You are on page 1of 3

CONCRETE [quantities according to BoQ]

A1. C40/50 Cast in Place Piles in main span, expressed in m3

= 1800mm; volume per meter height, expressed in m3 = 2.545 m3 = 2.54469*2880 = 7,328.7

[Ref. 2.1.1]

A2. C40/50 Pile Cap main span, expressed in m3 [Ref. 2.2.1] = 14,872.6

A3. C40/50 Concrete Finishes, expressed in m3 [Ref. 2.5.1] = 609.3

A4. C40/50 Cast in Place Piles for Approach Bridge expressed in m3 [Ref. 3.1.1] = 22,291.5

A5. C40/50 Pile Cap for Approach Bridge expressed in m3 [Ref. 3.2.1&3.2.2] = 8,028.2

A6. C40/50 Superstructure Box Girder for Approach Bridge expressed in m3 [Ref. 3.4.2] =4201.9

A7. C40/50 Cocnrete finishes for Approach Bridge expressed in m3 [Ref. 3.6.1] = 1,366.9

====================================================================
SUB-TOTAL (A) = 58,699 m3

B1. C50/60 Superstructure Box Girder for Approach Bridge expressed in m3 [Ref. 3.4.1] = 6,080

B2. C50/60 Concrete Pier in main span, expressed in m3 [Ref. 2.2.3] = 394.2
B3. C50/60 Concrete Pylon in main span, expressed in m 3 [Ref. 2.2.5] = 18,655.7
B4. C50/60 Concrete Box Guarder in main span, expressed in m3 [Ref. 2.3.1] = 11,164.5
B5. C50/60 Pier for Approach Bridge expressed in m3 [Ref. 3.3.1] = 850.2
B6. C50/60 Accessible Pier for Approach Bridge expressed in m 3 [Ref. 3.3.2] = 3,613.7
B7. C50/60 Precast concrete Beam for approach Bridge, expressed TT in m3 = 66400000 Ta for 6640 m
===========================================================================
SUB TOTAL (B) = 40,758 m3

TOTAL: 99,457 m3 (excluding the quantity for T-Beam in the approach bridge)
[A] Concrete for superstructures and substructures
V = 99,457 m3
REF. ESTIMATION:
A. Concrete Class – 45 MPa

 Cement = 540 kg (Basundhara, OPC)


 W/C = 0.26
 Water = 140.4 kg (Base Camp Pump Water)
 Stone Chips = 1251 kg (Pakur Stone, India)
 Sand = 613 kg (Panchagarh)
 Admixture = 0.7% (3.78 kg) (Sika Plast-5201 NS)

Density of concrete in the design = 2544 kg/m3

Ingredients for 99,457 m3 of concrete:

Ingredients Quantity, kg Quantity in Ton for


per m3 99,457 m3 of concrete
Cement 540 53,700
Sand 613 61,000
Stone Chippings 1251 124,400
[B] Concrete for Concrete Blocks for Slope Protection Works

BLOCK SIZE, CM NR VOLUME, M3


45x45x45 236,237 21,527
40 x 40 x 40 177,065 11,332
35 x 35 x 35 341,759 14,653
TOTAL 47,510

REF. ESTIMATION
B. Concrete Class – 20 MPa

 Cement = 340 kg (Akis, OPC)


 W/C = 0.44
 Water = 149.6 kg (Base Camp Pump Water)
 Stone Chips = 1014 kg (Pakur Stone, India)
 Sand = 944 kg (Panchagarh)

Admixture = 0.65% (Sika Plast-2004 NS)

Density of concrete in the design = 2448 kg/m3

Ingredients for 47,510m3 of concrete:

Ingredients Quantity kg Quantity in Ton for


per m3 47,510 m3 of concrete
Cement 340 16,150
Sand 944 44,850
Stone Chippings 1,014 48,180

SUMMARY OF CONCRETE INGREDIENT QUANTITIES

Concrete Ingredients Qty. in TON for Qty. in TON for Total


Main and Concrete Blocks Quantity in
Approach Bridges for Slope TON
Protection
Cement 53,700 16,150 69,850
Sand 61,000 44,850 105,850
Stone Chipping 124,400 48,180 172,580