% On-going JQD - Joselito Q. Dolauta
Training Center
BONTOC
Completion of Multi-Purpose Livelihood and Notice to Proceed:
Brgy. Catmon 0% Not Yet Started JQD - Joselito Q. Dolauta
Training Center SEPTEMBER 9, 2022
Completion of Multi-Purpose Livelihood and Notice to Proceed:
Brgy. Pong-on 0% Not Yet Started J'NER - Nerio D. Cepada, Jr.
Training Center SEPTEMBER 9, 2022
SAINT BERNARD
Notice to Proceed:
Construction of Meat Processing Building Brgy. Sug-angon 0% Not Yet Started J'NER - Nerio D. Cepada, Jr.
SEPTEMBER 9, 2022
ANAHAWAN
Construction of Multi-purpose Livelihood &
Brgy. Poblacion 0% Not Yet Started J'NER - Nerio D. Cepada, Jr.
Training Center
HINUNDAYAN
Construction of Multi-purpose Building Brgy. Baculod 95% On-going JQD - Joselito Q. Dolauta
Construction of Multi-purpose Building Brgy. District I 36% On-going J'NER - Nerio D. Cepada, Jr.
Percentage of
TITLE LOCATION REMARK Contractor / Sub-contractor Notes
Completion
HINUNANGAN
Hinunangan National Notice to Proceed:
Construction of Multi-Purpose Covered Court 0% Not Yet Started J'NER - Nerio D. Cepada, Jr.
High School SEPTEMBER 9, 2022
Construction of Multi-Purpose Livelihood and Canipaan National High Notice to Proceed:
0% Not Yet Started JQD - Joselito Q. Dolauta
Training Center School SEPTEMBER 9, 2022
PINTUYAN
Repair/Rehab. Of Pintuyan District Hospital Pintuyan 50% On-going JQD - Joselito Q. Dolauta