Republic of the Philippines

Province of Nueva Ecija


Municipality of Gabaldon

MUNICIPAL ENGINEERING OFFICE

Commission on Audit
Regional Office / Cluster
Consolidated Quarterly Report on Government Project / Program
For the Fourth Quarter, as of December 31, 2016

Project Name Location ABC Charging Fund Contract Amount Contractor/Payee Target Completion Date of Start Date of Completion Status Remarks
Days
Construction of Gabion Brgy. Bantug (Banay-banay Creek) 500,000.00 20% Dev't. Fund 6 C.D. 11/24/2016 12/2/2016 Completed
Construction of Gabion Brgy. Pantoc (Digmala Creek) 750,000.00 20% Dev't. Fund 8 C.D. 10/13/2016 11/4/2016 Completed
Construction of Gabion Brgy. Calabasa (Bitunin Creek) 1,600,000.00 20% Dev't. Fund 3,772,752.56 E.A. Padilla Builders 22 C.D. 10/24/2016 11/14/2016 Completed

Concreting of Mun.
Brgy. Pantoc 930,000.00 20% Dev't. Fund 17 C.D. 9/15/2016 10/7/2016 Completed
Slaughter Service Road
Salin Tubig Level 2 Brgy. South Poblacion 5,900,000.00 DILG/BUB/LGU 5,897,842.58 E.A. Padilla Builders 240 C.D. 10/17/2016 TO DATE On-going With LGU Counterpart
Instillation of Electrical 20% Dev't. Fund
Brgy. Pantoc 35,000.00 29,351.80 By Admin. 10 C.D 12/1/2016 12/10/2016 Completed Materials Only
Post (Sloughter House) (Continuing 2015)

Repainting of Mun. Hall Brgy. North Poblacion 229,503.00 20% Dev't. Fund/SPA 99,821.00 By Admin. 65 C.D. 12/1/2016 2/5/2016 Completed Materials Only
Construction of Placenta
Brgy. South Poblacion 15,000.00 20% Dev't. Fund 5,400.00 By Admin. 7 C.D. 12/22/2016 12/29/2016 Completed Labor Only
Pit & Sharp Pit

Prepared by:

MANUEL M. CABUNGCAL JR.


Municipal Engineer Approved:

ROLANDO S. BUE
Municipal Mayor