OFFICE OF THE SECRETARY TO

GOVERNMENT OF THE FEDERATION


PRESENTS

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE


FEDERAL EXECUTIVE COUNCIL (FEC)

FROM
MAY 2015 TO DECEMBER 2017

BY BOSS MUSTAPHA
CONTENT

1.0 INTRODUCTION
Vision, Mission Statements and Core Mandate

2.0 IMPLEMENTATION OF FEDERAL EXECUTIVE COUNCIL (FEC)


APPROVALS FOR:

2.1 Ecological Fund Office


2.2 Cabinet Affairs Office
2.3 Federal Road Safety Corps
2.4 National Hajj Commission of Nigeria
2.5. National Pension Commission
2.6 National Population Commission
2.7 Economic and Financial Crimes Commission

2
1.0 INTRODUCTION

The Office of the Secretary to the Government of the Federation is the Secretariat
of the Presidency responsible for ensuring the effective co-ordination and
monitoring of the implementation of Government policies and programmes.

MANDATE
Monitor and Coordinate the implementation of Government Policies and
Programmes; Serve as frontline advisory institution of the Presidency; Drive Policy
formulation, harmonization, and implementation; and Monitor institutions of
governance.

VISION
To lead and serve as an effective engine room for policy formulation,
harmonisation, implementation and monitoring of the institutions of governance.

MISSION
To deploy political will, administrative expertise, professionalism and the values of
loyalty and commitment in support of the attainment of the goals of the Federal
Government.

3
2.1 ECOLOGICAL FUND OFFICE
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS
CONTRACT & STATUS OF
DATE OF USER ACCESSED BY CREATED REMARKS (PROSPECTS OF
SN PROJECT TITTLE PROCUREME IMPLEMENTAT
APPROVAL AGENCY THE PROJECT SKILLED/ COMPLETION)
NT DURATION ION (%)
(%) UNSKILLED

The Scope of work include: Site


clearing /earth work; Removal of
Reconstruction of
Weak structures/old bridge;
Yola-Mubi Bridge
Construction of Culverts;
at Kaa'a Shiwa Ecological
1 November, 2015 7 Months N/A 100% 38 Re-construction of bridge and
and Mail 30 - Fund Office
Construction of mile 30 - Kwambla
Kwambla Road,
Road. The project is 100%
Adamawa State
completed. Commissioned and
handed over.

The Scope of work include:


Construction of Concrete Channels;
Daura Township
Construction of Box Culverts;
Erosion Control, Ecological
2 December, 2015 9 Months N/A 100% 38 Stone-Pitching and Rock Dumps for
Phase I, Daura, Fund Office
each erosion Control works. The
Katsina State
project is 100% completed.
Commissioned and handed over.

The Scope of work include:


Daura Township Site clearing;
Erosion And Construction of Culverts and
Ecological
3 Flood Control December, 2015 11 Months N/A 100% 45 Drains; and completion of Dam's
Fund Office
Project, Phase II, accessories. The project is 100%
Katsina State completed. Commissioned and
handed over.

The Scope of work include:


Site Clearing;
Drains of various sizes & dimension
Kaltungo Gully
in different locations in the town
Erosion Control Ecological
4 December, 2015 12 Months N/A 100% 38 including Culverts and 5km Road
Works, Gombe Fund Office
improvement.
State
The project is 100% completed.
Awaiting commissioning and
handing over.
4
ECOLOGICAL FUND OFFICE
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS
CONTRACT & STATUS OF
PROJECT DATE OF USER ACCESSED BY CREATED REMARKS (PROSPECTS OF
SN PROCUREME IMPLEMENTAT
TITTLE APPROVAL AGENCY THE PROJECT SKILLED/ COMPLETION)
NT DURATION ION (%)
(%) UNSKILLED

The Scope of work include:


Gully Erosion
Site Clearing;
Control Works
Ecological Construction of Culverts; and road
5 at Veritas December, 2015 7 Months N/A 100% 38
Fund Office improvement. The project is 100%
University,
completed. Awaiting
Bwari, Abuja.
commissioning and handing over.

The Scope of work include:


(i) Site Clearing
Kwoi Erosion (ii)Earth work
and Flood (iii) 1.5km Road Improvement;
Ecological
6 Control Project February, 2017 10 Months N/A 100% 40 (iv) 5 Nos. Culverts and 725m of
Fund Office
at Jaba, Kaduna Drainages of various dimensions .
State The project is 100% completed and
awaiting commissioning and
handing over.

The Scope of works include:


i. Grubbing of the mapped site;
ii. Excavation of the mapped site;
iii. Oily Sludge treatment under
aquatic condition and clean up;
Remediation of
iv. Site construction;
Warri Refinery Ecological
7 February 2017 12 Months N/A 100% 45 v. Bio-remediation of the to its
Phase II, Delta Fund Office
natural state; and
State
vi. Restoration of the air quality
free of hydrocarbon odour.
Project is 100% completed and
awaiting commissioning and
handing over.

5
ECOLOGICAL FUND OFFICE
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM MAY 2015 TO DECEMBER 2017

FUNDS
NO OF JOBS
CONTRACT & ACCESSED STATUS OF
DATE OF USER CREATED REMARKS (PROSPECTS OF
SN PROJECT TITTLE PROCUREMEN BY THE IMPLEMENTAT
APPROVAL AGENCY SKILLED/ COMPLETION)
T DURATION PROJECT ION (%)
UNSKILLED
(%)

Construction of 1.2km Drainage


Channelization
and Channilization. Other scope
and Desilting of
includes Construction of 2
Ogbagba and Ecological
8 March, 2017 12 Months N/A 100% 45 Culvents and sand filling. 100%
Okoko Rivers in Fund Office
Completed. Awaiting
Osogbo Phase
commissioning and handing
I&II, Osun State
over.

The Scope of work include:


(i) Clear areas for access to all
locations, remote all grass and
tree within the 1 No. Canal
(ii) Remove Top soil up to a
depth not exceeding 250mm in
Mubi Flood/
soft soil for all drains, outlets
Erosion Control
structure or as may be
Works and River Ecological
9 March, 2017 11 Months N/A 80% 45 redirected by Engineers;
Yalzaram Training, Fund Office
The Status is 80% and it is on-
Phase I Adamawa
going;
State
Challenge: Work was suspended
at site by Contractor during the
raining season due to heavy
downpour.
However, the Contractor is back
on Site and work is progressing.

6
ECOLOGICAL FUND OFFICE
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS
CONTRACT & STATUS OF
DATE OF USER ACCESSED BY CREATED REMARKS (PROSPECTS OF
SN PROJECT TITTLE PROCUREME IMPLEMENTAT
APPROVAL AGENCY THE PROJECT SKILLED/ COMPLETION)
NT DURATION ION (%)
(%) UNSKILLED

The scope of work include:


i. Earth works;
ii. Concrete drains;
Erosion Control
iii. Construction of culverts;
Works at Nda, Ecological
iv. Pavement/Surfacing.
10 Nnobi and Agbor, March, 2017 Fund 7 Months N/A 90% 38
The project is 90% and work is
Idemili LGA, Office
on-going. Challenge: The
Anambra State
progress of the project was
slow due to communal issues
which has been taken care of.

The Scope of work include:


(i) Dredging of the River (2,1km)
length
(ii) De-silting of the River
Adiabo Channel
Okutikang Beach Ecological (iii) Construction of 2.75km
11 Gully Erosion March, 2017 Fund 14 Months N/A 90% 40 embankment. The Status is
Control Works, Office 90% and it is on-going.
Cross River State Challenge: Contractor not
moving with the timeline and
has received two warnings.
However, the Contractor is back
on site and work is progressing.

7
ECOLOGICAL FUND OFFICE
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM MAY 2015 TO DECEMBER 2017

NO OF
FUNDS
CONTRACT & STATUS OF JOBS REMARKS
DATE OF USER ACCESSED BY
SN PROJECT TITTLE PROCUREMENT IMPLEMENTAT CREATED (PROSPECTS OF
APPROVAL AGENCY THE PROJECT
DURATION ION (%) SKILLED/ COMPLETION)
(%)
UNSKILLED

12 Erosion/Flood March, Ecological 12 Months N/A 50% 45 The Scope of work


Control 2017 Fund include:
Project of Rice Office (i) Clear areas for
Field, Bagudu access to all
LGA, Kebbi locations, remove
State all grass and tree
within the canal
(ii)Remove Top
soil up to a depth
not exceeding
250mm in soft;
(iii) Construction
of 1.2km Access
Road.
The Status is 50%
and it is on-going.
Challenge:
Contractor is not
moving according
to timeline and
consequently has
been written two
letters of warning
in July, 2017 and
January, 2018
respectively.

8
ECOLOGICAL FUND OFFICE
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM MAY 2015 TO DECEMBER 2017

CONTRACT FUNDS NO OF
& ACCESSED STATUS OF JOBS
PROJECT DATE OF USER REMARKS (PROSPECTS OF
SN PROCUREM BY THE IMPLEMENT CREATED
TITTLE APPROVAL AGENCY COMPLETION)
ENT PROJECT ATION (%) SKILLED/
DURATION (%) UNSKILLED
The Scope of work include:
(i) Dam/Dyke Construction;
(ii) Spillway, Stilling Basin and
Bottom outlet;
(iii) 5 Nos Reinforced concrete
Culverts construction;
(iv) Canal Construction.
Erosion/Flood
The Status is 40% and it is On-
Control Project of Ecological
13 March, 2017 15 Months N/A 50% 45 going.
Rice Field, Suru Fund Office
Challenge: The flood from River
LGA, Kebbi State
Niger due to heavy downpour at the
peak of raining season forced the
Contractor to suspend works at
site for about 3 months. the
Contractor is back on site and has
submitted a new work plan which is
still within the project time frame.

The Scope of works include:


i. Rehabilitation of Sabke
Treatment Plant;
ii. Completion of Distribution
Sabke/Dutsi and
Fed. Min. of Network (Reticulation);
Mashi Water
14 March, 2017 Water 19 Months N/A 70% 45 iii. Completion of Dutsi Water
Supply Project,
Resources Supply and Irrigation Plant;
Katsina State
iv. Completion of Mashi Water
Supply and Irrigation Plant; and
v. Associated Works.
The Project is 59.9% On-going.

The Scope of work include:


Ecological (i) Site clearance Work;
Challenges at (ii) 2 Nos. Culvert and 850m length
Alex Ekwueme Ecological of Drains;
15 April, 2017 8 Months N/A 100% 45
University, Ndufu Fund Office (iii) 2.7km Pavement and Surfacing .
Alike Ikwo, Ebonyi The project is 100% completed.
State Awaiting Commissioning and
9 Handing Over.
ECOLOGICAL FUND OFFICE
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM MAY 2015 TO DECEMBER 2017

CONTRACT FUNDS NO OF
& ACCESSED STATUS OF JOBS
DATE OF USER REMARKS (PROSPECTS OF
SN PROJECT TITTLE PROCUREM BY THE IMPLEMENT CREATED
APPROVAL AGENCY COMPLETION)
ENT PROJECT ATION (%) SKILLED/
DURATION (%) UNSKILLED
The Scope of work include:
Gully Erosion
(i) Site clearance Work;
Control and
(ii) Rehabilitation of 2.9km
Flood Ecological
Access Road and Drains .
16 Improvement April, 2017 Fund 10 Months N/A 100% 40
The Status is 100% completed.
Works at Awlaw, Office
Awaiting commissioning and
Oji-River LGA,
handing over
Enugu State

Rijau, Dugge, The Scope of work include:


Dukku, (i) Site Clearance and
T/Magajiya and Earthworks;
Genu, Rijau Local Ecological (ii) 5 Nos. Culverts and 950m
17 Government April, 2017 Fund 12 Months N/A 100% 38 length of drains;
Erosion and Office (iii) Pavement and surfacing
Flood Control The Status is 100% completed.
Project, Niger It is yet to be commissioned
State and handed over.

The scope of work include: .


i. Site Clearance;
ii. Earthworks and Excavation;
Erosion Control
iii. Construction of Concrete
Works at Odo Ecological
Drains and Culverts; and
18 Alaamo, April, 2017 Fund 10 Months N/A 100% 40
iv. Road work and Pavement
Ogbomoso, Oyo Office
Construction.
State
The project is 100% completed
and awaiting commissioning
and handing over.

10
ECOLOGICAL FUND OFFICE
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM MAY 2015 TO DECEMBER 2017

CONTRACT FUNDS NO OF
& ACCESSED STATUS OF JOBS
PROJECT DATE OF USER REMARKS (PROSPECTS OF
SN PROCUREM BY THE IMPLEMENT CREATED
TITTLE APPROVAL AGENCY COMPLETION)
ENT PROJECT ATION (%) SKILLED/
DURATION (%) UNSKILLED
The Scope of work include:
(i) Site Clearance;
(ii) Construction of 150m
Erosion Control Spillway;
on the Drainage (iii) Desilting of reservoir;
Basin of Ecological (iv) Reinstatement of Dam
19 Ahmadu Bello April, 2017 Fund 8 Months N/A 95% 38 Embankment;
University, Zaria Office (v) Provision of 275m Toe
Lake/Dam, Drain;
Kaduna State (vi) Provision of intake
structure. The
Status is 95% and it is on-
going.
The Scope of work include:
Nkari Erosion (i) Site clearance Work;
Control and (ii) Rehabilitation of 2.5km
Ecological
Road Access Road and Drains .
20 April, 2017 Fund 9 Months N/A 72% 40
Improvement The Status is 72% and it is on-
Office
Works, Ini LGA, going. Communal clashes
Akwa Ibom State slowed down the progress of
work.

The Scope of work include:


Gully Erosion
(i) Construction of Drains for
and Road
flood and racketed structures
Improvement Ecological
(800m)
21 Works, April, 2017 Fund 10 Months N/A 80% 40
(ii) 1.3km Road Improvement
Nasarawa Town Office
Works .
(Phase I),
The Status is 80% completed
Nasarawa State
and it is on-going.

11
ECOLOGICAL FUND OFFICE
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM MAY 2015 TO DECEMBER 2017

CONTRACT & FUNDS NO OF JOBS


STATUS OF
DATE OF USER PROCUREME ACCESSED CREATED REMARKS (PROSPECTS OF
SN PROJECT TITTLE IMPLEMENTAT
APPROVAL AGENCY NT BY THE SKILLED/ COMPLETION)
ION (%)
DURATION PROJECT (%) UNSKILLED

The Scope of work include:


(i) Site clearance Work;
University of (ii) Concrete Work.
Calabar (iii) Construction of 1,283m
Erosion & Ecological reinforced Concrete
22 Flood Control May, 2017 Fund 9 Months N/A 100% 38 drainage;
Works, Office (iv) Construction of 6 Nos.
Calabar, Cross Concrete catchment pit. The
River State Status is 100% completed.
Awaiting commissioning
and handing over.
The Scope of work include:
(i) Clearance and
Fumigation;
(ii) Shaping and compaction
of cleared section;
(iii) Reclamation of eroded
section;
Erosion (iv) Construction of draining
Control and chambers;
Ecological
Project at (v) Construction of 350m
23 June, 2017 Fund 6 Months N/A 85% 38
State House Office
length Retaining walls
Presidential (vi) Embankment of
Villa, Abuja protection chutes, stone
pitching. The Status is 70%
and it is on-going.
Challenge: The Security
clearance from State House
delayed the early
12 commencement of the
project.
ECOLOGICAL FUND OFFICE
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM MAY 2015 TO DECEMBER 2017

CONTRACT & FUNDS NO OF JOBS


STATUS OF
PROJECT DATE OF USER PROCUREME ACCESSED CREATED REMARKS (PROSPECTS OF
SN IMPLEMENTAT
TITTLE APPROVAL AGENCY NT BY THE SKILLED/ COMPLETION)
ION (%)
DURATION PROJECT (%) UNSKILLED
Flood And
Erosion The Scope of work include:
Control Of (i) Excavation
Ecological
Damaturu- (ii) 7,250m Concrete Drains and
24 June 2017 Fund 9 Months N/A 50% 45
Balmari- 7 Nos. of Culvert .
Office
Gashua Road, The Status is 50% and it is on-
Damaturu LGA, going.
Yobe State

The Scope of work include:


Ondo (i) Site Clearance and
Township Ecological Earthworks;
November, Contractor
25 Erosion Fund 9 Months N/A 40 (ii) Culverts and drains;
2017 Mobilized
Control Works, Office (iii) Pavement and surfacing.
Ondo State Construction work is on-going.
The project is 15% Ongoing.

Erosion
Control and
Road The Scope of work include:
Improvement (i) Site clearing Work;
Ecological
Works of November, (ii) Culvert and Drains;
26 Fund 9 Months N/A 45% 40
OORA/AAYO 2017 (iii) Pavement and Surfacing .
Office
River, Oke- Construction work is on-going.
Ayo Area, The project is 45% Ongoing.
Ilesha, Osun
State

13
ECOLOGICAL FUND OFFICE

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC)


FROM MAY 2015 TO DECEMBER 2017

CONTRACT & FUNDS NO OF JOBS


STATUS OF
PROJECT DATE OF USER PROCUREME ACCESSED CREATED REMARKS (PROSPECTS OF
SN IMPLEMENTAT
TITTLE APPROVAL AGENCY NT BY THE SKILLED/ COMPLETION)
ION (%)
DURATION PROJECT (%) UNSKILLED

Project
Development
The Scope of work include:
Institute
(i) Excavation
Enugu
Ecologica (ii) 765m Concrete Drains
(PRODA) November,
27 l Fund 8 Months N/A 50% 40 and 5 Nos. Culvert.
Federal 2017
Office Construction work is on-
Ministry of
going.
Science &
The project is 50% Ongoing.
Technology,
Enugu State

Gandu,
The Scope of work include:
Tukuntawa
(i)Site clearance and earth
and Zoo Road Ecologica
November, Contractor work
28 Erosion and l Fund 6 Months N/A 40
2017 Mobilized (ii) Culverts and drains;
Flood Control Office
(iii) Pavement and surfacing.
Project, Kano
The project is 15% Ongoing.
State

14
ECOLOGICAL FUND OFFICE
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM MAY 2015 TO DECEMBER 2017

CONTRACT FUNDS NO OF
& ACCESSED STATUS OF JOBS
PROJECT DATE OF USER REMARKS (PROSPECTS OF
SN PROCUREM BY THE IMPLEMENT CREATED
TITTLE APPROVAL AGENCY COMPLETION)
ENT PROJECT ATION (%) SKILLED/
DURATION (%) UNSKILLED

The Scope of work include:


(i)Construction of Old
Cemetery Drains;
Tundun
(ii)Construction of new
Magayaki/Ce
Cemetery Drains;
metery/ Gully
(iii) Construction of Drains
Erosion and Ecologica
November, Contractor along Dallatu Road.
29 Flood l Fund 6 Months N/A 40
2017 Mobilized (iv)Repair to completed
Control, Office
section of main drain;
Sokoto
(v)Extending of drains from
South LGA,
other roads to main drains
Sokoto State
Construction of main drain
at Magayaki,
The project is 15% Ongoing.

The Scope of work include:


i. 100m Shoreline
Shoreline protection; and
Ecologica
Protection, November, ii sand filling.
30 l Fund 8 Months N/A 70% 45
Alebiri, 2017 Dredging Machine moved to
Office
Bayelsa State site and work has began in
earnest.
The project is 70% Ongoing.

15
ECOLOGICAL FUND OFFICE (EFO) PROJECTS
BELOW FEDERAL EXECUTIVE COUNCIL (FEC)
THRESHHOLD FROM MAY 2015 TO DECEMBER 2017
ARE IN ANNEX (I)

Total Numbers of Projects : 64


Numbers of Completed Projects: 55
Numbers of Ongoing Projects: 9

JOB CREATION
➢ Skilled Jobs 357
➢ Unskilled Jobs 1,350

16
ESTIMATED NUMBER OF JOBS CREATED BY EFO
PROJECTS FROM MAY 2015 TO DECEMBER 2017

▪ Though the projects are short termed but during the period, several
jobs were created
▪ The following are the types of Skilled and Unskilled Employees
employed by Contractors/Consultants;

Skilled Unskilled
➢ Civil Engineers Labourers
➢ Structural Engineers
➢ Highway Engineers
➢ Water Engineers
➢ Mechanical/Electrical Engineers
➢ Technicians
➢ Welders
➢ Carpenters
➢ Masons
➢ Painters

17
▪ In addition, these projects also impacted lives in the Communities in
many ways;
➢ Increase in economic productivity
➢ Safety of lives and properties
➢ Improvement in the standard of living
➢ Access to Farmlands and Markets
➢ Reduction in prices of food items
➢ Increased Inter-Communal relationship and peace
➢ Reduction in cost of transportation
➢ Federal Government’s presence being felt
➢ Improved security within the Communities
➢ Value of properties improved/enhanced
➢ Communities have extended appreciation to Federal
Government

▪ For Small and Medium size projects, about 90 lives are impacted
which translate to about 5,760 lives in 64 projects executed
▪ For Bigger projects, about 120 lives are impacted which translate to
about 3,600 lives in 30 projects executed

18
▪ About 8,820 lives were directly impacted and empowered
ESTIMATED NUMBER OF JOBS CREATED BY EFO
PROJECTS FROM MAY 2015 TO DECEMBER 2017

▪ Out of 64 projects which fall within the EFO Tenders Board


approval limit, about 357 skilled employees were engaged
▪ The Unskilled labours were about 1,409 Labourers

▪ Out of 30 projects which fall within the Federal Executive


Council (FEC) approval, 270 skilled employees were engaged
The Unskilled labour were about 1,350

▪ 3,386 Professionals and Unskilled labour were created

19
ESTIMATED NUMBER OF JOBS CREATED BY EFO
PROJECTS FROM MAY 2015 TO DECEMBER 2017

Nos of Jobs Created by EFO Projects from May, 2015 to Dec.,


2017
Key: 2759
Skilled Employees
Civil Engineers
Structural Engineers
Highway Engineers
Water Engineers
Mechanical Engineers
Technicians
Welders
Carpenters
Painters
Masons

Unskilled Labour
Labourers

627

20
Skilled Unskilled
2.2 CABINET AFFAIRS OFFICE
PROGRESS REPORT ON THE IMPLEMENTATION OF THE DECISIONS OF THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM THE CABINET AFFAIRS OFFICE (CAO)

S/N MEETING OF REFERENCE NUMBER AND IMPLEMENTING DECISION TAKEN IN COUNCIL DETAILS OF ACTION
FEC AND SUBJECT OF MEMORANDUM MDAS TAKEN
DATE
1. EC(2015)14TH AOB: CAO Conclusion 8 i. Implemented
MEETING OF ii. Report on the
7 DECEMBER, Residential Accommodation for i. The President directed that Residential
2015 Ministers proposals be made to address Accommodation for
Ministers’ accommodation Ministers has been
challenge approved by the
Federal Executive
Council and
awaiting
implementation

2. EC(2016) 3RD 1. EC(2016)3: Report of the Cabinet CAO Conclusion 4 i. Cabinet Committee
MEETING of Committee on Nigeria’s accession to Assignment
17 the (Budapest) Convention on i. Approved the recommendations completed and
FEBRUARY, Cybercrime, (CET NO.185). of the Committee as highlighted in Report submitted
2016. paragraph 9 (i to iii) of the
memorandum

3 EC(2017)12TH 1. EC(2017)78: Approval for the Report of CAO Conclusion 5 Cabinet Committee
MEETING OF the Cabinet Committee to Resolve the 1. Approved the following Assignment
29 MARCH , Issue of Ministerial oversight of the ICT recommendations of the Cabinet completed and
2017 Sector in Nigeria Committee: Report submitted
Section 148(1) of the Constitution
gives the President the power to
assign responsibilities and mandates
to Ministers and this discretion cannot
be constrained by any existing laws,

21
CABINET AFFAIRS OFFICE
PROGRESS REPORT ON THE IMPLEMENTATION OF THE DECISIONS OF THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM THE CABINET AFFAIRS OFFICE (CAO)

President to direct the Business of Government


should be accepted as the basis of authority for the
assignment of mandates to MDAs.

The mandates of MDAs are determined by the


direction of Government Policy and Extant Laws
should be reviewed to support the implementation
of Government policy. The Laws regulating the
operations of NITDA, NIGCOMSAT Ltd. and Galaxy
Backbone Ltd should be reviewed and brought in
line with the policy intentions of Government

The Policy of Government on the mandates of the


Ministries of Science & Technology and
Communications is as stipulated in the extant
circular conveying the approved responsibilities,
structure and parastatals of the two Ministries
which is SGF Circular ref. No. 59386/IV/760 of 15
August, 2011. This Circular should be re-issued by
this Administration for the avoidance of doubt.

The mandate to drive information Technology


given to the Ministry of Communications was a
deliberate decision of Government to create a
specialized sector to leverage the emerging
potentials in ICT and this should be kept separate
from the MS&T, in accordance with global best
practices and the wishes of ICT professional
bodies in Nigeria.

The Ministry of Communications, which is the


rightful agency in which the Presidential Council
proposed on e-Government is to be domiciled,
should review the composition of the proposed
Council and include all critical stakeholders before
resubmitting the memorandum to Council.

22
CABINET AFFAIRS OFFICE
PROGRESS REPORT ON THE IMPLEMENTATION OF THE DECISIONS OF THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM THE CABINET AFFAIRS OFFICE (CAO)

The Federal MS&T presently has oversight of 17


parastatals, which are mostly research Agencies. It
is not optimal for its span of control and effective
supervision to further increase the number of
parastatals under it and therefore, the status quo
should be maintained.

There is need for greater collaboration and


harmonious working relationship between the
Ministries of Communications and Science &
Technology to ensure that the end result of
innovation is applied to develop the ICT sector.

The full functional review of the mandates of all


Ministries should be immediately undertaken and
the report presented to the Federal Executive
Council for consideration and approval.

Since the Committee did not find any reason to


support the objection by the Minister

of Science & Technology that the subjects of the


memoranda revolve around the statutory mandates
of that Ministry, the Minister of Communications
should represent the following two memoranda for
Council’s consideration.

the Nigeria e-Government Master-Plan 2016-2020.


the Nigeria ICT Sector Roadmap 2016-2019.

23
CABINET AFFAIRS OFFICE
PROGRESS REPORT ON THE IMPLEMENTATION OF THE DECISIONS OF THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM THE CABINET AFFAIRS OFFICE (CAO)
4 EC(2017)14TH AOB: CAO Conclusion 8(ix) i. Completed
. MEETING OF ii. Directory of
12 APRIL, Re-activation of the Website of i. Directed that every Ministry functional official
2017 Ministries should submit to Cabinet Affairs websites of MDAs
Office the upgrade on the status already compiled
of their official websites, by the Cabinet
including the names of their Affairs Office with
appropriate Desk Officers, for the Desk Officers
presentation to Council. also listed

5 EC(2017)17TH AOB: CAO Conclusion 13(xi) Complied with


. MEETING OF
10 MAY, 2017 Need to Adhere to the Rules Guiding i. Directed that, henceforth,
the Processing of Council memoranda to be considered at
Memoranda Council meetings must be
circulated on or before Friday
preceding the meeting

6 EC(2017)30TH 1. EC(2017)186: Approval for the CAO Conclusion 8 Complied with


. MEETING OF 9 Award of Contract for the Engineering
AUGUST, 2017 Procurement and Construction of the i. Directed the Cabinet Affairs Office
3,050mw Mambilla Hydroelectric to convey the directive of Council
Power Project, Gembu, Taraba State to the AGF/MoJ to enable him
propose a suitable date for the
meeting with the Minister of Power,
Works and Housing within a few
days to resolve the likely legal
issues that may arise on the matter

24
CABINET AFFAIRS OFFICE
PROGRESS REPORT ON THE IMPLEMENTATION OF THE DECISIONS OF THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM THE CABINET AFFAIRS OFFICE (CAO)

7 EC(2017)33RD 1. EC(2017)184: Approval for the CAO Conclusion 5 i. Cabinet committee


. MEETING OF passage into law of the: constituted and
13 Constitution (alteration) Bill, 2017: i. Stepped down Memorandum assignment is on-
SEPTEMBER, Electoral Act (Amendment) Bill, EC(2017)184 to enable the Vice going
2017 2017; Political Parties and President and the Attorney
Electoral Offences Commission General of the Federation &
Bill, 2017; and constituency Minister of Justice to constitute
delimitation centre bill, 2017 a Cabinet Committee that
would examine the Bills, with a
view to addressing the issues
raised by the Vice president,
and submit a Report to Council.
8 EC(2017)35TH 1. EC(2017)180: Approval of the CAO Conclusion 4 i. Cabinet committee
. MEETING OF Draft National Policy on Internally constituted and
27 Displaced Persons In Nigeria, 2017 i. Stepped down Memorandum assignment is on-
SEPTEMBER, EC(2017)180 on the Draft going
2017 National Policy on Internally
Displaced Persons in Nigeria
2017, for members to further
study the policy document and to
enable the National Commission
for Refugees, Migrants &
Internally Displaced Persons to
address the issues raised by
members and re-present to
Council within 2 weeks.

i. Directed the Ministry of Interior to


put in place mechanisms for
effective monitoring of the
activities of all organisations
assisting the IDPs, and that a
Committee should be set up to
25 check the activities of those
organisations
CABINET AFFAIRS OFFICE
9. 2. EC(2017)209: Approval for the CAO Conclusion 5 i. Cabinet committee
Report And Recommendations of the constituted and
Inter-Ministerial Working Committee i. Stepped down Memorandum assignment is on-
on the Status of Nigeria’s Membership EC(2017)209 to enable members to going
of International Organisations and aggregate their views on the Report
Associated Financial Obligations and re-present same to Council
within 2 weeks.

i. Directed the Minister of Finance to


include all the external statutory
obligations in the budget for onward
transmission to the National
Assembly (NASS) for approval, to
avoid the embarrassment which the
non-payment of Nigeria’s assessed
financial obligations to the IOs might
cause the country

10 EC(2017)37TH 1. EC(2017)228: Approval of the Report CAO Conclusion 4 i. The White Paper
. MEETING OF 11 of the Technical Committee on Industrial Drafting Committee is
OCTOBER, 2017 Relations Matters in the Federal Public i. Directed the Acting Secretary to the chaired by Minister of
Service Government of the Federation to Labour & Employment.
constitute a White Paper Drafting
Committee to examine the Report of i. The assignment is on-
the Technical Committee on Industrial going and the
Relations Matters in the Federal Public Committee would soon
Service and submit its report back to Council.
recommendations to Council.

i. Directed members to critically study the


Report and submit their inputs to the
Office of the Secretary to the
Government of the Federation.

i. Directed that the Yayale Ahmed


Committee Report be circulated to
members for their information and
guidance

26
CABINET AFFAIRS OFFICE
PROGRESS REPORT ON THE IMPLEMENTATION OF THE DECISIONS OF THE FEDERAL EXECUTIVE COUNCIL (FEC)
FROM THE CABINET AFFAIRS OFFICE (CAO)

11 EC(2017)44TH AOB: CAO Conclusion 9(vii) i. Complied with


MEETING OF ii. Actionable
29 Need to modify the Reporting of i. Directed the Council Secretariat decisions/directive
NOVEMBER, Council Discussions Under any to modify its rendition of AOB s are now reflected
2017 Other Business (AOB) in the discussions to capture under AOB
Conclusions, to Reflect Actionable actionable decisions and
Decisions/Directives directives of Council as
appropriate.

27
2.3 FEDERAL ROAD SAFETY CORPS (FRSC)
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE
FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE FEDERAL EXECUTIVE COUNCIL


FROM 2015 TO DATE
FUNDS
CONTRACT & STATUS OF REMARKS
DATE OF USER ACCESSED BY
S/N PROJECT TITLE PROCUREMENT IMPLEMENTATION (PROSPECTS OF
APPROVAL AGENCY THE PROJECT
DURATION (%) COMPLETION)
(%)

APPROVAL FOR THE AWARD


OF CONTRACT FOR THE VEHICLES
1 DIRECT PROCUREMENT OF 23/11/2016 FRSC 30 DAYS 100 100 DISTRIBUTED AS
OPERATIONAL VEHICLES ATTACHED
FOR THE FEDERAL ROAD
SAFETY CORPS

28
LIST OF FEDERAL ROAD SAFETY CORPS VEHICLES ACQUIRED IN DECEMBER 2016

DATE OF
NEW REG
S/N MAKE/TYPE COMMAND CHASSIS NO PURCHASE/ CONDITION PURPOSE
NO
ALLOCATION

1 IVM P/UP A01 459 RS RSHQ TSD FKZSR31B2ET110079 DEC 2016 FUNCTIONAL PATROL

2 IVM P/UP A01 542 RS RS 5.14 IGARA UNIT FKZSR31B2ET030051 DEC 2016 FUNCTIONAL PATROL

3 IVM P/UP A01 79 RS RS 6.2 A ODUKPANI OUTPOST FKZSR31B2ET110039 DEC 2016 FUNCTIONAL PATROL

4 IVM P/UP A01 842 RS RS 8.36 OGORIMAGONGO UNIT FKZSR31B2ET030160 DEC 2016 FUNCTIONAL PATROL

5 IVM P/UP A01 868 RS RS 4.14 BUKURU UNIT FKZSR31B2ET110021 DEC 2016 FUNCTIONAL PATROL

6 IVM P/UP A01 869 RS RS 7.18 YANGOJI UNIT FKZSR31B2ET030022 DEC 2016 FUNCTIONAL PATROL

7 IVM P/UP A01 870 RS RS 5.12 BENIN TOLL GATE UNIT FKZSR31B2ET110128 DEC 2016 FUNCTIONAL PATROL

8 IVM P/UP A01 887 RS RS 10.31 TALATA MAFARA UNIT FKZSR31B2ET110093 DEC 2016 FUNCTIONAL PATROL

9 IVM P/UP A01 919 RS RS 8.37 OKENE UNIT FKZSR31B2ET030021 DEC 2016 FUNCTIONAL PATROL

10 IVM P/UP A01 920 RS RS 2.28 A ILARO OUTPOST FKZSR31B2ET030091 DEC 2016 FUNCTIONAL PATROL

11 IVM P/UP A01 921 RS RS 2.23 A IBAFO OUTPOST FKZSR31B2ET110092 DEC 2016 FUNCTIONAL PATROL

12 IVM P/UP A01 922 RS RS 2.23 MOWE UNIT FKZSR31B2ET030095 DEC 2016 FUNCTIONAL PATROL

13 IVM P/UP A01 923 RS RS 7.111 B BWARI OUTPOST FKZSR31B2ET030132 DEC 2016 FUNCTIONAL PATROL

14 IVM P/UP A01 924 RS RS 6.13 ISIOKPO UNIT FKZSR31B2ET110013 DEC 2016 FUNCTIONAL PATROL

15 IVM P/UP A01 925 RS RS 12.21 BIU UNIT FKZSR31B2ET110057 DEC 2016 FUNCTIONAL PATROL

16 IVM P/UP A01 926 RS RS 7.11 GWAGWALADA UNIT FKZSR31B2ET110118 DEC 2016 FUNCTIONAL PATROL

17 IVM P/UP A01 927 RS RS 5.21 WARRI UNIT FKZSR31B2ET110085 DEC 2016 FUNCTIONAL PATROL

18 IVM P/UP A01 928 RS RSHQ TSD FKZSR31B2ET030172 DEC 2016 FUNCTIONAL PATROL

29
LIST OF FEDERAL ROAD SAFETY CORPS VEHICLES ACQUIRED IN DECEMBER 2016
19 IVM P/UP A01 929 RS RS 7.26 SABON WUSE UNIT FKZSR31B2ET030066 DEC 2016 FUNCTIONAL PATROL

20 IVM P/UP A01 930 RS RS 2.114 WHARF UNIT FKZSR31B2ET110162 DEC 2016 FUNCTIONAL PATROL

21 IVM P/UP A01 931 RS RS 11.37 KISI UNIT FKZSR31B2ET110129 DEC 2016 FUNCTIONAL PATROL

22 IVM P/UP A01 932 RS RS 7.1 FCT SECTOR FKZSR31B2ET030127 DEC 2016 FUNCTIONAL PATROL

23 IVM P/UP A01 933 RS RS 7.12 ABAJI UNIT FKZSR31B2ET030116 DEC 2016 FUNCTIONAL PATROL

24 IVM P/UP A01 934 RS RS 8.34 ZARIAGI FKZSR31B2ET110105 DEC 2016 FUNCTIONAL PATROL

25 IVM P/UP A01 935 RS RS 9.32 KM 78 ABA UNIT FKZSR31B2ET110005 DEC 2016 FUNCTIONAL PATROL

26 IVM P/UP A01 936 RS RS 9.23 NKALAGU FKZSR31B2ET110043 DEC 2016 FUNCTIONAL PATROL

27 IVM P/UP A01 937 RS RS 5.16 UWAN-ESIGIE UNIT FKZSR31B2ET030019 DEC 2016 FUNCTIONAL PATROL

28 IVM P/UP A01 938 RS RS 6.4 BAYELSA SECTOR FKZSR31B2ET110178 DEC 2016 FUNCTIONAL PATROL

29 IVM P/UP A01 939 RS RS 11.33 APATA UNIT FKZSR31B2ET110112 DEC 2016 FUNCTIONAL PATROL

30 IVM P/UP A01 950 RS RS 7.26 A TAFA OUTPOST FKZSR31B2ET110031 DEC 2016 FUNCTIONAL PATROL

31 IVM P/UP A01 951 RS RS 8.12 A ODO-OWA OUTPOST FKZSR31B2ET110025 DEC 2016 FUNCTIONAL PATROL

32 IVM P/UP A01 952 RS RS 8.1 A IDOFIAN OUTPOST FKZSR31B2ET110154 DEC 2016 FUNCTIONAL PATROL

33 IVM P/UP A01 953 RS RS 2.21A GATE 3 OUTPOST IJEBU-ODE FKZSR31B2ET030060 DEC 2016 FUNCTIONAL PATROL

34 IVM P/UP A01 954 RS RS 1.42 GUMEL UNIT FKZSR31B2ET110158 DEC 2016 FUNCTIONAL PATROL

35 IVM P/UP A01 955 RS RSHQ TSD COBRA FKZSR31B2ET030118 DEC 2016 FUNCTIONAL PATROL

36 IVM P/UP A01 956 RS RS 11.21 A AJEBANDELE OUTPOST FKZSR31B2ET030143 DEC 2016 FUNCTIONAL PATROL

37 IVM P/UP A01 957 RS RS 11.14 IKIRUN FKZSR31B2ET110003 DEC 2016 FUNCTIONAL PATROL

38 IVM P/UP A01 958 RS RS 10.2A YAURI OUTPOST FKZSR31B2ET110026 DEC 2016 FUNCTIONAL PATROL

39 IVM P/UP A01 959 RS RS 11.16 GBONGAN UNIT FKZSR31B2ET110161 DEC 2016 FUNCTIONAL PATROL

30 40 IVM P/UP A01 960 RS RS 11.24 ASEJERE UNIT FKZSR31B2ET110087 DEC 2016 FUNCTIONAL PATROL
LIST OF FEDERAL ROAD SAFETY CORPS VEHICLES ACQUIRED IN DECEMBER 2016
1 PGT 301 ACCESS 06-04 RS RSHQ MVA (HEAD PLANT GWA/LADA) VF3DDHMYBDJ847434 DEC 2016 FUNCTIONAL ADMIN

2 PGT 301 ACCESS 24-04 RS RS 2.0 LAGOS ZONAL COMMAND VF3DDHMYBEJ699925 DEC 2016 FUNCTIONAL ADMIN

3 PGT 301 ACCESS 32-04 RS RS 10.2 KEBBI SECTOR VF3DDHMYBDJ877755 DEC 2016 FUNCTIONAL ADMIN

4 PGT 301 ACCESS 37-04 RS RS 12.3 YOBE SECTOR VF3DDHMYBFJ546682 DEC 2016 FUNCTIONAL ADMIN

5 PGT 301 ACCESS 52-04 RS RSHQ MVA (HOS PRINT FARM) VF3DDHMYBEJ549807 DEC 2016 FUNCTIONAL ADMIN

6 PGT 301 ACCESS 55-04 RS RS 4.3 NASARAWA SECTOR COMDR VF3DDHMYBFJ546669 DEC 2016 FUNCTIONAL ADMIN

7 PGT 301 ACCESS 57-04 RS RS 12.2 BORNO SECTOR VF3DDHMYBDJ877759 DEC 2016 FUNCTIONAL ADMIN

8 PGT 301 ACCESS 59-04 RS RS 10.1 SOKOTO SECTOR CMDR VF3DDHMYBEJ546155 DEC 2016 FUNCTIONAL ADMIN

9 PGT 301 ACCESS 60-04 RS RS 12.1 BAUCHI SECTOR VF3DDHMYBDJ877762 DEC 2016 FUNCTIONAL PATROL

10 PGT 301 ACCESS 61-04 RS RS 11.1 OSUN SECTOR VF3DDHMYBDJ819994 DEC 2016 FUNCTIONAL ADMIN

11 PGT 301 ACCESS 64-04 RS RSHQ TRG CMDT JOS VF3DDHMYBDJ887148 DEC 2016 FUNCTIONAL ADMIN

12 PGT 301 ACCESS 65-04 RS RS 10.3 ZAMFARA SECTOR CMDR VF3DDHMYBDJ877761 DEC 2016 FUNCTIONAL ADMIN

13 PGT 301 ACCESS 72-04 RS RS 9.3 ABIA SECTOR VF3DDHMYBDJ887149 DEC 2016 FUNCTIONAL ADMIN

14 PGT 301 ACCESS 73-04 RS RS 8.2 EKITI SECTOR VF3DDHMYBFJ546657 DEC 2016 FUNCTIONAL ADMIN

15 PGT 301 ACCESS 85-04 RS RS 7.1 FCT SECTOR VF3DDHMYBFJ533271 DEC 2016 FUNCTIONAL ADMIN

16 PGT 301 ACCESS 93-04 RS RS 5.3 HEAD AWKA PLANT VF3DDHMYBDJ805296 DEC 2016 FUNCTIONAL ADMIN

17 PGT 301 ACCESS 98-04 RS. RS 8.3 KOGI SECTOR VF3DDHMYBFJ539979 DEC 2016 FUNCTIONAL ADMIN

18 PGT 301 ACCESS 99-04 RS RSHQ PIO VF3DDHMYBFJ546684 DEC 2016 FUNCTIONAL ADMIN

19 PGT 301 ACCESS A01 940 RS RS 7.111 A GWARIMPA OUT POST VF3DDHMYBFJ546663 DEC 2016 FUNCTIONAL PATROL

20 PGT 301 ACCESS A01 941 RS RS 11.13 IPETU-IJESHA VF3DDHMYBDJ881229 DEC 2016 FUNCTIONAL PATROL

21 PGT 301 ACCESS A01 943 RS RS 11.35 EGBEDA UNIT VF3DDHMYBDJ881230 DEC 2016 FUNCTIONAL PATROL

22 PGT 301 ACCESS A01 945 RS RS 7.11 GWAGWALADA UNIT VF3DDHMYBFJ546674 DEC 2016 FUNCTIONAL PATROL

23 PGT 301 ACCESS A01 946 RS RSHQ TSD VF3DDHMYBDJ864528 DEC 2016 FUNCTIONAL ADMIN

24 PGT 301 ACCESS A01 947 RS RS 7.110 LUGBE UNIT VF3DDHMYBDJ805295 DEC 2016 FUNCTIONAL PATROL

25 PGT 301 ACCESS A01 948 RS RS 11.12 ILESHA VF3DDHMYBDJ873928 DEC 2016 FUNCTIONAL PATROL

26 PGT 301 ACCESS A01 949 RS RS 7.1 A MPAPE OUTPOST VF3DDHMYBFJ546675 DEC 2016 FUNCTIONAL PATROL

27 PGT 301 ACCESS HQ 96 RS RSHQ TSD VF3DDHMYBFJ546696 DEC 2016 FUNCTIONAL ADMIN

SUMMARY:
IVM PICK -UP = 40

PGT 301 ACCESS = 27


31
2.4 NATIONAL HAJJ COMMISSION OF NIGERIA (NAHCON)
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE
FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017
S/NO PROJECT COST OF DATE OF USER CONTRACT FUNDS STATUS OF REMARKS
TITTLE PROJECT APPROVAL AGENCY & ACCESSD IMPLEMENT (PROSPECT
(N) PROCUREM BY THE ATION (%) OF
ENT PROJECT COMPLETION)
DURATION
1. Acquisition, . 8TH NOVEMBER, National Hajj 2017 - 2019 ▪ Partly 75% ▪ Awaiting the
and 2017. Commission of funded Completion Balance to be
Renovation of Nigeria from (Properties returned to
Acquired (HAHCON) Savings purchased. Hajj Account.
Properties, from Un-renovated) ▪ The Funds
Furnishing and Service required for
Equiping the Charges to renovation
Properties, Pilgrims and
and Relocation and Capital Furnishing of
of Office to the Budget the new Office
newly Appropriati has been
Acquired on Act of included in
Properties 2017. the 2018
named Metrol ▪ The sum of Budget
Plaza, at Plot N1.5B was Proposal
991/992 raised from
Mailari Street, Hajj
Central Savings
Business over the
District, FCT, past years;
Abuja. ▪ Balance
was to be
funded
from Year
2017
Budget
Appropriati
on out of
which 50%
had been
32 released.
2.5 NATIONAL PENSION COMMISSION
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE
FEDERAL EXECUTIVE COUNCIL FROM MAY 2015 TO DECEMBER 2017

CONTRACT & FUNDS ACCESSED STATUS OF REMARKS


S/N PROJECT COST OF PROJECT DATE OF USER AGENCY PROCUREME BY THE PROJECT IMPLEMENTATIO (PROSPECTS OF
TITLE APPROVAL NT DURATION (%) N (%) COMPLETION)

1 Direct $539,130.72@N3 11/1/2017 National Within five 33.33% 70% Deployment of


Procurement 04.75/$ (approved Pension (5) working (Deployment of Licenses as at
and = by Federal Commission days from (N54,766,695.64) Lisenses) February 2018:
Acquisition of N164,300,086.92 Executive the
1. Microsoft
Microsoft to be paid in 3 no Council) execution of Office Plus
Office 365 equal instalment contract Professional
Enterprise over a period of 3 agreement. 2016
(400 Licenses)
License years A license is
2. SharePoint
given Server
Enterprise
2016
(1 Server)
3. Project
Professional
2013
(5 Licenses)
4. Windows
Server 2016
(5 Licenses)
5. SQL Server
Standard Core
2017
(1 Server)
6. Windows 10

33
2.6 NATIONAL POPULATION COMMISSION
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE
FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

CONTRACT & FUNDS ACCESSED STATUS OF REMARKS


S/ PROJECT TITLE DATE OF USER AGENCY PROCUREME BY THE PROJECT IMPLEMENT (PROSPECTS
N APPROVAL NT DURATION (%) ATION (%) OF
COMPLETION)

1 Direct 17/05/2017 National 30 Days N308,480,000.00 100% Completed


Procurement of Population
Five Toyota Land Commission
Cruiser Jeeps;

One Toyota Hilux


Double Cabin
Pick-Up

One Toyota
Coaster Bus for
Operational uses.

34
2.7 ECONOMIC AND FINANCIAL CRIMES COMMSSION
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE
FEDERAL EXECUTIVE COUNCIL (FEC) FROM MAY 2015 TO DECEMBER 2017

CONTRACT & FUNDS STATUS OF REMARKS


S/N PROJECT TITLE DATE OF USER AGENCY PROCUREME ACCESSED BY IMPLEMENTATION (PROSPECTS
APPROVAL NT DURATION THE PROJECT (%) OF
(%) COMPLETION)

1 Award of 12/10/2016 EFCC 100% Completed


Contracts for the
Direct
Procurement of
Operational
Vehicles for the
Economic and
Financial Crimes
Commission
(EFCC)

2 Award of Contract 26/4/2017 EFCC 80% On-going


for revised
estimated total
cost for the
Contract for the
Completion of the
On-going
Construction of
the EFCC
Corporate
Headquarters
Office, Abuja

3 Award of Contract 6/12/2017 EFCC 8 Weeks 0% On-going


for the Provision of
Internet
Broadband and
Firewall for the
EFCC
Headquarters and
all its Zonal
Offices

35
PICTORIAL EVIDENCES OF SOME OF
THE APPROVED FEDERAL EXECUTIVE
COUNCIL (FEC) PROJECTS FROM
MAY 2015 TO DECEMBER 2017

36
ECOLOGICAL FUND OFFICE
UNIVERSITY OF CALABAR EROSION & FLOOD CONTROL WORKS, CALABAR, CROSS RIVER STATE

BEFORE

Above represents sample of parts of the ecological site before the commencement of work
37
UNIVERSITY OF CALABAR EROSION & FLOOD CONTROL WORKS, CALABAR, CROSS RIVER STATE

DURING

AFTER

38 Above represents sample of parts of the on-going work at site


UNIVERSITY OF CALABAR EROSION & FLOOD CONTROL WORKS, CALABAR, CROSS RIVER STATE

AFTER

39
Above represents sample of parts of completed work
REMEDIATION OF THE HYDROCARBON SLUDGE AT THE WARRI REFINERY AND
PETROCHEMICAL COMPANY PHASE II, WARRI SOUTH LGA, DELTA STATE.

BEFORE DURING

Above represents sample of parts of the ecological sites before the Above represents sample of parts of the on-going work at the site
commencement of work

AFTER

40 Above represents sample of parts of the completed work


EROSION CONTROL IN AWLAW TOWN, OJI RIVER L.G.A. ENUGU STATE

DURING

BEFORE

AFTER

41
Above represents sample of parts of the ecological site before the commencement of work
EROSION CONTROL IN AWLAW TOWN, OJI RIVER L.G.A. ENUGU STATE

DURING

42 Above represents sample of parts of the on-going work at the site


EROSION CONTROL IN AWLAW TOWN, OJI RIVER L.G.A. ENUGU STATE

AFTER

43
Above represents sample of parts of the completed work
CHANNELISATION AND DE-SILTING OF OKOKO AND OGBAGBA RIVERS IN OSOGBO, OSUN STATE

BEFORE DURING

Above represents sample of parts of the ecological sites before Above represents sample of parts of the on-going work at the
commencement of work site

AFTER

44
Above represents sample of parts of the completed work
RIJAU, DUGGE, DUKKU, T/MAGAJIYA AND GENU EROSION AND FLOOD CONTROL, RIJAU LGA, NIGER STATE

BEFORE

45
Above represents sample of parts of the ecological site before the commencement of work
RIJAU, DUGGE, DUKKU, T/MAGAJIYA AND GENU EROSION AND FLOOD CONTROL, RIJAU LGA, NIGER STATE

DURING

46
Above represents sample of parts of the on-going work at the site
RIJAU, DUGGE, DUKKU, T/MAGAJIYA AND GENU EROSION AND FLOOD CONTROL, RIJAU LGA, NIGER
STATE

AFTER

47
Above represents sample of parts of the completed work
DAURA TOWNSHIP EROSION CONTROL, PHASE I, DAURA, KATSINA STATE

DURING

48 Above represents sample of parts of the on-going work at the site


DAURA TOWNSHIP EROSION CONTROL, PHASE I, DAURA, KATSINA STATE

AFTER

49 Above represents sample of parts of the completed work


DAURA TOWNSHIP EROSION AND FLOOD CONTROL WORKS, PHASE 2, KATSINA STATE

COMMISSIONED AND HANDED OVER

50
Above represents sample of parts of the completed work
KWOI EROSION AND FLOOD CONTROL WORKS, JABA, KADUNA STATE

BEFORE

51
Above represents sample of parts of the ecological site before the commencement of work
KWOI EROSION AND FLOOD CONTROL WORKS, JABA, KADUNA STATE

DURING

52 Above represents sample of parts of the on-going work at the site


KWOI EROSION AND FLOOD CONTROL WORKS, JABA, KADUNA STATE

AFTER

53 Above represents sample of parts of the completed work


SABKE/DUTSI AND MASHI WATER SUPPLY PROJECT, KATSINA STATE AWAITING COMMISSIONING

ON-GOING

54 Above represents sample of parts of the on-going work at the site


EROSION CONTROL WORKS AT ALEX EKWUEME UNIVERSITY, NDUFU ALIKE IKWO, EBONYI STATE

BEFORE DURING

AFTER

55
Above represents sample of parts of the ecological site before the commencement of work
EROSION CONTROL WORKS AT ALEX EKWUEME UNIVERSITY, NDUFU ALIKE IKWO, EBONYI STATE

DURING

56
Above represents sample of parts of the on-going work at the site
EROSION CONTROL WORKS AT ALEX EKWUEME UNIVERSITY, NDUFU ALIKE IKWO, EBONYI STATE

AFTER

57
Above represents sample of parts of the completed work
EROSION CONTROL WORKS AT ODO ALAAMO, OGBOMOSO, OYO STATE

BEFORE DURING

Above represents sample of parts of the ecological site before the Above represents sample of parts of the on-going work at the site
commencement of work

AFTER

58 Above represents sample of parts of the completed work


FLOOD AND EROSION CONTROL WORKS , DAMATURU – BALMARI – GASHUA ROAD, DAMATURU LGA,
YOBE STATE

DURING

BEFORE

59
Above represents sample of parts of the ecological site before the commencement of work
FLOOD AND EROSION CONTROL WORKS , DAMATURU – BALMARI – GASHUA ROAD, DAMATURU LGA,
YOBE STATE

DURING

60
Above represents sample of parts of the on-going work at the site
FLOOD AND EROSION CONTROL WORKS , DAMATURU – BALMARI – GASHUA ROAD, DAMATURU LGA,
YOBE STATE

ON-GOING

61
Above represents sample of parts of the on-going work at the site
GULLY EROSION CONTROL WORKS AT VERITAS UNIVERSITY, BWARI, ABUJA

BEFORE DURING

Above represents sample of parts of the ecological site before the Above represents sample of parts of the on-going work at the site
commencement of work

AFTER

62
Above represents sample of parts of the completed work
EROSION AND FLOOD CONTROL WORKS AT PROJECT DEVELOPMENT
INSTUTUTE (PRODA), FEDERAL MINISTRY OF SCIENCE & TECHNOLOGY
ENUGU STATE
BEFORE

63
Above represents sample of parts of the ecological site before the commencement of work
EROSION AND FLOOD CONTROL WORKS AT PROJECT DEVELOPMENT
INSTUTUTE (PRODA), FEDERAL MINISTRY OF SCIENCE & TECHNOLOGY
ENUGU STATE

ON-GOING

64
Above represents sample of parts of the on-going work at the site
DISILTING OF OGBAGBA AND OKOKO RIVERS, OSHOGBO, PHASE I & II, OSUN STATE

BEFORE

65
Above represents sample of parts of the ecological site before the commencement of work
DISILTING OF OGBAGBA AND OKOKO RIVERS, OSHOGBO, PHASE I & II, OSUN STATE

DURING

66
Above represents sample of parts of the on-going work at the site
SHORELINE PROTECTION, ALEBIRI, BAYELSA STATE

BEFORE

67
Above represents sample of parts of the ecological site before the commencement of work
SHORELINE PROTECTION, ALEBIRI, BAYELSA STATE

ON-GOING

68
Above represents sample of parts of the on-going work at the site
ABAJI GULLY EROSION AND FLOOD CONTROL WORKS ABAJI AREA COUNCIL, ABUJA

BEFORE

69 Above represents sample of parts of the ecological site before the commencement of work
ABAJI GULLY EROSION AND FLOOD CONTROL WORKS ABAJI AREA COUNCIL, ABUJA

ON-GOING

Above represents sample of parts of the on-going work at the site


70
ABAJI GULLY EROSION AND FLOOD CONTROL WORKS ABAJI AREA COUNCIL, ABUJA

AFTER

71
Above represents sample of parts of the completed work
AZARE TOWNSHIP FLOOD AND EROSION CONTROL WORKS, AZARE, BAUCHI
STATE

BEFORE

72 Above represents sample of parts of the ecological site before the commencement of work
AZARE TOWNSHIP FLOOD AND EROSION CONTROL WORKS, AZARE, BAUCHI
STATE

ON-GOING

Above represents sample of parts of the on-going work at the site


73
AZARE TOWNSHIP FLOOD AND EROSION CONTROL WORKS, AZARE, BAUCHI
STATE

AFTER

74
Above represents sample of parts of the completed work
CHANNELIZATION AND FLOOD CONTROL OF PONJ-AFO RIVER, IKIRUN, OSUN STATE:
PICTORIALS OF SITE BEFORE COMMENCEMENT OF WORK

BEFORE

75 Above represents sample of parts of the ecological site before the commencement of work
CHANNELIZATION AND FLOOD CONTROL OF PONJ-AFO RIVER, IKIRUN, OSUN STATE:

DURING

Above represents sample of parts of the on-going work at the site


76
CHANNELIZATION AND FLOOD CONTROL OF PONJ-AFO RIVER, IKIRUN, OSUN STATE:

AFTER

77
Above represents sample of parts of the completed work
EROSION AND FLOOD CONTROL WORKS AT IFEDAYO/BOLUWADURO/ILA, OSUN STATE

BEFORE

Above represents sample of parts of the ecological site before the commencement of work
78
EROSION AND FLOOD CONTROL WORKS AT IFEDAYO/BOLUWADURO/ILA, OSUN STATE

DURING

79 Above represents sample of parts of the on-going work at the site


EROSION AND FLOOD CONTROL WORKS AT IFEDAYO/BOLUWADURO/ILA, OSUN STATE

AFTER

80
Above represents sample of parts of the completed work
FEDERAL ROAD SAFETY CORPS VEHICLES ACQUIRED IN DECEMBER 2016

81
Above represents sample of parts of the acquired vehicles
FEDERAL ROAD SAFETY CORPS VEHICLES ACQUIRED IN DECEMBER 2016

82
Above represents sample of parts of the acquired vehicles
NATIONAL HAJJ COMMISSION OF NIGERIA (NAHCON) ACQUIRED PROPERTY

83
NATIONAL PENSION COMMISSION (Volume License Agreement)

84
NATIONAL POPULATION COMMISSION PURCHASED VEHICLES

85
Above represents sample of parts of the purchased vehicles
NATIONAL POPULATION COMMISSION PURCHASED VEHICLES

86
Above represents sample of parts of the purchased vehicles
ECONOMIC AND FINANCIAL CRIMES COMMSSION (EFCC)
PURCHASED OPERATIONAL VEHICLES

87
Above represents sample of parts of the purchased Operational Vehicles
CONSTRUCTION OF THE ECONOMIC AND FINANCIAL CRIMES
COMMSSION (EFCC)’S CORPORATE HEADQUARTERS

88
Above represents sample of parts of the on-going construction work at the site
89
90
ANNEX (I)

ECOLOGICAL FUND OFFICE (EFO) PROJECTS


BELOW FEDERAL EXECUTIVE COUNCIL (FEC)
THRESHHOLD FROM MAY 2015 TO DECEMBER 2017

91
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS
CONTRACT & STATUS OF
DATE OF ACCESSED BY CREATED REMARKS (PROSPECTS OF
SN PROJECT TITTLE USER AGENCY PROCUREMEN IMPLEMENTATIO
APPROVAL THE PROJECT SKILLED/ COMPLETION)
T DURATION N (%)
(%) UNSKILLED

Provision of
Public
Conviniencies in
(3) LGAs, Ibadan,
Oyo State:
i. Mogaji Market, The Scope of work include:
Iyana Agbala i. Site Clearance;
along New ii. Excavation of Pit;
Ibadan-Ife Road, iii. Backfill and removal of
Egbeda LGA; excess of soil;
ii. Jonku Ecological iv. Construction of
1 July, 2015. 3 Months N/A 100% 18
Neigghbourhood Fund Office Conveniences;
Market along Iwo v. Drilling of Boreholes sealed
Road with overhead Steel Tank and
Interchange, Ojoo Solar Panels.
Expressway, The project is 100% completed.
Ibadan North East Commissioned and handed over.
LGA; and
iii. Orita Aperin
Market, Orita
Aperin Ibadan
South LGA.

The Scope of work include:


Soil Erosion Site clearing / earth works and
Control Works at November, Ecological Construction of Culverts and
2 1 Month. N/A 100% 30
Usho/Ise Road, 2015. Fund Office Drainages. The project is 100%
Ondo State. completed and awaiting
commissioning and handing over.

The Scope of work include:


i. Site Clearance;
ii. Earthworks and Excavation;
Soil Erosion iii. Construction of Reinforced
November, Ecological
3 Control Works At 1 Month. N/A 100% 25 Concrete Lined Channels;
2015. Fund Office
Zuba iv. Construction of Concrete
Culverts.
92 The project is 100% completed.
Commissioned and handed over.
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF
CONTRACT & FUNDS
STATUS OF JOBS
DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF
SN PROJECT TITTLE IMPLEMENTAT CREATED
APPROVAL AGENCY NT THE PROJECT COMPLETION)
ION (%) SKILLED/
DURATION (%)
UNSKILLED
The Scope of work include:
Construction of drainage
channels; Demolition & removal of
existing blocked/weak/inadequate
stream crossing structures and
Doma Flood drainages; Connection of existing
Erosion Control November, Ecological Channels to the newly constructed
4 4 Months N/A 100% 25
Works, Nasarawa 2015. Fund Office Channels; Stone-Pitching and
State Rock dump for erosion control
works; and Construction of
Access Culverts and provision of
access Slabs across the drainage
Channels. The project is 100%
completed and handed over

The Scope of work include:


Lohmak-
Site clearing and Earth works;
Kumkwum
Reinforcement of concrete and
Erosion Control November, Ecological
5 4 Months N/A 100% 25 lined channels; and Reinforcement
Works, Langtang 2015. Fund Office
of box culverts.
North LGA,
The Project is 100% completed
Plateau State
and handed over.

The Scope of work include:


i. Site Clearance;
ii. Earthworks and Excavation;
Gully Erosion iii. Construction of concrete
Control Works at December, Ecological drains/channels;
6 6 Month. N/A 100% 28
Magodo, Lagos 2015. Fund Office iv. Stone Pitching; and
State v. Construction of concrete
retaining wall.
The project is 100% completed.
Commissioned and handed over.

93
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF
CONTRACT & FUNDS
STATUS OF JOBS
DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF
SN PROJECT TITTLE IMPLEMENTAT CREATED
APPROVAL AGENCY NT THE PROJECT COMPLETION)
ION (%) SKILLED/
DURATION (%)
UNSKILLED

The Scope of work include:


i. Site Clearance;
ii. Earthworks and Excavation;
Oghere Ahmed
iii. Construction of Reinforced
Erosion Control December, Ecological
7 6 Months. N/A 100% 25 Concrete Lined Channels;
Works, Idimu, 2015. Fund Office
iv. Construction of Concrete
Lagos
Culverts.
The project is 100% completed.
Commissioned and handed over.

The Scope of work include:


i. Site Clearance;
ii. Demolition and removal of
existing blocked/weak and
inadequate structures;
Kudeti Flood iii. Construction of reinforced
December, Ecological
8 Control Works, 5 Months. N/A 100% 28 rectangular and trapezoidal
2015. Fund Office
Ibadan Oyo State drains/channels;
iv. Construction of culverts and
access slabs; and
v. Stone Pitching.
The project is 100% completed.
Commissioned and handed over.

Scope of work include:


Construction of one side
Umudiato Flood trapezoidal concrete drains;
Control Works, February 4th, Ecological Construction of appropriately sized
9 4 Months N/A 100% 25
Orlu LGA, Imo 2016 Fund Office box culverts; and Road
State improvement works. The project is
‘100% completed and awaiting
commissioning.

94
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF
CONTRACT & FUNDS
STATUS OF JOBS
COST OF DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF
SN PROJECT TITTLE IMPLEMENTAT CREATED
PROJECT (N) APPROVAL AGENCY NT THE PROJECT COMPLETION)
ION (%) SKILLED/
DURATION (%)
UNSKILLED

Scope of work include:


Umuoki- Construction of 2.4km drains;
Umuowasi Provision of concrete drains
Erosion Control Ecological and culverts; and Road
10 200,382,392.19 March, 2016 4 Months N/A 100% 28
and Road Fund Office improvement works.
Improvement The project is 100% completed.
Works. Commissioned and handed
over.

Scope of work include:


Owalla Avuvu Earth works; Concrete
Erosion Control Ecological Drains/Culverts; Box Culverts
11 N176,504,612.81 March, 2016 5 Months. N/A 100% 25
Works, Imo Fund Office and Stone-pitching.
State The project is 100% completed
and handed over.

The Scope of work include:


i. Construction of Solar
Powered Borehole;
Model Village ii. 5000 Liters Overhead
Development, Ecological Water Supply Tank;
12 July, 2016. 10 Months N/A 100% 25
Adamawa and N168,147,104.52 Fund Office iii. 50 Seating Capacity
Gombe States. Community Viewing Centre.
The project is 100% completed.
Awaiting commissioning and
handing over.

95
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS
CONTRACT & STATUS OF
DATE OF ACCESSED BY CREATED REMARKS (PROSPECTS OF
SN PROJECT TITTLE USER AGENCY PROCUREMEN IMPLEMENTATIO
APPROVAL THE PROJECT SKILLED/ COMPLETION)
T DURATION N (%)
(%) UNSKILLED

Scope of work include:


Reconstruction Construction of earth Dam;
of Maska Earth Construction of Spillway,
November, Ecological
13 Dam, Maska 3 Months N/A 100% 28 Embankment and Surface
2016 Fund Office
Funtua, dressed road. The project is
Katsina State 100% completed and handed
over

Scope of work include the


following:
Contract for
i. Construction of 2 No.
Erosion
Culverts length 18m,
andFlood March 6th, Ecological
14 6 Months N/A 100% 28 ii. Construction of Walkway
control Work in 2017. Fund Office
Access Road of 700m.
Bogoro LGA
Project is 100% Completed.
Bauchi State
Awaiting commissioning and
handing over.

Soil Erosion
The Scope of work include:
Control Works
Concrete Retaining wall and
at Nigerian Ecological
15 March, 2017 4 Months N/A 100% 28 earth works. The Contract is
Police Housing Fund Office
100% completed and handed
Estate Kurudu,
over
Abuja, FCT.

96
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF
CONTRACT & FUNDS
STATUS OF JOBS
DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF
SN PROJECT TITTLE IMPLEMENTAT CREATED
APPROVAL AGENCY NT THE PROJECT COMPLETION)
ION (%) SKILLED/
DURATION (%)
UNSKILLED

Scope of work include:


Gadan Toro to
Site Clearance and Earth work;
Market Road
Concrete works/Retaining wall;
Erosion Control Ecological
16 March, 2017 9 Months N/A 100% 28 and Rehabilitation of Eroded
Works, Toro Fund Office
Road. The project is 100%
LGA, Bauchi
completed and awaiting
State.
commissioning.

Scope of work include:


Construction and
Rehabilitation of Dam
Erosion/Flood embankment;
Control Project Expansion of Spillway;
March 9th, Ecological
17 of Rice Field, 4 Months N/A 100% 18 Construction of Discharge
2017 Fund Office
Shanga LGA, Channels and flood control
Kebbi State Dyke. The project is 100%
completed and awaiting
commissioning and handing
over.

97
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF
CONTRACT & FUNDS
STATUS OF JOBS
DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF
SN PROJECT TITTLE IMPLEMENTAT CREATED
APPROVAL AGENCY NT THE PROJECT COMPLETION)
ION (%) SKILLED/
DURATION (%)
UNSKILLED

Scope of work include:


Gully Erosion
Removing of blocked
Control Works
drains/Culverts and Earth
at Federal Ecological
18 March, 2017 4 Months N/A 100% 25 works. The project is 100%
Government Fund Office
completed and awaiting
College, Otobi,
Commissioning and Handing
Benue State
Over

Scope of work include:


Site clearing;
Channelization
Construction of Culverts;
and Flood
Carting away of all loosed
Control of Ponj- March 4th, Ecological
19 6 Months N/A 100% 30 materials & debris; and
Afo River, 2017 Fund Office
asphalt overlay road.
Ikirin, Osun
The project is 100% completed
State
and awaiting commissioning
and handing over.

Scope of work include:


Construction of earth road;
Construction of concrete drain
Ganye-Yelwa
800m long;
Road Erosion
Construction of 5No.
and Flood March 3rd, Ecological
20 10 Months N/A 100% 28 Reinforced concrete Culverts,
Control Works, 2017 Fund Office
double cell/single cell; and
Ganye LGA,
Stone-Pitching of road/drain
Adamawa State
side 500m. The project is 100%
completed.
Awaiting commissioning.
98
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

CONTRACT & FUNDS NO OF JOBS


STATUS OF
DATE OF USER PROCUREME ACCESSED BY CREATED REMARKS (PROSPECTS OF
SN PROJECT TITTLE IMPLEMENTAT
APPROVAL AGENCY NT THE PROJECT SKILLED/ COMPLETION)
ION (%)
DURATION (%) UNSKILLED

Ganye-Dabora-
Daksam Road Scope of work include:
Erosion and Construction of concrete drains;
Flood Control Concrete culverts;
Works, Ganye Ecological Earth works; and
21 March, 2017 7 Months N/A 100% 30
LGA and Fund Office rehabilitation of water supply.
Reconstruction of The project is 100% completed and
Jada Water Works awaiting Commissioning and
System, Handing Over.
Adamawa State

Scope of work include:


Site Clearance;
Azare Township Concrete Drains at GDSS Azare;
Flood and Matsago Low Cost Housing;
Ecological
22 Erosion Control March, 2017 5 Months N/A 100% 28 Old Airport and Cemetery; Culverts
Fund Office
Works, Bauchi and Access Slabs.
State. The project is 100% completed. To
be commissioned and handed
over.

Scope of work include:


Site clearance and earth works;
Tsoho Gwaram
Concrete works;
Erosion and
Ecological Reinforced concrete drainages,
23 Flood Control March, 2017 10 Months N/A 100% 28
Fund Office culverts and access slabs. The
Project, Gwaram
project is 100% completed.
LGA, Jigawa State
Awaiting commissioning and
handing over.
99
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF
CONTRACT & FUNDS
STATUS OF JOBS
DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF
SN PROJECT TITTLE IMPLEMENTAT CREATED
APPROVAL AGENCY NT THE PROJECT COMPLETION)
ION (%) SKILLED/
DURATION (%)
UNSKILLED
Scope of work include:
Kumo Gully Construction of concrete drains
Erosion Site, and culverts; and
Ecological
24 Anguwan Jauro March, 2017 5 Months N/A 100% 30 Stone-Pitching of embankment.
Fund Office
Musa, Akko LGA, The project is 100% completed and
Gombe State awaiting Commissioning and
Handing Over

Scope of work include:


Kumo Gully Construction of concrete drains
Erosion Site, and culverts; and
Ecological
25 Anguwan Jauro March, 2017 6 Months N/A 100% 28 Stone-Pitching of embankment.
Fund Office
Sabo, Akko LGA, The project is 100% completed.
Gombe State Awaiting commissioning and
handing over.

Scope of work include:


Amper Flood Construction of concrete drains;
Hazards and Ecological Concrete culverts; and Stone-
26 March, 2017 6 Months N/A 100% 28
Erosion Control Fund Office Pitching. The project is 100%
Works, Tarka LGA completed. Awaiting
commissioning and handing over.

Scope of work include:


Site Clearance and earth works;
East of Kumo Excavation for side drains and
General Hospital Culverts;
to Jauro Musa Ecological Construction of trapezoidal
27 March, 2017 4 Months N/A 100% 28
Stream Gully Fund Office concrete lined drains;
Erosion Control Concrete cover Slaps..
Project. The project is 100% completed.
Awaiting commissioning and
handing over.
10
0
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF
CONTRACT & FUNDS
STATUS OF JOBS
DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF
SN PROJECT TITTLE IMPLEMENTAT CREATED
APPROVAL AGENCY NT THE PROJECT COMPLETION)
ION (%) SKILLED/
DURATION (%)
UNSKILLED
Scope of work include:
Flood Control and
Dredging and De-silting;
De-silting of
Construction of Concrete
Ogbagba in Ecological
28 March, 2017 6 Months N/A 100% 30 embankment.
Oshogbo Fund Office
The project is 100% completed.
Township, Osun
Awaiting commissioning and
State
handing over.
Scope of work include:
Site Clearance;
Reclamation of half of the gully;
Construction of Road 1;
Abaji Gully
Construction of drainage along
Erosion and Ecological
29 March, 2017 6 Months N/A 100% 28 Road 1;
Flood Control, Fund Office
Provision of Collector drain to
FCT, Abuja
connect to the reclaimed gully.
The project is 100% completed.
Awaiting commissioning and
handing over.
Scope of work include:
Construction of concrete
Erosion & Flood
drains/Culverts;
Control at
Ecological Retaining wall;
30 Ifedayo/Boluwadu May, 2017 8 Months N/A 100% 30
Fund Office Earth work; and
ro/Ila in Osun
Asphalt pavement. The project is
State
100% Completed. Awaiting
commissioning and handing over.

Scope of work include:


Erosion Control
Dredging and De-silting;
and
Construction of Concrete
Channelization of Ecological
31 May 17th , 2017. 6 Months N/A 100% 30 embankment.
Okoko River, Fund Office
The project is 100% completed.
Oshogbo, Osun
Awaiting commissioning and
State
handing over.
10
1
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF
CONTRACT & FUNDS
STATUS OF JOBS
DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF
SN PROJECT TITTLE IMPLEMENTAT CREATED
APPROVAL AGENCY NT THE PROJECT COMPLETION)
ION (%) SKILLED/
DURATION (%)
UNSKILLED
Scope of work include:
Bagole-Kofare
Construction of concrete drains/
Erosion Control
Ecological culverts; and Earth work. The
32 Works, Yola May, 2017 6 Months N/A 100% 30
Fund Office project is 100% completed and
North, Adamawa
awaiting Commissioning and
State.
Handing Over.
Scope of work include:
Mitigation of Dredging; Concrete
Flooding into drains/culverts; and Retaining
Uburu Salt Lake wall. As at January, 2018, the
And Over 20,000 Ecological project is 45% on-going.
33 May, 2017 7 Months N/A 45% 30
HA of Rice Farm Fund Office Challenge: Community
at Asu-Umunaga, disagreement posed a challenge
Ubulu, Ebonyi but resolved already with
State. extension granted to the
Contractor
Scope of work include:
Site Clearance and earth work;
Amachara Flood
Retaining wall and drainages; and
And Erosion Ecological
34 May 3rd , 2017 7 Months N/A 100% 28 slope protection. The project is
Control Works, Fund Office
100% ongoing. The Contractor has
Abia State.
been instructed to speed up the
work.
Contract for Scope of work include:
Erosion control i. Construction of 1,235m
Works at Makinde Ecological Reinforced Concrete Channel.
35 June 1st ,2017. 7 Months N/A 85% 28
way and Environs Fund Office ii. Construction of 2 Culverts;
idimu Lagos iii. Pavement and Surfacing.
State Project is 85% on-going.
The scope of work include:
Contract for i. Construction of 1.2 km Walkway
Erosion and flood and Drainage;
control Project Ecological ii. Interlocking Pavement;
36 June 1st ,2017. 7 Months N/A 100% 30
Aiyeotoro Fund Office iii. Construction of 5 Box
Community Ondo Culverts. Project is 100%
State completed. Awaiting
10 commissioning and handing over.
2
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS
CONTRACT & STATUS OF
DATE OF ACCESSED BY CREATED REMARKS (PROSPECTS OF
SN PROJECT TITTLE USER AGENCY PROCUREMEN IMPLEMENTATIO
APPROVAL THE PROJECT SKILLED/ COMPLETION)
T DURATION N (%)
(%) UNSKILLED
Contract for Erosion Construction of 204m Reinforced
and flood control Concrete Channel and Construction
Ecological
37 Works in Eruwa, June 1st ,2017. 3 Months N/A 100% 25 of 2 Culverts. 100% Completed.
Fund Office
Ibarapa East LGA Awaiting commissioning and handing
Oyo State over.
Scope of work include:
Contract for Erosion
i. Construction of 1,777m of
and flood control
Reinforced Concrete Drains with
Works Medical
Ecological backfilling and Compaction;
38 School, Bauchi June 1st ,2017. 6 Months N/A 100% 28
Fund Office ii. Construction of 2 Box Culverts.
Town, Bauchi
Project is 100% completed and
Metropolis LGA
awaiting Commissioning and Handing
Bauchi State
Over.
Scope of work include:
i. Construction of 982m Drainage;
Contract for Erosion
ii. Earthworks;
and flood control
Ecological iii. Surfacing Work,
39 Works in Tarka and June 1st ,2017. 6 Months N/A 88% 28
Fund Office iv. Construction of 4 Box Culverts,
Guma LGA Benue
v. Bridge Works.
State
The project is 88% completed and
Ongoing.
Status of work done are:
i. Excavation and desilting of all the
existing drains and culverts including
the drains within the roundabout;
Jalingo Metropolis ii. Access slabs were provided as
(Kofar Fada) required in the BEME;
Shetima and Ecological iii. Double Cell Culvert has been
40 June 1st ,2017. 6 Months N/A 100% 30
Kasuwan Yelwa Fund Office constructed;
Areas, Turaki A iv. Pot holes and failed part of
Wards, Taraba State Shetimma Central Mosque road has
been rehabilitated.
The project has achieved 100%
completed. Awaiting commissioning
and handing over.
Scope of work include:
Site Clearing;
Erosion Control Construction of Drainages of various
Works in Uvu, Ecological sizes & dimensions; Culverts, Slabs
44 June 1st ,2017. 6 Months N/A 100% 30
Askira Uba LGA, Fund Office and
Borno State. Road Improvements Works etc. The
10 project is 100% completed. Awaiting
commissioning and handing over
3
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS
CONTRACT & STATUS OF
DATE OF ACCESSED BY CREATED REMARKS (PROSPECTS OF
PROJECT TITTLE USER AGENCY PROCUREMEN IMPLEMENTATIO
APPROVAL THE PROJECT SKILLED/ COMPLETION)
T DURATION N (%)
(%) UNSKILLED

Scope of work include:


Site Clearing;
Tambuwal-
Ecological reclamation works and construction of
45 Dogondaji Erosion June 1st ,2017. 7 Months N/A 100% 30
Fund Office drains at Bashire, Dogondaji and Road
Works, Sokoto State
improvement works at Jabo town.
The project is 85% ongoing.
Scope of work include:
Odolu Community Construction of concrete drains;
Soil Erosion and Ecological dredging;
46 June 1st ,2017. 12 Months N/A 100% 30
Flood Control Fund Office Stone-Pitching of the bridge area. The
Project, Kogi State project is 100% completed and awaiting
Commissioning..
Scope of work include:
Site clearing and earth works;
Gully Erosion and
Drainages and Culverts;
Flood Control, Ecological
47 June 1st ,2017. 6 Months N/A 100% 28 Road Improvement works and Surface
Idumu Osigbudu Fund Office
dressing. The project is 100%
Street, Delta State.
completed and awaiting commissioning
and handing over
Scope of work include:
Gully Erosion and Site Clearance & earth works; Culverts
Flood Control Works and Drains as well as Pavement
Ecological
48 at Akpene Eket and June, 2017. 7 Months N/A 100% 30 Surfacing.
Fund Office
Its Environs, Akwa The project is 100% completed.
Ibom State. Awaiting commissioning and handing
over.

Scope of work include:


Construction of type 1 rectangular
Magama LGA drains at Ibeto;
Erosion and Flood Ecological Construction of 2 drains (Trapezoid
49 June,2017. 9 Months N/A 89% 30
Control Project, Fund Office 2.3m base) at Ibeto; Construction of
Niger State. type 1 drains at Salka; and
Construction of a 3 cell box culverts at
Busra. The project is 89% Ongoing.

Soil Erosion Control Scope of work include:


and Road Site Clearing and earth works; 16m
Improvement Works, Ecological Culvert of 3m high;
50 June , 2017. 6 Months N/A 90% 30
Yalenguruza, Fund Office 4 No. side drains and Road
Gombe, Gombe improvement including retaining wall
10 StAte. etc. The project is 90% ongoing.

4
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

FUNDS NO OF JOBS
CONTRACT & STATUS OF
DATE OF ACCESSED BY CREATED REMARKS (PROSPECTS OF
SN PROJECT TITTLE USER AGENCY PROCUREMEN IMPLEMENTATIO
APPROVAL THE PROJECT SKILLED/ COMPLETION)
T DURATION N (%)
(%) UNSKILLED

Scope of work include:


Soil Erosion and Site clearing;
Flood Control Earth works;
Project at Ecological Concrete drainages, culverts and Slabs;
51 June, 2017. 5 Months N/A 100% 28
Agenebode/Fugar Fund Office Agronomic measures; and
Erosion Site, Edo soil conservation. The project is 100%
State completed and awaiting Commissioning
and Handing Over.

Flood,
Scope of work include:
Channelization and
Channelization of River Owa;
Reconstruction of
Ecological Reconstruction of failed structures; and
52 Failed Structures June ,2017. 6 Months N/A 50.16% 30
Fund Office Road Construction.
along Ijebu-Ode/
The project was Stopped at 50.16%
Ilese Road Via Owa
completion by Ogun State government.
River, Ogun State

Scope of work include:


Site Clearance;
Reclamation of part of the gully;
Abaji Gully Erosion Construction of Road 2; Construction of
and Flood Control Ecological a reinforced concrete drain along the
53 June ,2017. 6 Months N/A 100% 30
Works, Phase II, Fund Office Road 2; Provision of Collector drain to
FCT. Abuja connect to the reclaimed gully. the
project is 100% completed.
Awaiting commissioning and handing
over.

Scope of work include:


Site Clearance; Earth works; Culverts &
Jikwoyi Erosion and
Ecological Line Drains; Pavement and Surfacing.
54 Flood Control October, 2017 4 Months N/A 100% 28
Fund Office The project is 100% completed.
Works, AMAC
Awaiting commissioning and handing
over.

Gully Erosion/Flood
Scope of work include:
Control & Road
Site Clearing and earth works; Culverts
Improvement works
October 11th, Ecological and Drains; and Pavement and
55 at Sokale 3 Months N/A 100% 25
2017 Fund Office Surfacing. The project is 100%
Community, Dutse
completed and awaiting commissioning
Alhaji, Bwari Area
and handing over
Council, FCT
10
5
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF
CONTRACT & FUNDS
STATUS OF JOBS
DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF
SN PROJECT TITTLE IMPLEMENTAT CREATED
APPROVAL AGENCY NT THE PROJECT COMPLETION)
ION (%) SKILLED/
DURATION (%)
UNSKILLED

Erosion Control
Works along Scope of work include:
Bauchi-Ningi Site Clearance and Earth work;
Road Junction to Concrete works as Drains and
Ecological
56 the Main Campus October, 2017 4 Months N/A 65% 30 Culverts;
Fund Office
of Abubakar Stone-Pitching; and
Tafawa Balewa Pavement Surfacing.
University, The project is 65% ongoing.
Bauchi State

Scope of work include:


Burga -
Site Clearing;
Gwammadaji
Construction of culverts;
Flood and Ecological
57 6 Months N/A 65% 26 Earth works;
Erosion Control Fund Office
Drains and Concrete walls;
Works, Bauchi
Pavement and Surfacing. The
State
project is 65% Ongoing.
October, 2017.

Stream Erosion
Control at Chief The Scope of work include:
Ogungbo Road i. Site Clearance/Preparation;
One River along ii. Earthworks and Excavation;
Ecological
58 Olabisi Onabanjo 7 Months N/A 80% 30 iii. Dredging;
October, 2017. Fund Office
University Road, iv. Channel
Ago Iwoye, Ijebu Preparation/Rehabilitation works.
North LGA, Phase The project is 80% ongoing.
1, Ogun State

10
6
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF
CONTRACT & FUNDS
STATUS OF JOBS
DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF
SN PROJECT TITTLE IMPLEMENTAT CREATED
APPROVAL AGENCY NT THE PROJECT COMPLETION)
ION (%) SKILLED/
DURATION (%)
UNSKILLED

Scope of work include:


i. Site Clearing and
Rehabilitation of
Earthworks
Eroded Road and
ii. Culverts and Drains
Drain in Apo Ecological
59 October 2017 5 Months N/A 100% 26 iii. Road Works; and
Resetlement, Apo Fund Office
iv. Auxillary Works
District, AMAC,
The project is 100% completed.
Abuja
Awaiting commissioning and
handing over.

Scope of work include:


i. Site Clearing and
Flood and Earthworks;
Erosion Control Ecological ii. Culverts and Drains;
60 October 2017 6 Months N/A 100% 28
at Karshi Town in Fund Office iii. Pavement and Surfacing
FCT, Abuja The project is 100% completed
and awaiting commissioning

Gully
Erosion/Flood Scope of work include:
Control and Road i. Site Clearing and
Ecological
61 Improvement October 2017 3 Months N/A 100% 25 Earthworks;
Fund Office
Works at Durumi ii. Culverts and Drains;
Mpape, FCT. iii. Road Improvement Works
Abuja

10
7
THE STATUS OF IMPLEMENTATION OF APPROVALS BY THE ECOLOGICAL FUND OFFICE TENDERS
BOARD FROM MAY 2015 TO DECEMBER 2017

NO OF
CONTRACT & FUNDS
STATUS OF JOBS
DATE OF USER PROCUREME ACCESSED BY REMARKS (PROSPECTS OF
SN PROJECT TITTLE IMPLEMENTAT CREATED
APPROVAL AGENCY NT THE PROJECT COMPLETION)
ION (%) SKILLED/
DURATION (%)
UNSKILLED

Ratification of the
Scope of work include:
Award of Contract
i. Site Clearing and Earthworks;
for the
ii. Culverts and Drains;
Reconstruction of
Ecological iii. Road Improvement Works;
62 Damaged Culverts October 2017 3 Months N/A 100% 28
Fund Office iv. Pavement and Surfacing
and Road
The project is 100% completed and
Improvement
awaiting commissioning and handing
Works at Kapwa
over
Road, Lugbe, Abuja

Contract for the


Reconstruction of Scope of work include:
3,125m2 Colapsed i. Site Clearing and Earthworks;
Boundary Fence at Ecological ii. Concrete and Block works;
63 October 2017 N/A 100% 25
Federal Fund Office iii. Reinforcement and Formworks
Government The project is 100% completed and
College, Malali, awaiting commissioning.
Kaduna State

Scope of work include:


Reconstruction of i. Site Clearing and Earthworks;
Damaged Culvert ii. Culverts, Drains and Concrete
and Road Ecological works;
64 October 2017 4 Months N/A 100% 28
Improvement Fund Office iii. Pavement and Surfacing
Works at Saburi, iv. The project is 100% completed
AMAC, FCT. Abuja and awaiting commissioning
and handing over