Attachment 1 - Cost for trial pit works in Section C

Date: 2023-07-06
No Item Description Unit Quantity Record

The height is 2.2m, the width of both sides is 10m,


1.1 Color steel plate fence the lining is three 3cm* 3cm* 3cm square steel, and m2 44 30 Mtr
a vertical 5cm*5cm*5mm square steel column.

Set a water horse in front of the blocking position,


and at the same time, set a diversion water horse in
1.2 Water-filled barrier pcs 76 65
the middle of the road, with a distance of 5m and a
length of 300m.

Along one end of the blocking end through the


1.3 Warning light middle divider to the other end of the blocking, pcs 24 40
install solar warning lights, one at 10m intervals.

Place a diversion warning sign at each end of the


1.4 Warning board pcs 6 4
block, 100m away and 200m away.

A guide plate indicated


1.5 Two on each side. pcs 4 2
with a light arrow

Diversion guard Whistles, walkie-talkies, baton, reflective vests and


1.6 set 4 2
protection items other diversionary items.
215 Broken Head
1.7 With crushing head + digging bucket. month 2 1
Excavator Rental

1.8 Generators Generator rental + fuel costs month 2 1

Total-20 ( Traffic Signal Man- 02, Electrician -01, Safety officer -02, Site Engineer-
10 workers + 5 diversion staff per shift, 2 shifts in
1.9 Bangladeshi workers
total.
day 1800 01, Interpreter-01, Excavator Operator -01, General worker – 08,Security Night -
03, Security Day -01) Currently, only the day shift is continuing

1.10 Chinese staff 2 shifts day 120 2


Detecting instruments, road cutting machines, road
1.11 Small machinery pcs 1.00 7
rollers, etc.
1.12 Road restoration Restoring to passable state with brick slag. m2 628.16 Using existing excavated road material
Destroyed structural layers and other garbage are
1.13 Garbage disposal m3 314.00 None
discarded.
1.14 Transportation Business car. month 2.00 1

Total