This document provides a full body harness inspection form template for a project involving two 1000 MW coal-fired steam power plants. The form includes fields for harness details, inspection date and inspector name. It lists 10 audit points for the harness components and webbing to check for acceptable condition or defects. Space is provided for remarks and an overall inspection conclusion signed by the inspector.
This document provides a full body harness inspection form template for a project involving two 1000 MW coal-fired steam power plants. The form includes fields for harness details, inspection date and inspector name. It lists 10 audit points for the harness components and webbing to check for acceptable condition or defects. Space is provided for remarks and an overall inspection conclusion signed by the inspector.
This document provides a full body harness inspection form template for a project involving two 1000 MW coal-fired steam power plants. The form includes fields for harness details, inspection date and inspector name. It lists 10 audit points for the harness components and webbing to check for acceptable condition or defects. Space is provided for remarks and an overall inspection conclusion signed by the inspector.
Project Name: Jawa 9&10 (2 x 1,000 MW) CFSPP Project Format No: Harness Model No/ Name: Serial: Date of Manufacturing: Data of Purchase: …………………………………………………………………………………………………….... Date of Audit: Inspector Name:
# AUDIT POINTS ACCEPTABLE OBSERVATIONS
CRITERIA 01 BODY PAD 02 LANYARD 03 SNAP HOOK 04 ANY STITCHING DEFECTS 05 BUCKEL 06 D-RING 07 HARNESS WEBBING 08 LABELS 09 10 REMARKS: