Professional Documents
Culture Documents
Energy Policy
journal homepage: www.elsevier.com/locate/enpol
A R T I C L E I N F O A B S T R A C T
Keywords: Distributed energy resources (DERs) are poised to play a significant role in evolving power systems because of
Value of distributed energy resources their flexibility to be sited in areas of high value to the grid. Traditional DER compensation frameworks, spe
Distributed generation cifically net energy metering (NEM), inadequately communicate differences in the locational and temporal value
New York state
of DER generation to the grid. As a transition from NEM, New York State’s (NYS’s) Value of Distributed Energy
Parcels
Net energy metering
Resources (VDER) framework provides a methodology for calculating different value components that DERs offer
Front-of-the-meter the grid. To study the impacts of VDER frameworks on DER deployment, we developed a model to assess the
value of distributed solar and wind systems configured as either a behind-the-meter system or a front-of-the-
meter system for each parcel of land in NYS. Using parcel-level granularity, we can closely evaluate DER loca
tional value and siting availability, particularly in urban and suburban settings. Our analysis finds while most
DER generators would be modestly compensated for deferred transmission and distribution infrastructure up
grades (~0.01 $/kWh for solar PV), a subset of projects receive significant value from this component (0.035 to
0.089 $/kWh for top 5% of parcels for solar PV). Finally, our analysis finds VDER provides less overall
compensation than NEM to the average DER generator, however, it increases access to compensation for front-of-
the-meter DERs – a large and emerging market.
1. Introduction settings (Prakash et al., 2016; Carlisle et al., 2016). Such siting flexibility
could allow a project developer to pursue sites with the highest loca
The value of electricity is influenced by conditions that vary tional value. This stands in contrast to prevailing net energy metering
considerably both spatially and temporally (Hogan, 2013). These con (NEM) policies, wherein DER compensation is not spatially defined but
ditions include the cost of generation from the marginal generator dis is based on netted retail electricity expenditures (Taylor et al., 2015;
patched to meet load, costs of new and existing infrastructure to meet Zinaman et al., 2017).
demand throughout the grid, and diurnal and seasonal patterns in en
ergy demand and supply. Although utility-scale assets benefit from
economies of scale and lower levelized costs, by virtue of their proximity 1.1. Value of distributed energy resources
to demand, distributed energy resources (DERs) can provide unique
system benefits (e.g., reduced losses, congestion, and curtailment, and A developing theme in the management of U.S. power system is the
deferred infrastructure investment) and thus higher value per modernization of compensation mechanisms to better reflect spatial and
kilowatt-hour (kWh) generated (Fitzgerald et al., 2015; Prakash et al., temporal variability in the value of exports from distributed generation
2016; Zinaman et al., 2020). However, many of these benefits are not (DG) (Hansen et al., 2013; Linvill et al., 2013; Harari and Kaufman,
fully incorporated into electricity markets or compensation structures 2017; Holm et al., 2019; Proudlove et al., 2020). Regulators seek to
(Zinaman et al., 2020). balance the need for comprehensible tariffs and compensation mecha
Though utility-scale resource siting availability is constrained by nisms with the benefits of increased visibility into the fluctuating value
public attitudes and land-use considerations, DERs typically have more of energy (Bonbright, 1961; Linvill et al., 2013; Rábago et al., 2018).
siting flexibility to be colocated with demand in urban and suburban Most current U.S. compensation mechanisms do not communicate the
range of spatial and temporal variance in the value of exports from
* Corresponding author.
E-mail address: kevin.mccabe@nrel.gov (T. Bowen).
https://doi.org/10.1016/j.enpol.2021.112744
Received 8 December 2020; Received in revised form 19 October 2021; Accepted 24 November 2021
Available online 16 May 2022
0301-4215/© 2022 Elsevier Ltd. All rights reserved.
T. Bowen et al. Energy Policy 166 (2022) 112744
DERs. This misalignment between the rates at which distributed gen FTM systems compete for economic viability against two ends of the
eration are rewarded and the “true” value of that generation can lead to spectrum: smaller, retail-compensated BTM systems and larger,
misalignment between power system needs and the deployment and wholesale-compensated, utility-scale resources (Ackermann et al.,
operation of DERs (Zinaman et al., 2020; O’Shaughnessy et al., 2020). In 2001). In comparison with utility-scale generation resources, FTM sys
response to these concerns, as well as to higher penetrations of distrib tems are more expensive per kilowatt and accesses lower quality wind
uted generation, many stakeholders have advocated for a transition to and solar resources. However, in comparison to BTM, FTM resources are
more reflective and responsive approaches, such as value of solar (VOS) less expensive per kilowatt but potentially more challenging to site
frameworks (Hansen et al., 2013; Taylor et al., 2015; Proudlove et al., because of land constraints and interconnection limits. This suggests
2020; O’Shaughnessy et al., 2020).1 These frameworks seek to capture there may be significant economic potential for FTM resources under
the value of a diverse set of services DERs can provide to the power locational value frameworks because their value is assessed indepen
system, taking into account how this value may change depending on dently of on-site loads.
when and where power is injected. It is unclear, however, whether FTM resources can be sited in loca
Some of the more common value of DER frameworks attempt to tions that would be more highly compensated under a locational value
estimate value categories including energy, environmental, transmission framework. Factors that could inhibit siting availability in such locations
and distribution losses, generating capacity, and transmission and dis include land availability for development, shading, turbulence from the
tribution capacity (Hansen et al., 2013; Denholm et al., 2014; Harari and built environment, and interconnection limitations (Allen et al., 2013;
Kaufman, 2017; Proudlove et al., 2020). Some of these values, notably Allen, 2014; Lee et al., 2019). Even if it is technically feasible to site FTM
energy and capacity services, are already realized, and ongoing efforts resources at high-value sites that would be inaccessible to utility-scale
seek to improve DER access to these markets (NYISO, 2017; Lavillotti systems, it is not obvious the additional revenue would be sufficient to
et al., 2019; Federal Energy Regulatory Commission, 2020). However, offset higher FTM capital costs (Reiman et al., 2020; McCabe et al.,
other potential services DERs could provide are more difficult to reliably 2018; Cole et al., 2016).
quantify (e.g., the costs and benefits of DERs on distribution systems, as
they are highly complex and context-specific) (Denholm et al., 2014; 1.3. Evaluating renewable energy potential at the parcel-level
Horowitz et al., 2018). One leading example of a framework to quantify
the value of DER exports is New York state’s Value of Distributed Energy As the VDER framework defines locational value at a highly granular
Resources (VDER) regulation, which seeks to harmonize the locational level, we hypothesize there is substantial variance (Gooding et al., 2013)
and temporal value of exports across wholesale and retail scales (NYPSC, in the locational value of DERs across NYS that may not be captured
2017). VDER and similar frameworks offer the potential to alter the through the existing NEM framework (Case et al., 2018a). Sources of
historical paradigm of unidirectional power flow from centralized gen variance in locational value include DER siting availability, quality of
eration to one where DER adopters can become both consumers and wind and solar resources, utility territory and associated retail tariffs,
fair-value generators (Astoria, 2017). and whether DERs can access unique value streams such as the DRV and
One salient feature of NYS’s VDER framework is the unbundling of LSRV.
exports into multiple value streams, particularly the demand reduction Rather than applying a rastered (gridded) or clustering approach, we
value (DRV) (Section 2.6.6) and the locational system relief value evaluate siting availability and locational value for each unique parcel in
(LSRV) (Section 2.6.7), which correspond to the value of DERs in the state (n = 6.23 million).2 Our literature review did not identify any
deferring transmission and distribution infrastructure investments existing distributed wind and solar locational value studies at the parcel
respectively. These revenue streams only apply during high-demand level for an entire region, though others have studied spatial aspects of
periods and, in the case of LSRV, are only available within specifically renewable energy technical and economic potential (Brown et al., 2016;
designated distribution systems. The degree to which DERs can provide Lee et al., 2019). Most existing regional renewable energy potential
these services and their magnitude of value is still considered an open studies use rasterized cells with digital surface or digital elevation
question. models (Lopez et al., 2012; Sun et al., He and Kammen, Yushchenko
In this paper, we refer to the compensation of systems operating et al., 2018; Chow et al., 2014), though these approaches ignore the
under both NEM and VDER frameworks as “values.” However, it should impact of property ownership. Rasterized models particularly struggle
be emphasized only VDER frameworks are explicitly driven by the when applied to higher density areas because parcel size and geometry
theoretical value they can provide to the power system. Thus, although affects siting availability. Some parcel-scale analysis does exist for
VDER compensation represents value to both the customer and the microgrids (Mavromatidis et al., 2015), but none exists for large regions.
power system, NEM compensation represents value to only the Other studies have sought to assess the technical potential of rooftop
customer. solar at the building level using either lidar or aerial imagery (Mansouri
Kouhestani et al., 2019; Elshurafa and Muhsen, 2019, Sigrin and
Mooney, 2018).
1.2. Role for front-of-the-meter resources
We argue evaluating renewable energy potential at the parcel level is
needed to accurately assess DER locational value, particularly in urban
In addition to NEM versus VDER, another comparison is of behind-
and suburban settings. Parcel-level methods are better suited to
the-meter (BTM) and front-of-the-meter (FTM) configurations. Unlike
modeling the existing built environment and the decision-making of
BTM resources, FTM resources interconnect at the distribution or sub
individual investors than rasterized approaches. In the specific context
transmission level and their generation does not directly offset end users
of the VDER policy, a rasterized approach is insufficient to model
load. As a corollary, all generation from FTM systems is compensated
applicability of the LSRV and how site-specific load patterns contribute
under VDER, whereas for BTM-VDER systems, only nonconsumed gen
to VDER valuation. Furthermore, spatial granularity is needed to iden
eration is compensated under VDER.
tify high-value locations that could be masked through averaged results
(e.g., evaluating average VDER results at the utility or state level),
1 though it is less relevant for spatially-agnostic frameworks (e.g., NEM).
In this analysis, we use the term “framework” to loosely capture potential
methods of ascribing value to generation from DERs. This is distinct from a
The aim of such approaches is to identify sites with higher value to the
“compensation mechanism,” defined as comprising (1) a metering and billing power system and, ultimately, align investor interests with power
arrangement, (2) a retail tariff, and (3) a sell rate (Zinaman et al., 2017).
Compensation under a VOS framework could be described as a net billing
2
scheme, in which the sell rate varies temporally and spatially. A parcel is a contiguous piece of land, which may contain a building.
2
T. Bowen et al. Energy Policy 166 (2022) 112744
system value. the largest locational value and siting availability. Section 4 discusses
the primary implications of the work regarding locational value under
1.4. Contributions to literature VDER. Additional details on the methodology are available in the Sup
plemental Information.
In this article, we provide novel contributions to the literature
regarding the locational value of DERs as implemented in the New York 2. Methodology
state VDER framework. Specifically, we demonstrate the application of
parcel-based methods over rasterized and top-down approaches, which This analysis develops a parcel-level database of potential DER sites
inadequately represent correlations in land-use, siting availability, and in NYS and evaluates their potential for siting distributed solar or wind
locational value. This paper is one of few to analyze the VDER frame generators. For each parcel, we compare hourly generation profiles with
work in such depth and in such granularity. Many jurisdictions are (a) on-site load (for BTM frameworks) and (b) either the hourly values of
debating transitioning from NEM frameworks, and VDER offers one VDER components (for VDER frameworks) or retail tariff rates (for NEM
promising alternative to align compensation with value provided to the frameworks) to evaluate project economics.
power system. Our analysis of the VDER framework provides significant
insight into the impact of such transitions on customers which can 2.1. Data sources
inform ongoing discussions on DER compensation. Finally, we contrast
the value of DERs under both BTM and FTM configurations and Assembling a geographic database of parcels for an entire state was a
demonstrate the opportunity that VDER could offer FTM systems, an significant endeavor. The core data sets used include a commercially
opportunity that does not exist under NEM frameworks. available parcel database providing zoning, land-use, and other property
characteristics (Homeland Infrastructure Foundation-Level Data, 2020),
1.5. Research questions supplemented by data sets of different resolution. Wind resource data
were licensed from AWS TruePower at a 20-km resolution using
We address three research questions methods described in (Lantz et al., 2016). Rooftop area available for
solar development was sampled from county-level distributions of lidar
1. To what degree does wind and solar generation provide DRV and measurements (Kwasnik and Sigrin, 2019). Utility rate information was
LSRV value? How much do these components contribute to overall selected from the Utility Rate Database, considering the most popular
project revenue? tariff in each utility service territory for each sector (residential, com
mercial, and industrial) [Open Energy Information, 2020]. Geographic
We find that on average for all parcels across NYS, the LSRV and DRV boundaries of protected areas and easements were compiled using the U.
provide only a small portion of the overall value of BTM and FTM solar S. Geological Survey Protected Area Database (U.S. Geological Survey
PV and wind systems under the VDER framework (see Table 2). How (USGS) Gap Analysis Project (GAP), 2018). Consumption data were
ever, for select parcels, the combined DRV and LSRV can provide sig taken from the U.S. Energy Information Administration’s Residential
nificant value, presumably in more constrained areas of the power Energy Consumption Survey and its Commercial Buildings Energy
system. This finding indicates both the value of providing locationally Consumption Survey (EIA, 2008). Though our assembled database is
specific values to distributed resources aligned with power system needs comprehensive in many regards, it does not include parcel-level con
and the importance of evaluating these systems’ performance at a suf sumption data or feeder-level interconnection restrictions. No person
ficiently granular level. ally identifiable information was used in this study.
2. Does transitioning from NEM to VDER frameworks lead to reduced 2.2. Wind and solar siting
revenue for DER generators? Does it result in greater variance in
revenue? The siting and sizing of systems on parcels was intended to maximize
the system size on the parcel irrespective of load. For each parcel, we
We find that generators transitioning from BTM-NEM to BTM-VDER were able to compare the same system across valuation frameworks
and FTM frameworks on average suffer decreases in revenues (5.8% and (BTM-NEM, BTM-VDER, and FTM-VDER) and isolate differences in
7.5% for solar PV and 16.9% and 14.4% for wind) (see Section 3.2). We revenue. Constraints such as land-use restrictions lead all development
also find that while wind exhibits more variance in break-even costs in within protected areas to be excluded. For each eligible parcel, the solar
general (see Table 4 and Fig. 5), the impact of transitioning from NEM to and wind system sizing was independent based on the parcel’s
VDER on variance is utility-specific. characteristics.
For wind, we tested a variety of turbine rotor diameters and heights
3. How does VDER affect revenue for FTM systems? Are FTM systems to see whether they would clear the canopy coverage on the parcel while
able to be sited in areas of high locational value? meeting statewide setback requirements. Of the eligible wind systems,
we chose the largest system capacity. If the area of the parcel was larger
We find that although the developable potential under the FTM than 5 acres, we tested to see whether multiple turbines could be sited to
VDER framework is smaller than for NEM (see Table 3), there is still maximize the total installed capacity on the parcel. Although we did not
significant potential for both FTM solar PV and wind: approximately 20 model wake effects between the turbines, a power density limit of 3
GW for solar PV and 92 GW for wind in the ~2000 $/kW to ~4000 MW/km2 was applied to parcels with multiple turbines. Detail about
$/kW range. The answers to these questions are based on a snapshot in how the resource data were estimated at an 8760 resolution is provided
time of grid conditions, captured based on historical data for 2018. It by (Sigrin et al., 2016; Appendix B2).
should be noted that as the grid continues to evolve (i.e., more customers For solar, developable rooftop area was sampled from published
adopt DER and NYS transitions to cleaner utility-scale generation), the county-sector distributions derived from previous lidar measurements
value of new DER and consequently of VDER will also change. (Kwasnik and Sigrin, 2019). The tilt and azimuth of the rooftop pitch
The rest of the article is organized as follows. Section 2 describes our were similarly sampled. These samples were not matched on an address
methodology for assessing parcel data; determining siting availability basis, but the total area sampled was normalized to match the measured
for distributed wind and solar in BTM-NEM, BTM-VDER, or FTM county-level developable rooftop area. For parcels larger than 5 acres,
frameworks; and assessing their locational value. Section 3 describes our we allowed for ground-mounted solar PV installations sized to match the
results, which are organized around the intersection of the parcels with annual energy production of the selected wind system.
3
T. Bowen et al. Energy Policy 166 (2022) 112744
After excluding protected land-use applications and selecting only Economic potential is a subset of the technical or siting potential that
parcels with a nonzero siting potential for both solar and wind in meets or exceeds a target rate of return for economically viable gener
stallations, the number of eligible parcels was reduced from 6.23 million ating capacity, and it is influenced by both the revenues a generator can
to 1.04 million.3 This study focuses exclusively on sites capable of earn and the costs associated with building and operating a given
hosting both wind and solar PV systems in order to better enable a generator. Wind project costs are a function of turbine size and hub
parcel-to-parcel comparison of the two technologies. However, this height, and they were derived from (Sigrin et al., 2016). Solar costs are a
methodology may underestimate the absolute siting potential for each function of the system size and were derived from (National Renewable
technology throughout NYS. Energy Laboratory, 2019). In determining the project NPV of systems for
In addition to parcel-related constraints, the ability to site a given this study, the technology lifetime assumed for wind and solar systems
DER depends on the ability to interconnect it to the existing distribution was 30 years and the discount rate was set to be the nominal
system and the extent of distribution upgrades needed to safely inter weighted-average cost of capital. The weighted-average cost of capital
connect the system. Interconnection barriers to DER could arise for value used in this study was 7.7%, taken from the 2019 National
several reasons; for example, (Case et al., 2018b): Renewable Energy Laboratory’s Annual Technology Baseline for
land-based wind in 2018 (National Renewable Energy Laboratory,
1. The generator is located on an isolated network, which might cause 2019). In this analysis, we assumed all the initial capital investments for
protection equipment to trip if DER generation exceeded behind-the- a generator were made in Year 1, the year in which the system was
meter load. built.4
2. There is inadequate service capacity, in which the rating of existing
conductors delivering power to the building is lower than the ca
pacity of the DER. 2.6. Project valuation
3. There is inadequate local load, which could cause excess DER gen
eration to backflow and cause protection equipment to trip. Project valuation represents the sum of all value streams available to
a project under NEM and VDER frameworks. For NEM, the value stack
Given the limited availability of highly granular data on the hosting comprises offsetting self-consumption at the prevailing retail rate and
capacity of the NYS distribution system, we did not model discrete exported generation credited toward future consumption within the
interconnection limits. When siting, we did enforce a 5-MW intercon same year.
nection limit, which is the upper limit for distributed generators and VDER project valuation considers offset consumption value for BTM
energy storage systems provided by the NYS Public Service Commission frameworks but not for the FTM evaluation of parcels. The VDER
(Commission, 2017). framework has four additional components that are applicable to all
parcels: the hourly value of energy, an hourly allocation of capacity
2.3. Load Zones and utility territories value, an environmental value, and a DRV intended to capture periods of
peak demand within transmission-constrained areas. Additionally, there
For this study, all the major investor-owned utilities in NYS were is the LSRV, only available within utility-specified geographies, which is
evaluated for their potential to site DER systems and the value of those dispatchable by utilities to incentivize demand reduction (or genera
exports to the grid. As municipal utilities are not required to offer VDER tion), as needed. This study’s methodology and relevant input values for
as a compensation mechanism, they were excluded from consideration. calculating these value stack components were derived from the official
For a map of these utility territories see Figure A1 in Appendix A. New York State Energy Research and Development Authority’s Value
Stack Calculator, which in turn were based on the official VDER
compensation framework, using 2018 as the reference year (NYPSC,
2.4. Behind-the-meter load considerations
2019).5
A key underlying assumption of this study is that the values that the
Regardless of the interconnected system size, each parcel and tech
distributed systems under VDER receive remain constant over the sys
nology combination was compared under three different valuation
tem’s lifetime. This has been necessary given a lack of information on
frameworks: BTM-NEM, BTM-VDER, and FTM VDER. NEM refers to
future values. The validity of this assumption varies by component
crediting BTM generation in excess of on-site consumption exported to
value, as some values fluctuate year-to-year and others are fixed for a
the grid at the retail electricity rate. This credit can be used to offset
long period of time to provide revenue certainty to investors (see below).
consumption from the grid in the current, and often future, billing cycles
As more DER comes online, and as other broader changes take place (e.
(Zinaman et al., 2017). At the time of writing, NEM was available across
g., increased electrification and additional clean utility-scale genera
NYS, but it is expected to be replaced with the VDER framework. In both
tion), power system conditions will change. In a framework such as
the BTM-NEM and BTM-VDER frameworks, generation is first used to
VDER that seeks to pass information on local power system conditions
offset any BTM load before being exported. For BTM frameworks, load
on to DG owners, this ultimately means the price signals they see will
profiles were synthesized using normalized hourly electric consumption
also change. Thus, the results presented in this work provide only a
patterns derived from [Office of Energy Efficiency & Renewable Energy
snapshot of the distribution of high-value locations, which are certain to
(EERE), 2013] in combination with the average annual electricity load
change over time. Despite the limited ability to forecast future power
by building type.
system conditions, the results in this study provide insight into areas of
high value and a general sense for the impacts DG adopters will face as
2.5. Technology costs and net present value
4
T. Bowen et al. Energy Policy 166 (2022) 112744
they transition from NEM to VDER. Although these benefits do not directly accrue to the utility (e.g., they do
not offset infrastructure or fuel costs), they indirectly benefit society at
2.6.1. Value of self-consumption large and are compensated under policy regimes. Within VDER, the
The value of self-consumed generation (i.e., the avoided electricity monetary value for the environmental value was based on the higher of
consumption from the grid offset by generation from BTM systems) is either the Clean Energy Standard Tier 1 renewable energy certificate
determined by the relevant retail tariff rate. Retail tariffs were taken prices or the social cost of carbon calculated by the New York Depart
from the Utility Rate Database [Open Energy Information, 2020] and ment of Public Services (NYSERDA, 2019). The renewable energy cer
representative rates were assigned to each customer based on their tificate price was used for this analysis to compare the environmental
sector (e.g., residential, commercial, or industrial). Sector-specific values of the BTM and FTM resources more easily, and for 2018 was set
representative rates were mapped to individual parcels based on the to $17.01 per megawatt-hour of generation (NYSERDA, 2020). Although
given parcel’s land-use type. The amount of self-consumption was the price of renewable energy certificates can fluctuate throughout the
calculated by clipping the system’s generation profile to the parcel’s year, the value was fixed over the lifetime of the system for this analysis
load (i.e., the hourly amount of generation offsetting consumption). The which is consistent with the VDER framework.
total electricity bill with the system was then deducted from the calcu
lated electricity bill, absent any system to isolate the annual revenue 2.6.6. Demand reduction value
from self-consumption. Similar to the avoided capacity investment value, the DRV is a
measure of the ability of DER exports to reduce utility infrastructure
2.6.2. Net metering value investments by reducing the load utilities must meet during peak pe
Although FTM frameworks were only evaluated using the VDER riods. Rather than addressing the fixed costs associated with the gen
framework, BTM frameworks were evaluated under both NEM and eration fleet, however, the DRV expresses the value of reducing fixed
VDER frameworks to compare the resulting value. Under the NEM costs associated with the transmission and distribution capacity needed
frameworks, DER generation in excess of consumer demand exported to to deliver power.
the grid was credited at the retail tariff rate that the customer pays to Both the valid hours during which DER exports qualify for the DRV
consume electricity (Zinaman et al., 2017).6 and as well as the monetary value associated with exports are utility-
specific. And while the DRV awarded to new systems can vary year to
2.6.3. Avoided energy value year, once a system is installed, its DRV is locked in for 10 years. For this
The avoided energy value represents the variable costs, such as fuel analysis, the utility-specific valid hours and monetary value were taken
costs or operation and maintenance costs, avoided when DG offsets directly from the Value Stack Order (NYPSC, 2019). See Section B.2 of
generation from centralized units. The net energy benefits associated the Appendix for more information on the DRV and how its rates and
with DER exports are quantified in VDER via a generator’s ability to times varied between, and in some cases within, utilities.
reduce the purchases load-serving entities need to make from the elec
tricity market by meeting demand locally. Specifically, we calculated 2.6.7. Locational system relief value
the product of the hourly electricity exports to the grid with the equiv The LSRV measures the value of a DER’s export to reduce congestion
alent day-ahead market price for the New York Independent System at specific points by injecting power near demand. This value is limited
Operator (NYISO) load zone from which the DER exports. The day- not only to specific time periods but also to specific subsections of the
ahead market prices were taken from (NYISO, 2020b) for 2018. In power system that utilities identify as experiencing significant conges
practice, the avoided energy value changes hourly and by NYISO load tion. Only exports originating from within these LSRV zones can qualify
zone. for LSRV compensation. Similar to the DRV, the LSRV awarded to new
systems can vary year to year, but once a system is installed, its LSRV is
2.6.4. Avoided capacity investment value locked in for 10 years. Unlike the DRV or capacity value, the periods
The avoided capacity investment value represents the costs utilities during which exports qualify are determined dynamically by utilities
avoid when DERs can be reliably expected to help meet peak demand, through “calls.” Utilities are required to make at least 10 calls per year
thereby reducing a utility’s obligation to build additional capacity or and each call must be at least 1 h in duration and no more than 4 h.
procure it from a capacity auction (as is done for investor-owned utilities Unlike the DRV, only the minimum instantaneous generation within the
in NYS). As only a select number of hours contribute to peak demand and given call was applied to the $/kW-call value for the duration of the call.
determine capacity auction requirements, only DER exports within these We simulate LSRV calls by taking the 10 days with the highest peak load
hours can provide capacity value. The VDER framework defines these for a given utility and creating a 4-h period around each call with the
periods as those in which the entire NYISO territory is likely to experi highest cumulative load across the 4 h. For an illustration of a LSRV
ence peak demand, defined in the latest Value Stack Order (NYPSC, zone, see Figure B1 of Appendix B.1.
2019). The capacity value of exports during these hours was determined
by the capacity auction for the NYISO load zone from which the DER was 2.6.8. Avoided transmission and distribution losses value
exporting (NYISO, 2020a). In practice, the avoided capacity investment Compared to centralized generation, generators located on the dis
value remains fixed throughout a given year but changes by NYISO load tribution system suffer fewer losses when meeting customer demand, as
zone and varies year-to-year based on actual capacity market spot the power must not travel as far. This is particularly true for BTM sys
prices. tems satisfying on-site customer demand. To account for these reduced
losses, the hourly generation profiles used to calculate energy and ca
2.6.5. Environmental value pacity values are scaled up by the avoided loss percentage for that
The environmental value captures the benefits that accrue to society utility. FTM evaluations only receive a transmission loss multiplier,
when renewable distributed generation offsets fossil-fuel generation. whereas BTM receive both a transmission and distribution loss multi
plier (NYSERDA, 2019).
6
In 2020, New York established a customer benefit contribution charge 3. Results
[$/kWDC] to reduce cost shifting and ensure customers with distributed gen
eration under the NEM framework continued to contribute to public benefit Our analysis focuses on understanding the drivers of DER locational
programs (NYPSC, 2020). This charge was not included in this analysis, as it value under different frameworks, differences therein between NEM and
uses price data and other data from the historical year 2018. VDER frameworks and BTM and FTM configurations, and the resulting
5
T. Bowen et al. Energy Policy 166 (2022) 112744
investment opportunities. In particular, we examine the amount of DER parcels in NYS for each technology were considered “high value.” For
potential (3.1); total DER compensation under VDER as compared to NYS, the cumulative siting potential for FTM systems in high-value lo
NEM (3.2); the specific components in the value stack (3.3) with cations was 7.42 GW for solar PV (achieving more than $0.089/kWh)
particular focus on the value of deferred transmission and distribution and 5.60 GW for wind (achieving more than $0.070/kWh). This in
(T&D) investments locational value; and the resulting economic po dicates that even under VDER-styled compensation, there would be
tential for DERs (3.4), with a focus on whether VDER increases variance significant developable potential for both solar PV and wind FTM
in project returns. Overarching this is our thesis that locational value systems.
frameworks, unlike NEM, provide greater opportunity for project de
velopers to target sites of higher value, especially for midscale FTM
systems. 3.2. Total per-kWh values
6
T. Bowen et al. Energy Policy 166 (2022) 112744
Fig. 1. Cumulative distribution function for total per-kWh values for solar PV (left) and wind (right) for the BTM-NEM and FTM frameworks in NYS. Note the
different x-axis ranges for solar PV and wind technologies.
retail tariffs (for BTM configurations), nodal energy and capacity prices, broadly similar, given that both are based on similar retail rates. For
and monetization of DRV and LSRV components (for VDER frame VDER frameworks, the Energy and Environmental components made
works). Fig. 2 shows the total per-kWh value for solar and wind tech significant contributions to the total per-kWh value. For FTM systems,
nologies and BTM-NEM and FTM configurations. The large map to the which do not offset BTM consumption, the energy component is
left shows the total per-kWh value for wind, FTM. The three maps on the particularly substantial, accounting for over 50% of per-kWh value. For
right show the differences between the total per-kWh value for wind and VDER frameworks, on average, the Energy, Environmental, and, in the
FTM and the following configurations (from top to bottom): solar and BTM configuration, Consumption values represent 80%–95% of the total
FTM, wind and BTM-NEM, and solar BTM-NEM. The large map for wind per-kWh value for wind and solar generators.
and FTM shows a clear concentration of high-value parcels in the In contrast, both solar and wind on average derived modest value
southeast, particularly in LIPA. Compared to wind and FTM, solar PV from the Capacity, DRV, and LSRV components under VDER. Each of
and FTM tend to have a higher total per-kWh value, as shown in the these components is time-constrained in the sense that they could only
predominantly blue-green upper-right map, particularly in Consolidated be earned in certain windows. Notably, the solar per-kWh value for each
Edison (CONED). Conversely, BTM-NEM parcels, both solar and wind, component was 2–4 times larger in magnitude than wind, indicating the
are typically of a higher value than FTM, with particularly higher values windows for eligibility for these time-constrained values align substan
in LIPA. tially better with solar generation than wind. Conversely, for both BTM
In particular, we note that: and FTM configurations, time-unconstrained components (i.e., those
earned in all hours) such as Energy and Environmental play a larger role
(1) Values under the BTM-NEM frameworks are significantly higher for wind than solar PV, even though the absolute value is smaller for
for solar PV and wind (0.099 and 0.097 respectively) than for the wind.
BTM-VDER frameworks (0.069 and 0.056). This analysis only covered nondispatchable generators without en
(2) Values under the FTM framework are broadly higher for solar ergy storage and assumed that only generation in excess of load (for
than for wind, specifically in CONED. BTM frameworks) was exported. Therefore, it is not surprising that such
(3) LIPA and CONED territories in southeast NYS have a significantly generators would not see significant value from these components. More
higher value for DER generators than other utility territories. (1) strategic operation of these distributed generators, especially if com
For solar and BTM-NEM, the top three utilities by average total bined with energy storage, could help such systems capture more of
per-kWh value are LIPA (0.203), CONED (NYC) (0.149), and ORU these limited eligibility component values.
(0.137). (2) For solar and FTM the top three are CONED (West One of the guiding principles of VDER is to align power system needs
chester) (0.128), CONED (NYC) (0.116), and LIPA (0.091). (3) with customer compensation. LSRV and DRV values are structured to
For wind and BTM-NEM, the top three are LIPA (0.199), CHGE compensate for “nonwires” alternatives to distribution and transmission
(0.135), and ORU (0.134) [CONED (Westchester) is fourth and upgrades and their associated fixed infrastructure costs. We find that,
CONED (NYC) is seventh]. (4) For wind and FTM the top three are combined, these components provide $4–$7/MWh for wind and $11–
CONED (NYC) (0.078), LIPA (0.073), and CONED (Westchester) $18/MWh for solar generators in value, which partially refutes the hy
(0.065). pothesis that these components would be important value streams for
(4) A comparison of Fig. 2 and Table 1 shows significant potential to eligible generators. For most systems, the value from DRV and LSRV
site DERs in high-value areas such as LIPA (17.0 GW and 8.9 GW components is unlikely to spur significant additional investment.
for solar and wind respectively), CONED (Westchester) (3.3 GW However, although the LSRV and DRV values are not particularly
and 2.3 GW), and ORU (12.4 GW and 9.9 GW). valuable on average, they do provide substantial value in select loca
tions (Fig. 3).10 Among the top 5% of sites, the combined LSRV and DRV
3.3. Component per-kWh values value for solar PV ranged from 0.035 to 0.089 $/kWh, which is well
above the average. We estimate 3.35 GW of siting potential for solar
Next, we explore the magnitude and coincidence of each individual generators with a combined LSRV and DRV value above $0.05/MWh.
component of value under each of the configuration frameworks by However, the top 5% contributions of these two components are
technology (Table 2). While the total per-kWh values for the BTM-NEM significantly smaller for wind generators: 0.008—0.025 $/kWh. For
framework are largely a function of the retail rate, the BTM-VDER and wind, 0.28 GW derive at least $0.015/kWh from the combined LSRV and
FTM frameworks’ values are driven by a series of distinct “component DRV. These outliers show that parcels within the LSRV and DRV
values” (see Section 2.6).
Several trends are apparent from Table 2. First, by definition, BTM-
NEM systems derive value through the NEM and Consumption compo 10
The FTM framework was selected to avoid complications with behind-the-
nents exclusively (i.e., generation exported to the grid and self- meter load patterns interfering with the generator’s ability to achieve the
consumed respectively). Solar and wind BTM-NEM per-kWh values are component values.
7
T. Bowen et al. Energy Policy 166 (2022) 112744
Fig. 2. Rasterized map of total per kWh values for wind, FTM (main) and differences for solar PV, FTM (top right); wind BTM-NEM (middle right); and solar PV BTM-
NEM (bottom right) for New York state.
Table 2
Average Component per-kWh Value and Contribution to Total per-kWh Value by Framework and Technology.
Component Solar PV Wind
Consumption 0.023 (24.27%) 0.023 (24.57%) 0.000 (0.00%) 0.023 (24.86%) 0.023 (27.51%) 0.000 (0.00%)
NEM 0.076 (75.70%) 0.000 (0.00%) 0.000 (0.00%) 0.067 (75.12%) 0.000 (0.00%) 0.000 (0.00%)
Energy 0.000 (0.00%) 0.030 (42.46%) 0.037 (54.29%) 0.000 (0.00%) 0.027 (45.73%) 0.035 (61.63%)
Capacity 0.000 (0.00%) 0.004 (5.39%) 0.005 (7.55%) 0.000 (0.00%) 0.001 (1.71%) 0.002 (2.65%)
DRV 0.000 (0.00%) 0.006 (8.36%) 0.009 (12.13%) 0.000 (0.00%) 0.002 (2.90%) 0.003 (4.62%)
Environmental 0.000 (0.00%) 0.013 (18.82%) 0.017 (25.34%) 0.000 (0.00%) 0.013 (21.89%) 0.017 (30.69%)
LSRVa 0.000 (0.00%) 0.005 (6.32%) 0.009 (11.25%) 0.000 (0.00%) 0.002 (3.97%) 0.004 (6.33%)
Totalb 0:099 (100:00%) 0:079 (100:00%) 0:069 (100:00%) 0:097 (100:00%) 0:065 (100:00%) 0:056 (100:00%)
a
For the “LSRV” component, the averages are only for those parcels in qualifying LSRV zones.
b
Please note that as these are average values across all relevant parcels, the sum of the component values may not equal the Total.
zones—especially those suitable for solar project development—can 3.4. Break-even costs
likely receive significantly higher overall project value than the average
system could. Our last results consider the degree to which DER deployment is
Many of these high-value sites are located in Consolidated Edison’s economic under the frameworks considered, and the impact of the VDER
DRV zone, which offers 0.854 $/kWh for the hours in which generation framework on heterogeneity of project returns as compared to NEM.
is eligible (see Table B1 in Appendix B.2). Similarly, the LIPA territory Specifically, we evaluate the break-even cost for each parcel, defined as
has some of the highest wind resource potential in the state, and offers a the minimum capital cost ($/kW) needed for the system to achieve a
high LSRV compensation (NYSERDA, 2019). Thus, although most pro positive NPV, or the transition point whereby the system becomes
jects do not derive substantial value from the LSRV and DRV compo economically viable. Higher break-even costs indicate lucrative parcels
nents, there is significant variability in the distribution. Qualification for in which generators are more profitable on a per-kW basis (or could
high LSRV and DRV values is likely to spur targeted investment at these tolerate higher capital costs and still maintain a positive NPV).
sites. Solving for the system break-even cost requires an initialization of
the estimated break-even cost, defined as “CAPEXEstimated”. This
8
T. Bowen et al. Energy Policy 166 (2022) 112744
Fig. 3. Rasterized map of combined LSRV and DRV per-kWh values for solar PV (top) and wind (bottom) for the FTM frameworks for NYS, for the top 5% of values,
with a focus on specific utilities.
estimated capital cost ($/kW) is then used to calculate the system NPV. technologies and the BTM-NEM and FTM frameworks (Fig. 4). The
From there, the break-even cost formula linearly perturbates from the supply curves provide an ordered ranking of all parcels to show how
NPV to find the break-even CAPEX. For example, if a 5 kW solar system each parcel contributes to the cumulative developable potential (here
has a NPV of -$500 using an “estimated” cost of $2000/kW, this implies represented by positive break-even costs). These are useful for priori
that the system is uneconomic at $2000/kW and would have a break- tizing economic development, or comparing the developable potential
even cost of $1900/kW. Estimates of current distributed wind and across technologies, frameworks, or territories. Furthermore, the supply
solar technology costs are from Lantz et al., (2016) and National curves allow for an estimate of economic potential by comparing the x-
Renewable Energy Laboratory (2019) respectively. Equation (1) de position of a point along the curve at a given y-coordinate, which rep
scribes how the capital costs, system size, and original NPV (calculated resents the assumed CAPEX value.
as explained in Section 2.5) are used to calculate the break-even cost. Consistent with prior results examining the per-kWh value of DERs
Equation (1). Calculation of the break-even cost ($/kW) using esti under the NEM and VDER frameworks, we generally find i) transitioning
mated capital expenditures (CAPEX), NPV, and system size: to VDER leads to poorer economics for DERs than NEM, ii) there is a
higher economic opportunity for solar distributed generation than
NPV
CAPEXBreakEven = CAPEXEstimated + distributed wind, and iii) there is a smaller range of break-even costs
System Size
under VDER than NEM. As with the cumulative siting potential, the
The break-even cost metric for analysis is preferable in this instance
cumulative developable potential (systems with a break-even cost above
to NPV, as it is not indexed to a specific technology cost at a moment in
0 $/kW) for solar is higher than for wind (approximately 725 GW versus
time. DER capital costs are both projected to continue to decline and can
475 GW), though these result in a similar amount of annual generation
vary substantially based on the system design, so the break-even cost is a
(GWh).11 In general, for solar PV, the BTM-NEM framework has more
relatively agnostic way to evaluate them. Although the break-even cost
developable potential than FTM and a wider range (from ~0 $/kW –
has advantages over NPV metrics, it is not a measure of economic po
~3500 $/kW for BTM-NEM versus 400 $/kW – ~2500 $/kW for FTM)
tential, but rather an estimate to determine under which conditions a
(Table 3). The average break-even costs for solar PV were 1413.33 $/kW
technology in a given location would be economically feasible. There
and 996.26 $/kW for the BTM-NEM and FTM frameworks respectively.
fore, we refer to “developable” potential rather than the “economic”
As with solar PV, for wind the BTM-NEM framework had more
potential. We decline to provide estimates of economic potential, as
these depend on assumptions about CAPEX costs, which are constantly
changing and, in the case of distributed wind, difficult to estimate. As
11
noted earlier, because distributed wind generators have higher capacity For solar the break-even capacity is identical across both frameworks, but
factors, they tend to have higher break-even costs. for wind some parcels had a sufficiently low capacity factor that, even with a
A supply curve of break-even costs was generated for both $0/kW CAPEX, fixed operating costs prevented a positive NPV. These sites were
excluded from consideration in this section.
9
T. Bowen et al. Energy Policy 166 (2022) 112744
Fig. 4. Supply curves of break-even costs for solar PV (left) and wind (right) for the BTM-NEM and FTM frameworks in NYS, for positive break-even costs. Please note
the different x-axis ranges for solar PV and wind technologies.
Fig. 5. Violin plots of the break-even costs ($/kW) for solar (top) and wind (bottom) across all frameworks for each utility. Note that for violin plots, the width of the
plot at a given y-axis value is proportional to the frequency of that outcome.
10
T. Bowen et al. Energy Policy 166 (2022) 112744
Table 4 this study are unique to NYS, the general trend of high-value compo
Coefficient of Variance for Break-Even Costs by Utility and Technology for the nents incentivizing deployment in constrained areas of the grid is likely
BTM-NEM and FTM Frameworks. to be more universal. Allowing FTM systems to access the full value of
Utility Solar PV Wind their generation through a clear and consistent framework such as VDER
NEMa FTM NEMa FTM
reveals a large opportunity for these systems to contribute to the power
system, which is not available under NEM frameworks. Finally, from a
CHGE 0.241 0.074 0.425 0.531
methodological standpoint, and applicable well beyond NYS, this study
CONED-NYC 0.270 0.088 0.524 0.463
CONED-WCHSTR 0.264 0.373 0.351 0.360 revealed the power and importance of evaluating DER economics at the
LIPA 0.086 0.106 0.331 0.413 most granular level possible, helping reveal geographic and temporal
NGRID 0.457 0.087 0.634 0.472 trends not accessible through aggregated approaches.
NYSEG-LH 0.240 0.405 0.343 0.375
NYSEG-NYA 0.139 0.084 0.389 0.513
ORU 0.275 0.103 0.449 0.482 4.1. Significant opportunity for DERs to contribute to state-wide goals
RGE 0.070 0.084 0.309 0.392
a Both distributed solar PV and wind, on a technical basis, could
NEM refers to the BTM-NEM framework.
contribute substantially to NYS’s decarbonization goal of 100% clean
energy by 2040. As noted earlier, the combined technical potential for
($0.091/kWh), variability increased for both wind and solar projects.
distributed solar and wind is approximately 900 TWh, or nearly 6 times
One method for viewing population distributions is through violin
the entire statewide electricity consumed in 2019. For example, hy
plots, wherein the width is proportional to the frequency of the outcome.
pothesizing that 25% (40 TWh) of the overall NYS decarbonized load is
Fig. 5 shows violin plots for the break-even costs for wind and solar PV
met by DERs, we can identify the most suitable sites to meet this goal.
for all frameworks for each utility in NYS. This figure demonstrates that
Starting by filtering the supply curve on only the most profitable 40 TWh
wind technologies exhibited more variance in the break-even costs than
of DER generators and for solar FTM projects, the minimum per-kWh
solar (also visible in the supply curves, Fig. 4).
value is $0.081/kWh. These values are substantially higher than
Fig. 5 also demonstrates there is significant inter-utility variance in
compensation under wholesale markets or via power purchase agree
the value of DERs. The sources of variance include explicit differences
ments and should incentivize substantial DER investment as a fraction of
such as the amount of population served, renewable resource quality,
NYS total demand in 2019.12
and service territory area, to the design of retail rates to recover revenue,
Also, the methods developed herein enable a new capability to pre
to more subtle differences in the implementation of the VDER policy.
cisely evaluate which DER sites might best contribute to deployment
Two general trends we observe are that DER compensation is correlated
goals based on technoeconomic feasibility. For instance, approximately
with grid constraints (i.e. higher energy, capacity and DRV/LSRV values
23.2 TWh of the hypothetical 40-TWh goal would be sited in LIPA, 8.3
as one approaches the more constrained areas of NYC and Long Island)
TWh in National Grid, 4.8 TWh in Consolidated Edison, and 3.7 TWh in
(see Tables A1 and A2 as well as Figures A1 and A2). Second, the specific
all other utilities. Grouped by land use, the modal land-use types were
DRV values and hours of generation that qualify for compensation under
vacant plots (7.0 TWh), followed by 6.0 TWh for residential condos, 3.0
these mechanisms vary significantly (see Table B1). Understanding the
TWh on single-family residential properties, and 24.0 TWh on all other
variation of DER compensation is a critical research aim for this paper,
types. These tools would allow policymakers to iteratively define goals
as one key aspect of the VDER policy is introducing heterogeneity in the
for the contribution of DERs to future power system and evaluate
spatial and temporal value of DER generation that is better aligned with
possible deployment trends. Currently, these figures may actually un
system value.
derestimate the developable potential in NYS, as only parcels capable of
siting both technologies were evaluated. Future work could expand to
4. Conclusion and broader U.S. implications
include parcels that can only site one technology for a more compre
hensive estimate.
This analysis focused on the impact of theoretical DER systems
installed in NYS under VDER, but it revealed trends that are broadly
4.2. Comparisons of NEM and VDER
applicable to distributed generators in most jurisdictions in the United
States and elsewhere. There is a tremendous opportunity for DERs to
Under NEM valuation frameworks, the per-kWh revenue is similar
contribute to policy ambitions for clean energy generation that can be
for projects of different technologies and geographies, as the temporal-
tapped by properly aligning incentives and addressing interconnection
spatial value of energy is not considered. Historically, this similarity
barriers (which were not a focus of this study). Furthermore, as more DG
has led to DER adoption trends driven by socio-demographic trends,
comes online, there may be a shift away from generous compensation
independent of factors such as transmission and distribution grid con
mechanisms such as NEM toward more granular, reflective mechanisms
straints or the internodal wholesale value of energy. In contrast, loca
like VDER, which can help align investment decisions with power sys
tional frameworks like VDER compensate generation coincident with
tem needs. In practice, policymakers must balance a variety of objec
periods of grid scarcity. Put another way, the VDER framework aligns
tives, some of which may at times compete (such as providing economic
grid and project developer interests to deploy DERs to sites with the
signals and enabling equitable uptake of DER). The evolution of DER
greatest value to the grid.
compensation frameworks will necessarily be influenced by the trade-
This alignment comes with the expense of decreases in DER
offs policymakers choose to make between these different policy goals.
compensation relative to NEM. Our analysis shows that on average, the
This study revealed a trend likely applicable outside of NYS: gener
per-kWh value for solar PV generators decreases by 5.8% and 7.5% for a
ators on average will see declines in their compensation during the
parcel when transitioning from NEM to BTM-VDER and FTM, respec
transition from NEM to VDER-like mechanisms. Significant variance in
tively, and declines for distributed wind are even larger (16.9% to BTM-
project economics indicate there will be projects that are more economic
VDER and 14.4% for FTM). However, the mean level of compensation
under cost-reflective VDER-like mechanisms than under NEM. While
can be a misleading metric, as there is substantial variance in the project
time-invariant components (Energy, Environmental, and Consumption)
will likely play the largest role in compensating DG on average, more
constrained components (Capacity, DRV, and LSRV) can be significant 12
Note that this calculation is based on the 2019 consumption, and 2040
drivers of investment for DG in high-value areas, driving deployment
consumption could differ substantially, which is beyond the scope of this work.
where it is most needed for the grid. While the individual components in
Also, it only considers energy served and not meeting peak demand.
11
T. Bowen et al. Energy Policy 166 (2022) 112744
revenue. For instance, we model at least 20 GW of FTM PV with a break- utility revenue sufficiency and prevent a shift in the burden of paying for
even cost of >$2000/kW and 23 GW of FTM wind with a break-even cost fixed infrastructure costs from adopting to nonadopting customers. For
of >$3000/kW, both of which are competitive with current best-in-class these reasons, FTM systems are largely inconsistent with NEM-
project costs. These shifts are likely to incentivize larger DER systems framework-styled compensation, as there is no BTM load to credit and
that can benefit from economies of scale. Similarly, VDER may dis they have historically been deployed either as utility-sponsored “com
incentivize small-scale DERs, which are well known to have high munity” projects or wholesale merchant plants. Under VDER, however,
customer acquisition costs (Tegen, 2016; O’Shaughnessy, 2018). Under there is a clear framework for investors to evaluate FTM value. This
VDER, customer acquisition is likely to be more complex because of the analysis shows that there is substantial siting potential for FTM systems
increased variability and data requirements between projects. Tools that in high-value locations under VDER, with 7.42 GW of solar and 5.60 GW
can analyze the value of DERs to customers and the power system in high of wind potential capable of achieving at least $0.070/kWh. Additional
geospatial and temporal fidelity will be essential to efficiently direct factors that could shift the balance from BTM to FTM systems are: i) the
investment. decrease in the per-kWh value, which motivates economies of scale; ii)
the increase of the maximum interconnection size to 5 MW; and iii)
4.3. Deferred T&D value is modest for most, substantial for some higher heterogeneity in locational value, which discourages deployment
in arbitrary locations. FTM systems—disconnected from load but
One of the most contentious aspects of DERs is their ability (or lack interconnected at the distribution level—could prove to be a high value
thereof) to defer transmission and distribution investments needed to and rapidly expanding market segment.
meet growth in peak demand and energy served. Because these calcu
lations are data-intensive and often idiosyncratic to a particular power Declaration of competing interest
system, generalization on this topic remains elusive. The VDER frame
work provides clarity by providing a transparent algorithm for assessing The authors declare that they have no known competing financial
deferred T&D value via the DRV and LSRV value stack components. We interests or personal relationships that could have appeared to influence
find that the DRV and LSRV components comprise a negligible portion of the work reported in this paper.
the total per-kWh value for most eligible systems. However, looking at
the top 5% of combined LSRV and DRV component value (Fig. 3), there Acknowledgements
are areas where the LSRV and DRV components provide significant
value. This work was authored by the National Renewable Energy Labo
As the LSRV and DRV (as well as the capacity) components are only ratory (NREL), operated by Alliance for Sustainable Energy, LLC, for the
earned in a select few hours of a year, they are sensitive to underlying U.S. Department of Energy (DOE) under Contract No. DE-AC36-
load patterns and could potentially be missed if energy from the 08GO28308. Funding was provided by the U.S. Department of Energy
distributed generator is used to meet the BTM load instead. There may Office of Energy Efficiency and Renewable Energy Wind Energy Tech
be additional potential for battery storage coupled with distributed nologies Office. The views expressed in the article do not necessarily
generation to supply generation during these market signals. Although represent the views of the DOE or the U.S. Government. The U.S. Gov
the highest value areas for LSRV and DRV are currently concentrated in ernment retains, and the publisher by accepting the article for publi
Consolidated Edison for solar PV (where there is high compensation and cation acknowledges that the U.S. Government retains, a nonexclusive,
the DRV windows naturally align with solar PV generating hours), and paid-up, irrevocable, worldwide license to publish or reproduce the
the LIPA for wind, with the addition of storage more areas could prove to published form of this work, or allow others to do so, for U.S. Govern
be profitable. ment purposes. This research was performed using computational re
sources sponsored by DOE’s Office of Energy Efficiency and Renewable
4.4. VDER and potential for FTM projects Energy and located at NREL.
The authors thank Billy Roberts (NREL) for preparing maps pre
Based on our analysis, the transition to VDER is likely to incentivize sented in the article, Margaret Mulhearn (NREL) for conducting GIS
growth of DERs deployed under front-of-the-meter configurations if they analysis to encode the LSRV zone boundaries, Donna Heimiller (NREL)
are eligible for compensation. Net-metering arrangements typically for assistance in procuring the parcel data set, and Schuyler Matterson
restrict system sizes to annually generate an approximately equal and Luke Förster (New York State Energy and Research and Develop
quantity to the customer’s load. These rules are intended to help ensure ment Authority) for interpreting the VDER framework.
For this study, we evaluated all the larger utility territories (excluding municipal utilities) for their potential to site solar PV and wind generators
for BTM-NEM, BTM-VDER, and FTM-VDER frameworks. As municipal utilities are not required to offer VDER as a tariff/compensation mechanism,
they were excluded from consideration. Figure A1 shows the major utility territories in New York state.
12
T. Bowen et al. Energy Policy 166 (2022) 112744
Fig. A1. Major New York utility territories, with municipal utilities, used in this analysis. Source: Government of New York (2020).
Table A1
Factors of Adjustment Based on Transmission and Distribution Losses, DRV and LSRV Values by New York Utility Territory for 2018. Source:
NYSERDA (2019).
Q1 Median Q3
13
T. Bowen et al. Energy Policy 166 (2022) 112744
Table A2
Day-Ahead LBMP and Capacity Prices by NYISO Load Zone for 2018.a Source: NYISO (2020b).
Q1 Median Q3
14
T. Bowen et al. Energy Policy 166 (2022) 112744
Fig. B2. The DRV Subsections of the Consolidated Edison Utility Territory.
Table B1
DRV Values and Time Windows for New York Utilities.
CONEDa
A 199.4 11:00–15:00 June 24—September 15 0.854
B 199.4 14:00–18:00 June 24—September 15 0.854
C 199.4 16:00–20:00 June 24—September 15 0.854
D 199.4 19:00–23:00 June 24—September 15 0.854
ORU 64.78 14:00–19:00 June 24—September 15 0.222
CHGE 14.55 14:00–19:00 June 24—September 15 0.050
(continued on next page)
15
T. Bowen et al. Energy Policy 166 (2022) 112744
Table B1 (continued )
Utility Annual Value( Hour Window Date Window DRV Value(
$/kW-year) nonholiday weekend hours $/kWh)
References Fitzgerald, G., Mandel, J., Morris, J., Hervé, T., 2015. The Economics of Battery Energy
Storage. Oct. Rocky Mountain Institute, Boulder, CO. Technical Report. https://rmi.
org/insight/economics-battery-energy-storage/.
Ackermann, T., Andersson, G., Söder, L., 2001. Distributed generation: a definition. Apr
Gooding, J., Edwards, H., Giesekam, J., Crook, R., 2013. Solar city indicator: a
Elec. Power Syst. Res. 57 (3), 195–204. http://www.sciencedirect.com/science/artic
methodology to predict city level PV installed capacity by combining physical
le/pii/S0378779601001018.
capacity and socio-economic factors, 95, pp. 325–335. http://www.sciencedirect.co
Allen, A., 2014. Voltage impacts of utility-scale distributed wind. Technical Report
m/science/article/pii/S0038092X13002570.
NREL/TP-5D00-61825, NREL, Golden, CO. URL. https://www.nrel.gov/docs/fy14os
Government of New York, 2020. NYS electric utility service territories. URL. https://data
ti/61825.pdf.
.ny.gov/Energy-Environment/NYS-Electric-Utility-Service-Territories/q5m9-rahr.
Allen, A., Zhang, Y.C., Hodge, B.-M., Sep. 2013. Impact of Increasing Distributed Wind
Hansen, L., Lacy, V., Glick, D., 2013. A review of solar PV benefit & cost studies. Sep,
Power and Wind Turbine Siting on Rural Distribution Feeder Voltage Profiles. NREL,
Technical Report, Rocky Mountain Institute, Boulder, CO, 2nd Edition. https://pscdo
London, U.K. https://pdfs.semanticscholar.org/6453/97399c44c724b070dd02ca5c
cs.utah.gov/electric/14docs/14035114/263609ExASierraClubInitCommEx1RMIMe
1f1880dc9612.pdf.
taAnaly2-6-2015.pdf.
Astoria, R., 2017. On the radicality of New York’s reforming the energy vision. Jun
Harari, S., Kaufman, N., 2017. Assessing the Value of Distributed Solar. Tech. Rep. Sep.
Electr. J. 30 (5), 54–58. http://www.sciencedirect.com/science/article/pii/
Yale Center for Business and the Environment, New Haven, CT. https://cbey.yale.
S1040619017301070.
edu/sites/default/files/2019-10/Distributed%20Solar_FINAL.pdf.
Bonbright, J.C., 1961. Principles of Public Utility Rates, first ed. Columbia University
He, G., Kammen, D.M.. Where, when and how much solar is available? A provincial-scale
Press, New York. URL. https://www.raponline.org/wp-content/uploads/2016/
solar resource assessment for China 85, 74–82. http://www.sciencedirect.com/sci
05/powellgoldstein-bonbright-principlesofpublicutilityrates-1960-10-10.pdf.
ence/article/pii/S0960148115300501.
Brown, A., Beiter, P., Heimiller, D., Davidson, C., Denholm, P., Melius, J., Lopez, A.,
Hess, D.J., Lee, D., Apr, 2020. Energy decentralization in California and New York:
Hettinger, D., Mulcahy, D., Porro, G., Aug. 2016. Estimating renewable energy
conflicts in the politics of shared solar and community choice. Renew. Sustain.
economic potential in the United States: methodology and initial results. NREL TP
Energy Rev. 121, 109716. http://www.sciencedirect.com/science/article/pii/
64503. URL. http://www.nrel.gov/docs/fy15osti/64503.pdf.
S1364032120300149.
Carlisle, J.E., Solan, D., Kane, S.L., Joe, J., 2016. Utility-scale solar and public attitudes
Hogan, W.W., 2013. Electricity scarcity pricing through operating reserves. Apr
toward siting: a critical examination of proximity. Land Use Pol. 58, 491–501. Dec.
Economics of Energy & Environmental Policy 2 (2). http://www.iaee.org/en/publ
http://www.sciencedirect.com/science/article/pii/S0264837716303738.
ications/eeeparticle.aspx?id=48.
Case, T., Liburd, S., Reilly, L., Anderson, K., Li, X., Lisell, L., 2018a. Grid ready: strategies
Holm, A., Cook, J.J., Aznar, A., Coughlin, J., Mow, B., 2019. Distributed solar
for interconnecting large-scale PV in New York city. Technical Report NREL/TP-
photovoltaic cost-benefit framework study: considerations and resources for
7A40-71344, NREL, Golden, CO. URL. https://www.nrel.gov/docs/fy19osti/71344.
Oklahoma. Aug, Technical Report NREL/TP-7A40-72166, NREL, Golden, CO. URL.
pdf.
https://www.nrel.gov/docs/fy19osti/72166.pdf.
Case, T., Liburd, S., Reilly, L., Anderson, K., Li, X., Lisell, L., 2018b. Grid ready: strategies
Homeland Infrastructure Foundation-Level Data, 2020. Parcel data - LightBox. htt
for interconnecting large-scale PV in New York city. Technical Report NREL/TP-
ps://gii.dhs.gov/hifld/content/hifld-data-catalog.
7A40-71344, NREL, Golden, CO. URL. https://www.nrel.gov/docs/fy19osti/71344.
Horowitz, K.A.W., Palmintier, B., Mather, B., Denholm, P., 2018. Distribution system
pdf.
costs associated with the deployment of photovoltaic systems. Jul Renew. Sustain.
Chow, A., Fung, A.S., Li, S., 2014. GIS modeling of solar neighborhood potential at a fine
Energy Rev. 90, 420–433. URL. http://www.sciencedirect.com/science/article/pii/
spatiotemporal resolution. Jun Buildings 4 (2), 195–206. https://www.mdpi.com/20
S1364032118301734.
75-5309/4/2/195.
Kwasnik, T., Sigrin, B., 2019. Distributed solar technoeconomic agent characteristics
Cole, W., Lewis, H., Sigrin, B., Margolis, R., 2016. Interactions of rooftop PV deployment
dstac. Tech. rep., National Renewable Energy Laboratory-Data (NREL-DATA),
with the capacity expansion of the bulk power system. Apr Appl. Energy 168,
Golden, CO (United…. https://data.nrel.gov/submissions/112.
473–481. http://www.sciencedirect.com/science/article/pii/S0306261916301271.
Lantz, E., Sigrin, B., Gleason, M., Preus, R., Baring-Gould, I., 2016. Assessing the future of
Commission, N.Y.S.P.S., 2017. Standardized interconnection requirements and
distributed wind: opportunities for behind-the-meter projects. Technical Report
application process for distributed generators and energy storage systems 5 mw or
NREL/TP-6A20-67337, NREL, Golden, CO. https://www.nrel.gov/docs/fy17osti/
less connected in parallel with utility distribution systems. https://www3.dps.ny.
67337.pdf.
gov/W/PSCWeb.nsf/All/DCF68EFCA391AD6085257687006F396B?OpenDocume
Lavillotti, M., Smith, Z., Apr, 2019. DER energy & capacity market design. https://www.
nt.
nyiso.com/documents/20142/6006612/BIC%20DER%20Market%20Design%20
Denholm, P., Margolis, R., Palmintier, B., Barrows, C., Ibanez, E., Bird, L., Zuboy, J.,
Presentation.pdf/9cdc8700-ab90-d741-c28d-0c29b3468807.
2014. Methods for analyzing the benefits and costs of distributed photovoltaic
Lee, N., Flores-Espino, F., Oliveira, R., Roberts, B., Bowen, T., Katz, J., 2019. Exploring
generation to the U.S. Electric utility system. Technical Report NREL/TP-6A20-
renewable energy opportunities in select southeast asian countries: a geospatial
62447, NREL, Golden, CO. URL. https://www.nrel.gov/docs/fy14osti/62447.pdf.
analysis of the levelized cost of energy of utility-scale wind and solar photovoltaics.
Efficiency & Renewable Energy (EERE), 2013. Commercial and residential hourly load
Jun, Technical Report, NREL, Golden, CO. https://www.nrel.gov/docs/fy19osti/
profiles for all TMY3 locations in the United States. Jul. https://openei.org/doe-open
71814.pdf.
data/dataset/commercial-and-residential-hourly-load-profiles-for-all-tmy3-location
Linvill, C., Shenot, J., Lazar, J., 2013. Designing distributed generation tariffs well: fair
s-in-the-united-states.
compensation in a time of transition. Nov, Tech. rep., Regulatory Assistance Project,
EIA, 2008. 2003 Commercial Building Energy Consumption Survey (CBECS). Public Use
Montpelier, VT. http://www.raponline.org/wp-content/uploads/2016/05/rap-linvi
Microdata. U.S. Energy Information Administration, Washington, DC. http://www.
llshenotlazar-faircompensation-2013-nov-27.pdf.
eia.gov/consumption/commercial/data/2003/index.cfm?view=microdata.
Lopez, A., Roberts, B., Heimiller, D., Blair, N., Porro, G., 2012. U.S. Renewable energy
Elshurafa, A.M., Muhsen, A.R., 2019. The upper limit of distributed solar PV capacity in
technical potentials: a GIS-based analysis. Technical Report NREL/TP-6A20-51946,
Riyadh: a GIS-assisted study, 11 (16), 4301. https://www.mdpi.com/2071-1050/11
NREL, Golden, CO. https://www.nrel.gov/docs/fy12osti/51946.pdf.
/16/4301.
Mansouri Kouhestani, F., Byrne, J., Johnson, D., Spencer, L., Hazendonk, P., Brown, B.,
Federal Energy Regulatory Commission, Sep, 2020. Participation of distributed energy
2019. Evaluating solar energy technical and economic potential on rooftops in an
resource aggregations in markets operated by regional transmission organizations
urban setting: the city of Lethbridge, Canada. Mar International Journal of Energy
and independent system operators. https://www.ferc.gov/sites/default/files/
and Environmental Engineering 10 (1), 13–32. https://doi.org/10.1007/s40095-
2020-09/E-1_0.pdf.
018-0289-1.
16
T. Bowen et al. Energy Policy 166 (2022) 112744
Marwick, B., Krishnamoorthy, K., 2019. Cvequality: tests for the equality of coefficients O’Shaughnessy, E., Ardani, K., Apr, 2020. Distributed rate design: a review of early
of variation from multiple groups. URL. https://CRAN.R-project.org/package=c approaches and practical considerations for value of solar tariffs. Electr. J. 33 (3),
vequality. 106713. http://www.sciencedirect.com/science/article/pii/S1040619020300051.
Mavromatidis, G., Orehounig, K., Carmeliet, J., 2015. Evaluation of photovoltaic Prakash, P., Khatod, D.K., May, 2016. Optimal sizing and siting techniques for
integration potential in a village. Sol. Energy 121, 152–168. http://www.sciencedi distributed generation in distribution systems: a review. Renew. Sustain. Energy Rev.
rect.com/science/article/pii/S0038092X15001711. 57, 111–130. http://www.sciencedirect.com/science/article/pii/S1364032
McCabe, K., Sigrin, B., Lantz, E., Mooney, M., 2018. Assessment of the economic 115014823.
potential of distributed wind in Colorado, Minnesota, and New York. Technical Proudlove, A., Lips, B., Sarkisian, D., 2020. 50 states of solar - Q4 2019 quarterly report
Report NREL/TP-6A20-70547, NREL, Golden, CO. URL. https://www.nrel.gov/ & 2019 annual review. Tech. Rep., NC clean energy technology center. Jan, North
docs/fy18osti/70547.pdf. Carolina. https://nrellibrary.nrel.gov/store/NCSU/2019/NCSU_50StateofSolar
National Renewable Energy Laboratory, 2019. 2019 annual technology baseline. https:// _Q42019.pdf.
atb.nrel.gov/electricity/2019/data.html. Rábago, K.R., Valova, R., Oct 2018. Revisiting Bonbright’s principles of public utility
NYISO, 2017. Distributed energy resources roadmap for New York’s wholesale electricity rates in a DER world. Electr. J. 31 (8), 9–13. http://www.sciencedirect.com/science/
markets. Jan, Technical Report, New York Independent System Operator, article/pii/S1040619018302276.
Rensselaer, NY. https://www.nyiso.com/documents/20142/1391862/Distribute Reiman, A.P., Homer, J.S., Bhattarai, B., Orrell, A.C., Feb, 2020. Quantifying technical
d_Energy_Resources_Roadmap.pdf/ec0b3b64-4de2-73e0-ffef-49a4b8b1b3ca. diversity benefits of wind as a distributed energy resource. In: 2020 IEEE Power
NYISO, 2019. Power Trends 2019. Annual Grid & Markets Report. NYISO, Rensselaer, Energy Society Innovative Smart Grid Technologies Conference (ISGT), pp. 1–5 iSSN:
NY. https://www.nyiso.com/documents/20142/2223020/2019-Power-Trends-Re 2472-8152. URL. https://ieeexplore.ieee.org/document/9087665.
port.pdf. Sigrin, B., Gleason, M., Preus, R., Baring-Gould, I., Margolis, R., 2016. Distributed
NYISO, 2020a. Monthly auction summary. http://icap.nyiso.com/ucap/public/auc generation market demand model (dGen): documentation. Technical Report NREL/
_view_monthly_selection.do. TP-6A20-65231, NREL, Golden, CO. URL. https://www.nrel.gov/docs/fy16osti/
NYISO, 2020b. Pricing data - day-ahead market LBMP. https://www.nyiso.com/ene 65231.pdf.
rgy-market-operational-data. Sigrin, B.O., Mooney, M.E., Apr, 2018. Rooftop solar technical potential for low-to-
NYPSC, 2015. Order establishing a community distributed generation program and moderate income households in the United States. Tech. Rep. NREL/TP–6A20-
making other findings. Jul. http://documents.dps.ny.gov/public/Common/ViewDoc 70901, NREL, Golden, CO. http://www.osti.gov/servlets/purl/1434891/.
.aspx?DocRefId=%7b76520435-25ED-4B84-8477-6433CE88DA86%7d. Sun, Y.-w., Hof, A., Wang, R., Liu, J., Lin, Y.-j., Yang, D.-w.. GIS-based approach for
NYPSC, 2017. Order on net energy metering transition, phase one of value of distributed potential analysis of solar PV generation at the regional scale: a case study of fujian
energy resources, and related matters. Mar. http://documents.dps.ny.gov/ province 58, 248–259. http://www.sciencedirect.com/science/article/pii/S0301
public/Common/ViewDoc.aspx?DocRefId=%7B5B69628E-2928-44A9-B83E-65CEA 421513001560.
7326428%7D. Taylor, M., McLaren, J., Cory, K., Davidovich, T., Sterling, J., Makhyoun, M., Mar. 2015.
NYPSC, 2018. Staff Whitepaper on Future Community Distributed Generation Value of solar: program design and implementation considerations. Technical Report
Compensation. Jul. Staff White Paper, New York Public Service Commission, Albany, NREL/TP-6A20-62361, NREL, Golden, CO. URL. https://www.nrel.gov/docs/fy15os
NY. URL. https://www.nyserda.ny.gov/-/media/NYSun/files/Staff-Whitepaper- ti/62361.pdf.
Future-Community-Distributed-Generation-Compensation.pdf. Tegen, S., 2016. Distributed wind cost reduction: learning from solar. Feb. https://www.
NYPSC, 2019. In the matter of the value of distributed energy resources. Apr, URL. htt nrel.gov/docs/fy16osti/66031.pdf.
ps://www.nyserda.ny.gov/All-Programs/Programs/NY-Sun/Contractors/Value-of- U.S. Geological Survey (USGS) Gap Analysis Project (GAP), 2018. Protected areas
Distributed-Energy-Resources. database of the United States (PAD-US): U.S. Geological Survey data
NYPSC, 2020. Order establishing net metering successor tariff. Jul. http://documents. releaseItemType: dataset. URL. https://www.usgs.gov/core-science-systems/science
dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=E5A4CFD8-BD26-428 -analytics-and-synthesis/gap/science/pad-us-data-overview?qt-science_center_obje
7-B3F1-C1A72A3540BA. cts=0#qt-science_center_objects.
NYSERDA, 2019. Solar value stack calculator. Sep. https://www.nyserda.ny.gov/All Yushchenko, A., Bono, A.d., Chatenoux, B., Patel, M.K., Ray, N., 2018. GIS-based
-Programs/Programs/NY-Sun/Contractors/Value-of-Distributed-Energy-Resources assessment of photovoltaic (PV) and concentrated solar power (CSP) generation
/Solar-Value-Stack-Calculator. potential in West Africa. Renew. Sustain. Energy Rev. 81, 2088–2103. URL. http://
NYSERDA, 2020. 2020 compliance year. Apr. https://www.nyserda.ny. www.sciencedirect.com/science/article/pii/S1364032117309619.
gov/All-Programs/Programs/Clean-Energy-Standard/REC-and-ZEC-Purch Zinaman, O.R., Aznar, A., Linvill, C., Darghouth, N., Bianco, E., Dubbeling, T., Oct, 2017.
asers/2020-Compliance-Year Office of Energy. Grid-connected distributed generation: compensation mechanism basics. Brochure
Open Energy Information, 2020. Utility Rate Database. https://openei.org/wiki/Utilit NREL/BR-6A20-68469, NREL. URL. https://www.nrel.gov/docs/fy18osti/68469.
y_Rate_Database. pdf.
O’Shaughnessy, E.J., 2018. The effects of market concentration on residential solar PV Zinaman, O., Bowen, T., Aznar, A., 2020. An overview of behind-the-meter solar-plus-
prices: competition, installer scale, and soft costs. Jun, Fact Sheet NREL/TP–6A20- storage regulatory design - approaches and case studies to inform international
71296, NREL, Golden, CO. http://www.osti.gov/servlets/purl/1452704/. applications. Mar, Technical Report NREL/TP-7A40-75283, NREL, Golden, CO. URL.
https://www.nrel.gov/docs/fy20osti/75283.pdf.
17