KUNAL CONSRTUCTION JSW/SHE/2023/04/P

PROJECT : JSW STEEL COATED PRODUCT LIMITED REV :


CHECKLIST FOR LADDER
NAME OF LOCATION : FREQUENCY : MINIMUM ONCE IN A WEEK
NAME OF CONTRACTOR / EMPLOYEE : INSPECTION BY (NAME) :
DATE OF RAGISTRATION : EQUIPMENT :
DATE OF INSPECTION :

11
1
12
6

3
7
9

10

SR NO. POINT OF INSPECTION YES NO N/A


1 Rail damage ( Crack , deformation etc.).

2 Rung broken.

3 Rung missing .

4 Run distance unven.

5 Rung clean.

6 Rung loose.

7 Rung lock.

8 Top hook damaged / damage.

Rope and pulley system ( Optional - typically found on longer


9
models.

10 Anti - slip safety shoe / foot.

11 Fly section.

12 Base Section.
Accepteble If not accepteble -
(YES/NO)
Overall Observation : equipment removed from
site (Date)

CHECKED BY DATE
Contractor's Supervior :
JSW Representive :
JSW/SHE/2023/04/PCC/01
0

NCE IN A WEEK

OBSERVATION DETAILS
Corrective / Preventive action taken on
(Date)

SIGNATURE