Ref: APMPL: SATIA: EMAIL-203: 2009 18th March 2009.

To: M/s.Satia Papers Mills Limited, Muktsar

Kind Attn. Mr. V.K.Gupta – G.M. (Mech.)

Dear Sir,

Sub: Drawings for LTI System

We are pleased to enclose the following drawings for the construction purpose, pertaining to the LTI
plant vide transmittal No:401-09-101.

S. No. Description Drawing No.


1. Layout plan – LTI Plant APMPL-401-2602-01-R2

2. LTI Equipment Foundation Pad Details APMPL-401-2602-04-R1

3. LTI Equipment Foundation Load Plan APMPL-401-2602-05-R1

4. LTI Column Foundation details & Load Data APMPL-401-2602-06-R1

5. LTI - RCC Grillage Foundation for LTI APMPL-401-2604-03-R1

6. P& I Diagram LTI- Oxidation APMPL-401-2601-01-R1

7. P& I Diagram for Material Handling APMPL-401-2601-02-R1

8. P& I Diagram LTI Scrubber APMPL-401-2601-03-R1

You may please proceed the LTI foundation work based on the above drawing.

Thanking you and assuring you of our best services at all times.

Yours faithfully,
for AGRO PULPING MACHINERY PVT. LTD.,

K THOMAS MATHEW
Manager (Design & Development)

Encl. : As above
AGRO PULPING MACHINERY PVT. LTD. DOC NO: 401-09-101
CHENNAI – 600 017
DATE : 18.03.09

DRAWING TRANSMITTAL
TO: SATIA INDUSTRIES LIMITED J.O No. 44A
S.NO. DESCRIPTION DRAWING NO. REV REMARKS
1 LAYOUT PLAN –LTI PLANT APMPL-401-2602-01 R2
2 LTI EQUIPMENTS FOUNDATION PAD DETAILS APMPL-401-2602-04 R1
3 LTI EQUIPMENT FOUNDATION LOAD PLAN APMPL-401-2602-05 R1
LTI COLUMN FOUNDATION DETAILS & LOAD
4 APMPL-401-2602-06 R1
DATA
5. LTI – RCC GRILLAGE FOUNDATION FOR LTI APMPL-401-2604-03 R1
6. P & I DIAGRAM LTI – OXIDATION APMPL-401-2601-01 R1
7. P & I DIAGRAM FOR MATERIAL LANDLING APMPL-401-2601-02 R1
8. P & I DIAGRAM – LTI SCRUBBER APMPL-401-2601-03 R1

MODE OF DESPATCH :- PURPOSE:-

o BY COURIER o PRELIMINARY ONLY


o BY E-MAIL o FOR APPROVAL
o BY PERSON o FOR REFERENCE ONLY
o FOR INFORMATION & USE

MANAGER – DESIGN & DEVELOPMENT