1. The right to demarcate Right of Way for local level road is: a. Province Government b. Central Government c. Local Level d. All of above 2. The first step work for any construction project is a. Design b. Survey c. Estimate d. Tendering 3. The ruling gradient provided for hill road is: a. 12󠆼percent b. 9 percent c. 7 percent d. 0.5 percent 4. Bid Price is: a. Price quoted by bidder b. Tendering price c. Estimated price d. Price after variation 5. Which is the principle of public procurement? a. Transparency b. Accountability c. Utilization d. All of above
6. Which is the element of contract document?
a. Estimate b. Performance bond c. Tender Notice d. Bid document 7. For any bid, if the bid validity period is 120 days, and suppose a bidder submit the following bid validity period, which one is rejected? a. 125 days b. 119 days c. 90 days d. b & c 8. Quality control is responsibility of a. Engineer b. Contractor c. Owner d. All of above 9. Mass failure includes a. Landslide b. Wedge failure c. a and b both d. a or b only one 10. As per current Financial Act of Nepal bill amount not less than........must be endorsed with VAT bill. a. Rs.15000 b. Rs.20000 c. Rs.25000 d. Rs.5000