Amou
Tahun Jan Feb Mar
2012 15 18 12
2013 15.0 20.0 19.0
2014 23.0 13.0 18.0
2015 12.0 18.0 14.0
Act 2016 22.0 24.0 27.0
Avg. Max Rainfall/Month (X) up to 2015 17.40 18.60 18.00
Avg. Max Rainfall/Month (X) up to 2016 17.40 18.60 18.00
Avg. Max Rainfall/Month (X) up to 2017 17.17 18.50 17.83
Avg. Max Rainfall/Month (X) up to 2018 17.00 18.43 17.71
Avg. Max Rainfall/Month (X) up to 2019 16.75 18.13 17.38
Standard Deviation (s) plan 2016 6.00 4.13 5.15
Standard Deviation (s) plan 2017 6.83 5.62 8.19
Standard Deviation (s) plan 2018 6.89 5.63 8.21
Standard Deviation (s) plan 2019 13.86 14.20 14.98
Standard Deviation (s) plan 2020 7.05 5.87 8.42
(a) 2016 0.21 0.31 0.25
(a) 2017 0.19 0.23 0.16
(a) 2018 0.19 0.23 0.16
(a) 2019 0.09 0.09 0.09
(a) 2020 0.18 0.22 0.15
(Xo) 2016 14.70 16.74 15.68
(Xo) 2017 14.33 16.07 14.31
(Xo) 2018 14.07 15.96 14.14
(Xo) 2019 10.76 12.04 10.97
(Xo) 2020 13.57 15.48 13.58
Plan 2016 (X) 17.00 18.00 17.00
Plan 2017 (X) 16.00 18.00 17.00
Plan 2018 (X) 16.00 18.00 17.00
Plan 2019(X) 15.00 16.00 15.00
Plan 2020 (X) 16.00 17.00 16.00
Daily Pl
Tahun Jan Feb Mar
2012 24.6 29.0 16.3
2013 31.1 12.8 15.9
2014 14.8 27.0 21.3
2015 14.3 27.0 14.3
Act 2016 28.7 15.2 18.8
Avg. Max Rainfall/Month (X) up to 2015 21.20 23.96 16.95
Avg. Max Rainfall/Month (X) up to 2016 22.69 22.21 17.32
Avg. Max Rainfall/Month (X) up to 2017 22.31 21.83 17.18
Avg. Max Rainfall/Month (X) up to 2018 21.97 21.51 17.06
Avg. Max Rainfall/Month (X) up to 2019 21.47 21.01 16.73
Standard Deviation (s) plan 2016 9.93 9.18 3.74
Standard Deviation (s) plan 2017 11.00 10.72 3.92
Standard Deviation (s) plan 2018 11.10 10.81 3.96
Standard Deviation (s) plan 2019 19.10 18.67 12.70
Standard Deviation (s) plan 2020 11.52 11.23 4.37
(a) 2016 0.13 0.14 0.34
(a) 2017 0.12 0.12 0.33
(a) 2018 0.12 0.12 0.32
(a) 2019 0.07 0.07 0.10
(a) 2020 0.11 0.11 0.29
(Xo) 2016 16.72 19.82 15.26
(Xo) 2017 17.74 17.39 15.55
(Xo) 2018 17.31 16.96 15.40
(Xo) 2019 13.37 13.10 11.34
(Xo) 2020 16.28 15.96 14.76
Plan 2016 (X) 19.10 22.02 16.16
Plan 2017 (X) 20.37 19.95 16.49
Plan 2018 (X) 19.96 19.55 16.35
Plan 2019(X) 17.93 17.56 14.38
Plan 2020 (X) 19.03 18.64 15.80
Xtr = Xr + K.Sx
K = (Ytr - Yn)/Sn
Ytr = -In.In (Tr)/(Tr-1)
Xtr = Xr + (Ytr-1)/(Sn).Sx
Xtr =
Monthly Rainfall Data (mm/month)
Apr Mei Jun Jul Agst Sep Okt Nov
253 321 100 236 90 90 372 312
327 714 92 444 110 110 224 319
221 248 161 106 165 58 14.9 424.1
319.9 171.5 80.3 38.3 152.0 29.0 61.5 460.4
563.5 238.5 54.0 156.3
330.19 327.82 95.49 188.34 125.90 68.35 152.58 371.75
324.40 318.49 93.78 181.60 124.58 67.01 146.45 368.94
316.49 308.38 91.49 174.80 123.41 65.82 141.03 366.45
63.29 295.69 44.14 218.71 43.05 43.66 199.42 91.51
190.01 306.09 55.93 220.96 43.43 44.05 201.19 92.33
191.77 308.93 56.45 223.01 43.84 44.46 203.05 93.18
299.05 382.56 87.03 257.53 44.25 44.88 204.99 94.07
198.06 316.43 58.27 228.00 44.68 45.32 206.98 94.98
0.02 0.00 0.03 0.01 0.03 0.03 0.01 0.01
0.01 0.00 0.02 0.01 0.03 0.03 0.01 0.01
0.01 0.00 0.02 0.01 0.03 0.03 0.01 0.01
0.00 0.00 0.01 0.00 0.03 0.03 0.01 0.01
0.01 0.00 0.02 0.01 0.03 0.03 0.01 0.01
251.73 230.49 88.45 107.60 109.87 52.09 78.31 337.67
251.32 200.77 72.28 96.63 107.87 50.07 69.08 333.43
243.84 188.71 70.07 87.92 106.16 48.33 61.15 329.80
189.74 146.23 54.60 65.64 104.65 46.80 54.15 326.58
227.31 165.90 65.25 72.14 103.29 45.42 47.83 323.69
266.85 301.12 99.00 159.84 120.15 62.52 125.95 359.53
296.72 273.90 85.64 149.41 118.25 60.59 117.14 355.49
289.65 262.52 83.56 141.20 116.63 58.95 109.66 352.06
261.18 237.62 75.39 127.16 115.22 57.52 103.12 349.06
274.63 241.49 79.17 126.60 113.96 56.24 97.28 346.38
pit abc
Des Min. Max
575 90 575
Tahun
414 92 714
402.7 14.9 424.1 2016
306.6 29 486.6 2017
54 631 2018
413.97 2019
409.78 2020
406.08 *_Jalan,Rom,Workshop,Out pit,Mined out
136.26
137.48
138.75
140.07
141.44 1236812.62
0.01 123.681262
0.01
0.01
0.01
0.01
363.22
356.91
351.50
346.71
342.40
395.77 62.52073 395.7714
389.75 60.59277 389.7545
384.64 58.9546 384.6419
380.17 57.52252 380.1725
376.18 56.24434 376.1835
Q = (0,278).C.I.A
C 0.9
Q = Debit air limpasan, (m3/detik)
C = Koefisien limpasan (tanpa satuan) I 10.82
I = Intensitas curah hujan, (mm/jam) A 0.176
A = Luas daerah tangkapan hujan, (km2) Q 0.476460864
April Mei Juni Juli Agustus September
33.46 27.89 16.57 16.00 12.00 78.00
19.21 10.00 10.75 6.83 0.18 21.57
27.33 24.86 13.13 11.60 29.30 14.71
23.64 7.33 22.00 15.20 13.43 23.17
23.27 20.77 19.67 11.73 28.73 13.18
29.27 12.00 28.15 11.67 8.40 15.67
18.07 22.93 12.50 29.50 30.00 19.00
16.35 39.67 11.50 24.67 11.00 14.56
18.42 27.56 32.20 15.14 23.57 29.00
22.85 34.30 16.06 19.15 38.00 29.00
18.20 29.20 15.57 20.49 22.69 21.01
18.67 24.48 14.59 20.15 22.07 20.61
18.52 23.95 14.14 19.86 21.55 20.28
16.24 21.56 12.79 19.61 21.09 19.98
17.93 22.77 13.25 19.38 20.68 19.72
21.56
22.77
25.117647059 23.95
29.4 24.48
30 29.20
31.692307692 29.40
32.2 30.00
37.529411765 32.20
38 38.00
39.666666667 39.67
47.6
78
D saluran 1m b 1
Panjang saluran 153 m h 0.52
Koefisien kekasaran 0.125 S 0.3
1. Rumus Manning
`
2 1
1
V R 3
S 2
n
Jari-jari Hidrolis
Jari2 hidrolis
0.254902
2 1
1 3
V R S 2
n
V 0.094902
Q3 FxV
0.032077 m3/detik
PIT ABC 2016
CURAH 29.20 MM/DAY 6 MM/JAM 0.39577 m/bulan
CATHMENT 393,043 M2 0.393 KM2 39 Ha
DURASI 4.56 jam
0.49 m3/detik
Debit limpasan
8,040 m3/Jam/day
U 0.985324928 m/dettik
Koefisien gesekan
hf = λ. LD . v22g
V22 0.02
G 9.8
hf 0.024192
Head Dynamic : Total length pipe x friction loss
Head dynamic 2.17728
U 0.023158 m/dettik
Koefisien gesekan
hf = λ. LD . v22g
V22 0.023158
G 9.8
hf 0.020008
Head Dynamic : Total length pipe x friction loss
Head dynamic 1.800745
U 0.03225407472968 m/dettik
Koefisien gesekan
hf = λ. LD . v22g
V22 0.03225407472968
G 9.8
hf 0.05263864995883
Head Dynamic : Total length pipe x friction loss
Head dynamic 8.94857
U 0.01852914906 m/dettik
Koefisien gesekan
hf = λ. LD . v22g
V22 0.01852914906
G 9.8
hf 0.06225794083
Head Dynamic : Total length pipe x friction loss
Head dynamic 21.79028
U 0.03155008747239 m/dettik
Koefisien gesekan
hf = λ. LD . v22g
V22 0.03155008747239
G 9.8
hf 0.05603295535097
Head Dynamic : Total length pipe x friction loss
Head dynamic 10.3661
U 0.02695713631 m/dettik
Koefisien gesekan
hf = λ. LD . v22g
V22 0.02695713631
G 9.8
hf 0.05693347189
Head Dynamic : Total length pipe x friction loss
Head dynamic 12.52536
U 0.02840677496617 m/dettik
Koefisien gesekan
hf = λ. LD . v22g
V22 0.02840677496617
G 9.8
hf 0.05045043233992
Head Dynamic : Total length pipe x friction loss
Head dynamic 9.33333
U 0.03010884215 m/dettik
Koefisien gesekan
hf = λ. LD . v22g
V22 0.03010884215
G 9.8
hf 0.09307245284
Head Dynamic : Total length pipe x friction loss
Head dynamic 29.96933
U 0.03000103274488 m/dettik
Koefisien gesekan
hf = λ. LD . v22g
V22 0.03000103274488
G 9.8
hf 0.06912237944421
Head Dynamic : Total length pipe x friction loss
Head dynamic 16.58937
U 0.04857836052 m/dettik
Koefisien gesekan
hf = λ. LD . v22g
V22 0.04857836052
G 9.8
hf 0.15016542804
Head Dynamic : Total length pipe x friction loss
Head dynamic 48.35327
U 0.02977858 m/dettik
Koefisien gesekan
hf = λ. LD . v22g
V22 0.02977858
G 9.8
hf 0.02915918
Head Dynamic : Total length pipe x friction loss
Head dynamic 2.974237
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
9,954
Q total V A
9,954 0.465 4628.687 m2
Volume 29,489 m3
To Kpl3
CURAH 22.77 MM/DAY 5 MM/JAM 0.37618 m/bulan
CATHMENT 99,351 M2 0.099 KM2 10 Ha
DURASI 4.15 jam
0.11 m3/detik
Debit limpasan
1,585 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
1,585
Q total V A
1,585 0.465 737.1801 m2
Volume 4,697 m3
To Kpl5 To Kpl6
CURAH 22.77 MM/DAY 5 MM/JAM 0.37618 m/bulan CURAH
CATHMENT 82,936 M2 0.083 KM2 8 Ha CATHMENT
DURASI 4.15 jam DURASI
0.09 m3/detik
Debit limpasan Debit limpasan
1,323 m3/Jam/day
Saluran 1 Saluran 1
Q saluran :AxV Q saluran
Bentuk saluran Trapesium 51059 Bentuk saluran Trapesium
A : Bx (mh)h A
B m h A B
1.25 1 0.8 0.8 m2 1.25
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
2,804
Q total V A
2,804 0.465 1303.682 m2
Volume 8,306 m3
To Kpl4
CURAH 22.77 MM/DAY 5 MM/JAM 0.37618 m/bulan
CATHMENT 51,059 M2 0.051 KM2 5 Ha
DURASI 4.15 jam
Debit limpasan 0.05 m3/detik
814 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
815
Q total V A
815 0.465 378.9711 m2
Volume 2,414
:AxV
Bentuk saluran Trapesium
: Bx (mh)h
m h A
1 0.8 0.8 m2
: Q1+Q2
3,409
V A
0.465 1585.089 m2
Volume 10,891 m3
To Kpl1
CURAH 24.48 MM/DAY 6 MM/JAM 0.38975 m/bulan
CATHMENT 591,310 M2 0.591 KM2 59 Ha
DURASI 4.25 jam
0.66 m3/detik
Debit limpasan
10,141 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
10,141
Q total V A
10,141 0.465 4715.709 m2
Volume 30,044 m3
To Kpl3
CURAH 24.48 MM/DAY 6 MM/JAM 0.39577 m/bulan
CATHMENT 153,601 M2 0.154 KM2 15 Ha
DURASI 4.56 jam
0.17 m3/detik
Debit limpasan
2,826 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
2,827
Q total V A
2,827 0.465 1314.493 m2
Volume 8,375 m3
To Kpl5
CURAH 29.20 MM/DAY 6 MM/JAM 0.39577 m/bulan
CATHMENT 1,287,823 M2 1.288 KM2 129 Ha
DURASI 4.56 jam
1.60 m3/detik
Debit limpasan
26,344 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium 51059
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
26,345
Q total V A
26,345 0.465 12250.27 m2
Volume 78,046 m3
To Kpl7
CURAH 29.20 MM/DAY 6 MM/JAM 0.39577 m/bulan
CATHMENT 105,288 M2 0.105 KM2 11 Ha
DURASI 4.56 jam
0.13 m3/detik
Debit limpasan
2,154 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
2,154
Q total V A
2,154 0.465 1001.759 m2
Volume 6,883 m3
To Kpl2
CURAH 24.48 MM/DAY 6 MM/JAM 0.38975
CATHMENT 587,730 M2 0.588 KM2 59
DURASI 4.25 jam
0.66 m3/detik
Debit limpasan
10,079 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
10,080
Q total V A
10,080 0.465 4687.158 m2
Volume 29,862 m3
To Kpl4
CURAH 24.48 MM/DAY 6 MM/JAM 0.39577 m/bulan
CATHMENT 280,036 M2 0.280 KM2 28 Ha
DURASI 4.56 jam
0.31 m3/detik
Debit limpasan
5,153 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
5,153
Q total V A
5,153 0.465 2396.308 m2
Volume 15,267
To Kpl6
CURAH 29.20 MM/DAY 6 MM/JAM 0.39577 m/bulan
CATHMENT 727,812 M2 0.728 KM2 73 Ha
DURASI 4.56 jam
0.91 m3/detik
Debit limpasan
14,888 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
14,889
Q total V A
14,889 0.465 6923.334 m2
Volume 47,570 m3
m/bulan
Ha
(1/n*R^2/3*S^0,5)
To Kpl1
CURAH 23.95 MM/DAY 5 MM/JAM 0.380173 m/bulan
CATHMENT 591,310 M2 0.591 KM2 59 Ha
DURASI 4.45 jam
0.62 m3/detik
Debit limpasan
9,919 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
9,920
Q total V A
9,920 0.465 4612.7874 m2
Volume 29,388 m3
To Kpl3
CURAH 23.95 MM/DAY 5 MM/JAM 0.39577 m/bulan
CATHMENT 153,601 M2 0.154 KM2 15 Ha
DURASI 4.56 jam
0.16 m3/detik
Debit limpasan
2,640 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
2,641
Q total V A
2,641 0.465 1228.029 m2
Volume 7,824 m3
To Kpl5
CURAH 23.95 MM/DAY 5 MM/JAM 0.39577 m/bulan
CATHMENT 1,375,869 M2 1.376 KM2 138 Ha
DURASI 4.560 jam
1.44 m3/detik
Debit limpasan
23,651 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium 51059
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
23,652
Q total V A
23,652 0.465 10998.083 m2
Volume 70,068 m3
To Kpl7
CURAH 23.95 MM/DAY 5 MM/JAM 0.39577 m/bulan
CATHMENT 168,698 M2 0.169 KM2 17 Ha
DURASI 4.56 jam
Debit limpasan 0.18 m3/detik
2,900 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
2,900
Q total V A
2,900 0.465 1348.7051 m2
Volume 9,267 m3
To Kpl2
CURAH 23.95 MM/DAY 5 MM/JAM 0
CATHMENT 587,730 M2 0.588 KM2 59
DURASI 4.45 jam
0.62 m3/detik
Debit limpasan
9,859 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
9,860
Q total V A
9,860 0.465 4584.86 m2
Volume 29,210 m3
To Kpl4
CURAH 23.95 MM/DAY 5 MM/JAM 0.39577 m/bulan
CATHMENT 280,036 M2 0.280 KM2 28 Ha
DURASI 4.56 jam
Debit limpasan 0.29 m3/detik
4,814 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
4,814
Q total V A
4,814 0.465 2238.672 m2
Volume 14,263
To Kpl6
CURAH 23.95 MM/DAY 5 MM/JAM 0.39577 m/bulan
CATHMENT 602,086 M2 0.602 KM2 60 Ha
DURASI 4.56 jam
Debit limpasan 0.63 m3/detik
10,350 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
10,350
Q total V A
10,350 0.465 4812.94 m2
Volume 33,070 m3
To Kpl8
CURAH 23.95 MM/DAY 5 MM/JAM 0.39577 m/bulan
CATHMENT 682,606 M2 0.683 KM2 68 Ha
DURASI 4.56 jam
Debit limpasan 0.71 m3/detik
11,734 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
11,735
Q total V A
11,735 0.465 5456.567 m2
Volume 37,492 m3
m/bulan
Ha
(1/n*R^2/3*S^0,5)
To Kpl1
CURAH 21.56 MM/DAY 5 MM/JAM 0.38017 m/bulan
CATHMENT 591,310 M2 0.591 KM2 59 Ha
DURASI 4.47 jam
0.56 m3/detik
Debit limpasan
8,931 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
8,932
Q total V A
8,932 0.465 4153.242 m2
Volume 26,460 m3
To Kpl3
CURAH 21.56 MM/DAY 5 MM/JAM 0.38017 m/bulan
CATHMENT 153,601 M2 0.154 KM2 15 Ha
DURASI 4.47 jam
0.14 m3/detik
Debit limpasan
2,320 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
2,321
Q total V A
2,321 0.465 1079.038 m2
Volume 6,875 m3
To Kpl5
CURAH 21.56 MM/DAY 5 MM/JAM 0.38017 m/bulan
CATHMENT 1,375,869 M2 1.376 KM2 138 Ha
DURASI 4.47 jam
1.29 m3/detik
Debit limpasan
20,781 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium 51059
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
20,782
Q total V A
20,782 0.465 9663.508 m2
Volume 61,566 m3
To Kpl7
CURAH 21.56 MM/DAY 5 MM/JAM 0.38017 m/bulan
CATHMENT 168,698 M2 0.169 KM2 17 Ha
DURASI 4.47 jam
0.16
Debit limpasan
2,548 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
2,549
Q total V A
2,549 0.465 1185.07 m2
Volume 8,143 m3
To Kpl2
CURAH 21.56 MM/DAY 5 MM/JAM 0.38017
CATHMENT 587,730 M2 0.588 KM2 59
DURASI 4.47 jam
0.55 m3/detik
Debit limpasan
8,877 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
8,878
Q total V A
8,878 0.465 4128.097 m2
Volume 26,300 m3
To Kpl4
CURAH 21.56 MM/DAY 5 MM/JAM 0.38017 m/bulan
CATHMENT 280,036 M2 0.280 KM2 28 Ha
DURASI 4.47 jam
Debit limpasan 0.26 m3/detik
4,230 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
4,230
Q total V A
4,230 0.465 1967.041 m2
Volume 12,532
To Kpl6
CURAH 21.56 MM/DAY 5 MM/JAM 0.38017 m/bulan
CATHMENT 602,086 M2 0.602 KM2 60 Ha
DURASI 4.47 jam
0.57
Debit limpasan
9,094 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
9,094
Q total V A
9,094 0.465 4228.925 m2
Volume 29,057 m3
To Kpl8
CURAH 21.56 MM/DAY 5 MM/JAM 0.38017 m/bulan
CATHMENT 1,208,323 M2 1.208 KM2 121 Ha
DURASI 4.47 jam
1.13
Debit limpasan
18,251 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
18,251
Q total V A
18,251 0.465 8486.766 m2
Volume 58,312 m3
m/bulan
Ha
(1/n*R^2/3*S^0,5)
To Kpl1
CURAH 22.77 MM/DAY 5 MM/JAM 0.37618 m/bulan
CATHMENT 591,310 M2 0.591 KM2 59 Ha
DURASI 4.15 jam
0.63 m3/detik
Debit limpasan
9,432 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
9,433
Q total V A
9,433 0.465 4386.319 m2
Volume 27,945 m3
To Kpl3
CURAH 22.77 MM/DAY 5 MM/JAM 0.37618 m/bulan
CATHMENT 153,601 M2 0.154 KM2 15 Ha
DURASI 4.15 jam
0.16 m3/detik
Debit limpasan
2,450 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
2,451
Q total V A
2,451 0.465 1139.583 m2
Volume 7,260 m3
To Kpl5
CURAH 22.77 MM/DAY 5 MM/JAM 0.37618 m/bulan
CATHMENT 1,194,910 M2 1.195 KM2 119 Ha
DURASI 4.15 jam
1.28 m3/detik
Debit limpasan
19,061 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium 51059
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
19,061
Q total V A
19,061 0.465 8863.559 m2
Volume 56,469 m3
To Kpl7
CURAH 22.77 MM/DAY 5 MM/JAM 0.37618 m/bulan
CATHMENT 168,698 M2 0.169 KM2 17 Ha
DURASI 4.15 jam
0.18 m3/detik
Debit limpasan
2,691 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
2,692
Q total V A
2,692 0.465 1251.566 m2
Volume 8,599 m3
To Kpl2
CURAH 22.77 MM/DAY 5
CATHMENT 587,730 M2 0.588
DURASI 4.15 jam
0.63
Debit limpasan
9,375
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8
Q total : Q1+Q2
9,376
Q total V A
9,376 0.465 4359.763 m2
Volume 27,776 m3
To Kpl4
CURAH 22.77 MM/DAY 5 MM/JAM 0.37618
CATHMENT 280,036 M2 0.280 KM2 28
DURASI 4.15 jam
Debit limpasan 0.30 m3/detik
4,467 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
4,468
Q total V A
4,468 0.465 2077.422698 m2
Volume 13,235
To Kpl6
CURAH 22.77 MM/DAY 5 MM/JAM 0.37618 m/bulan
CATHMENT 602,086 M2 0.602 KM2 60 Ha
DURASI 4.15 jam
0.64 m3/detik
Debit limpasan
9,604 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
9,605
Q total V A
9,605 0.465 4466.249284 m2
Volume 30,687 m3
To Kpl8
CURAH 22.77 MM/DAY 5 MM/JAM 0.37618 m/bulan
CATHMENT 1,516,500 M2 1.517 KM2 152 Ha
DURASI 4.15 jam
1.62 m3/detik
Debit limpasan
24,191 m3/Jam/day
Saluran 1
Q saluran :AxV
Bentuk saluran Trapesium
A : Bx (mh)h
B m h A
1.25 1 0.8 0.8 m2
Q total : Q1+Q2
24,191
Q total V A
24,191 0.465 11248.97393 m2
Volume 77,291 m3
MM/JAM 0.37618 m/bulan
KM2 59 Ha
m3/detik
m3/Jam/day
m2
V (1/n*R^2/3*S^0,5)
m/bulan
Ha
(1/n*R^2/3*S^0,5)
Curah Hujan bulanan di daerah
2016
KPL 1 9954 0.51109656455125 623985
KPL 2 2803 0.51109656455125 175724
2016
KPL 3 1585 0.51109656455125 99351
KPL 4 814 0.51109656455125 51059
KPL 5 1323 0.51109656455125 4697
KPL 6 3408 0.51109656455125 213662
Settling Pond
Pipe Length, m Kapasitas, m3
Surface Area, m2
150 20,100
90 9,045
4628.687 29,489
1303.682 8,306
737.18 4,697
378.97 2,414
615.42 3,921
1585.089 10,891
170 25,198
350 14,475
4715.709 30,044
4687.158 29,862
1314.493 8,375
2396.308 15,267
12250.27 78,046
6923.334 47,570
1001759 6,883
185 24,648
220 21,060
4612.787 29,388
4584.86 29,210
1228.029 2,239
2238.572 14,263
10998.083 70,068
4812.97 33,070
1348.705 9,267
5456.567 37,492
185 22,193
322 23,523
4153.242 26,460
4128.027 26,300
1079.038 6,875
1967.041 12,532
9663.508 61,566
4228.925 29,057
1185.07 8,143
8486.766 58,312
240 23,438
322 37,953
102 23,265
4386.32 27,945
4359.76 27,776
1139.58 7,260
2077.42 13,235
8863.56 56,469
4466.24 30,687
1251.57 8,599
11248.97 77,291
Oktober November Desember
90 249 374
262 260 427
281 281 412
283 276 476
291 520 249
221 254 588
372 312 575
224 319 414
14.9 424.1 402.7
61.5 460.4 306.6