TRANSITION INVESTMENT SUPPORT PLAN (TISP)


Potable Water Supply Project for ARMM
Status of Implementation as of February 25, 2015
PROVINCE OF SULU
FUND RELEASED
PHYSICAL
MUNICIPALITIES NAME OF SERVICE AREA PROJECT MODE OF ACCOMPLISHMENT REMARKS
IMPLEMENTATION
PROJECT COST AMOUNT
%
1.LUGUS Construction of PWS Tingkangan Proper &Extention P9,450,000.00 Contract 100% P9,450,000 62.03% The project implementation is
Level – II Bas Lugus and Lugus Proper On-going on progress
2.LUUK Construction of PWS Tandu Bato, Niog-Niog, P9,450,000.00 LGU Luuk 100% P9,450,000 100 % Subject for Turnover of the
Level – II Kanmindus and Tubig Putih
Project
3.MAIMBUNG Construction of PWS Poblacion, Laum Maimbung, P9,450,000.00 LGU Maimbung 100% P9,450,000 100 % Turn - over Ceremony of Maimbung
Level – II Kandang, Gulangan, Bualo Water System as of October 29, 2014
Lipid

4.OMAR Construction of PWS Angilan P9,450,000.00 Implemented by the 0% P0,000,000 100 % Subject for Turnover of the
Level – II Province Project
5.PANDAMI Construction of PWS Hambilan, Baligtang, Parian P9,450,000.00 Contract 100% P9,450,000 64 % The project implementation
Level – II. Dakula & Subah- Subah On-going is on progress
6.PANGLIMA Construction of PWS Gata – Gata P9,450,000.00 LGU 100% P9,450,000 79.25 % The project implementation
ESTINO Level – II Panglima Estino On-going is on progress
7.PATA Construction of PWS Saimbangon (Poblacion), P9,450,000.00 LGU Pata 100% P9,450,000 79.75 % The project implementation
Level – II Pisak-Pisak and Kiput On-going is on progress
8.TALIPAO Construction of PWS Bilaan Poblacion, Liban, P9,450,000.00 LGU Talipao 100% P9,450,000 100 % Subject for Turnover of the
Level – II Samak and Bandang
Project

TOTAL COST P75,600,000 P66,150,000


Prepared by: Noted by:

AL-JUNEER S. HALUD HJA. SITTI KAUSAR H. SAHIJUAN


Engineer – I Provincial Director
DILG – ARMM, Province of Sulu

PVC Pipe laying @ Lugus Proper as of Jan.23,2014 PVC Pipe laying @ Lugus Proper PVC Pipe laying @ Lugus Proper

1. LOCATION LUGUS

2. SERVICE AREAS Tingkangan Proper, Tingkangan Extention, Bas Lugus and Lugus Proper

3. FUND RELEASE / PROJECT COST P 9,450,000 (100%) / P9,450,000

4. PHYSICAL ACCOMPLISHMENT REPORT 62.03 % On-going

5. ISSUES AND CONCERNS Delayed implementation from the previous months due to the contractor

6. RECOMMENDATION Recommending to hire capable and diligent contractor to avoid delayed implementation.

7. ACTION TAKEN Engr. Wazzer Urao said the contractor is now continuing the implementation of the project.
Prepared by: Noted by:

AL-JUNEER S. HALUD HJA. SITTI KAUSAR H. SAHIJUAN


Engineer – I Provincial Director
DILG – ARMM,Province of Sulu

(R-L) Mpdc Delmar Yusop, Al-juneer Halud-DILG Hired


Engineer, Acting Mlgoo Leila Ynawat and Victor Transmission line from the deep well going to Brgy. Complete set of Solar panel
Taguinud, contractor at the on-going construction of deep Hambilan and Brgy. Parian dakula
well at Brgy Hambilan as of Dec. 04, 2014

1. LOCATION PANDAMI

2. SERVICE AREAS Hambilan, Baligtang, Parian Dakula & Subah- Subah

3. FUND RELEASE / PROJECT COST P 9,450,000 (100%) / P9,450,000

4. PHYSICAL ACCOMPLISHMENT REPORT 64 % On-going

5. ISSUES AND CONCERNS None


6. RECOMMENDATION None

7. ACTION TAKEN MPDC Delmar Yusop committed to fast-track the implementation of the project.

Prepared by: Noted by:

AL-JUNEER S. HALUD HJA. SITTI KAUSAR H. SAHIJUAN


Engineer – I Provincial Director
DILG – ARMM,Province of Sulu

Inspecting the pipeline distribution at Brgy. Lubuk- Pipeline distribution located @ Brgy. Lubuk-Lubuk Pipeline distribution at Brgy. Gata-Gata going
Lubuk, Panglima Estino to adjacent Brgy. Lubuk-Lubuk

1. LOCATION PANGLIMA ESTINO

2. SERVICE AREAS Brgy. Gata – Gata

3. FUND RELEASE / PROJECT COST P 9,450,000 (100%) / P9,450,000

4. PHYSICAL ACCOMPLISHMENT REPORT 79.25 % On-going


5. ISSUES AND CONCERNS None

6. RECOMMENDATION None

7. ACTION TAKEN Engr. Leo Datiles, Municipal Engineer/OIC-MPDC committed to fast-track the implementation of the project.

Prepared by: Noted by:

AL-JUNEER S. HALUD HJA. SITTI KAUSAR H. SAHIJUAN


Engineer – I Provincial Director
DILG – ARMM,Province of Sulu

On-going Construction of Dam Site located On-going Construction of Dam Site On-going Construction of Dam Site
at Brgy. Saimbangon, Pata, Sulu at Brgy. Saimbangon

1. LOCATION PATA

2. SERVICE AREAS Saimbangon (Poblacion), Pisak-Pisak and Kiput

3. FUND RELEASE / PROJECT COST P 9,450,000 (100%) / P9,450,000


4. PHYSICAL ACCOMPLISHMENT REPORT 79.75 % On-going

5. ISSUES AND CONCERNS None

6. RECOMMENDATION None

7. ACTION TAKEN LCE and Mun. Engr. Gener Alih committed to fast-track the implementation of the project..

Prepared by: Noted by:

AL-JUNEER S. HALUD HJA. SITTI KAUSAR H. SAHIJUAN


Engineer – I Provincial Director
DILG – ARMM,Province of Sulu