Weekly Report
Week Ending in February 18, 2011
Project to Date:
THIR: 8.83 PTD
TRIR: 0.53 PTD
Progress Kikori Bridge - Commenced installatrion of decking.
Highlights Mubi Bridge - Commenced assembly of launch nose on launch rails.
Road Breakthrough from Kantobo to Mubi on 16 February.
Recommenced work at Hides on 14 February.
.
* HGCP / Hides area recommenced work on 14 February after shut down due to security breach which
occurred at Wellpad A on 21 January.
3 week
Kikori Bridge - Complete bridge installation.
look ahead
Kwill Creek - Launch bridge.
Mubi Bridge - Commence main truss assembly.
ACCOMPLISHED ACTIVITIES LOOK AHEAD
Lost Time
KPI’s
West – Drilling and piling of piles. 1st sections are Mubi-Kantobo Road
drilled. Splicing has begun. - Continue Pioneering track, widening,
trimming road surface, sheeting and
Gobe: tidying of batters.
Gobe-Mubi Road: Continue with road Furniture
installation. Hides
Culvert 52 to be fully installed by 13 FEB. 3 barrel Security Shutdown
culvert – last one on this section of road. Investigate EPC5 ROW Quarry
ACCOMPLISHED ACTIVITIES LOOK AHEAD
source
Mubi-Kantobo Road - Surveyed through CH 5600. Highlands Highway
Cleared through CH 5950. Pioneered through CH 6000. Continue Road Maintenance
Bulk Earthwork through CH7990. Sheeting through CH Demobilization planning of
9650. Contractor staff from Oyarip
camp .
Kantobo Retrieval of C1 assets from Kiburu
Mubi-Kantobo Road - Surveyed through CH 5500. Relocate crew to Section 5 for
Cleared through CH 5200. Pioneered through CH 4850. road maintenance work
Bulk Earthwork through CH 4500. Sheeting through
CH 3500.
Key Issues
Security and Threat escalation in
Hides Hides hindering progress
Site Shut down – All Non essential Personnel C1 Staffing - EOS personnel issue
demobilized and Security Threats to personnel
Security Upgrades to Well Pad A and C1
Camp area ( HGCP) Progressed Key Learnings and Positive
Feedback
Hides Utilities
Commissioning of Washington Rig complete – C1 - 5 million man-hours –
mobilization expected at Hides work re-start. Recognition program roll-out in
Hides Pad ready to receive coming 2 weeks all C1 Sites
Execution Planning and Procurement 2nd Hides Community interface
reconciliations in progress with Clan Leaders – Community
support for the Project confirmed
Highlands Highway Mobile Squad engagement and
Camps ( Supply to Hides ) presence at C1 Sites more
Shipment of 6 accommodation Blocks to Hides prominent
Bridges
HP03 concrete formwork in progress
All other bridge propping complete
Roads
Road works Section 4 (2 areas- split
resources)
Personnel Port Douglas Workshop Cost close out. Close out of Workshop (issue notes,
Logistics Issued Org Chart structure action items, budget etc)
Renee Gray Issued correspondence to CCJV that response is Make minor changes to Org Charts
still outstanding on charter numbers and Monthly Reporting
processes. Close out of Milestone & Recognition
Continued efforts on expediting mobilisation of Plan
staff. Continue following up on staff
ACCOMPLISHED ACTIVITIES LOOK AHEAD
Clarified IT’s intensions for Field and relayed C1’s mobilisation
frustrations.
Confirmed merchandise for Kikori Bridge Opening
NOTE:
200%
150%
100%
50%
0%
Jan- Feb- Mar- Apr- May- Jun- Aug- Sep- Oct- Nov- Dec-
2009 2010 Jul-11 YTD PTD
11 11 11 11 11 11 11 11 11 11 11
Lagging Indicators
3.00 18
15
2.00 12
9
1.00 6
3
0.00 2009 2010 J an-11 Feb-11 Mar-11 Apr-11 May-11 J un-11 J ul-11 Aug-11 Sep-11 Oct-11 No v-11 Dec-11 YTD P TD
0
ROLLING LTIFR 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
LTIFR 0.00 0.00
Reco rdables 3 9 3 0 0 0 0 0 0 0 0 0 0 0 3 15
ROLLING TRIFR 2.74 0.50 1.30 0.73
TARGET 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3
RIFR 0.73 0.48
Logistics Statistics
Jan 12th Feb - 18th Feb
C1 RPT WK 7 2011
PORT ACTIVITY
Vessel Arrival Lae 1
Vessels Schedule to Arrive Lae 1
BOL's Pending Customs Lae 7
Vessel Arrival POM 1
Vessels Schedule to Arrive POM 1
BOL's Pending Customs POM 8
TRUCKING ACTIVITY (LAE)
Laydown Yards
No of Loads in Backlog Gen FRT 4.5
Gobe camp units Loads 11
Tamadigi Camp (HBS Yard) Stored Loads 19.5
Kopi Camp (NLB) Stored Loads 0
Yellow Iron Equip 3
General Equiment BBK 0
Blasting Equipment in Storage Loads 7
366,750 frt tonnes
Piles BBK 20 loads
FRT Movement
No of Convoys for Period EX Lae 6
CCJV 25
No of Convoys for Period EX MDU 7
CCJV 11
Destination
Lae Hides 22
Lae Kobalu 1
Lae MXH 1
Lae MDU 1
MDU Hides 8
MDU Lae 3
CUSTOMS / QUARATINE
No issues to RPT 0