KUNAL CONSTRUCTION JSW/SHE/2023/2023/04/PCC

PROJECT : JSW STEEL COATED PRODUCT LIMITED REV :


CHECKLIST FOR CONCRETE MIXER MACHINE
NAME OF LOCATION : FREQUENCY : MINIMUM ONCE IN A WEEK
NAME OF CONTRACTOR / EMPLOYEE : INSPECTION BY (NAME) :
DATE OF REGISTRATION : EQUIPMENT SERIAL NO. :
DATE OF INSPECTION :

1
5

2 6

SR NO. POINT OF INSPECTION YES NO N/A


Mixer machine should be physically should sound in
1
good condition.

2 No damage in tire.

3 Engine should be covered with proper machine


guard.

4 Moving parts should be covered with fix guards.

5 Proper rotator handle lock should be available.

6 Rotator handle should be free from defect.

Handle for movement of mixer should be without


7 defect.

8 Spark arrester should be used if required.

Accepteble If not accepteble - equipment


Overall Observation : (YES/NO) removed from site (Date)

CHECKED BY DATE
Contractor's Supervisor :
JSW Representive :
JSW/SHE/2023/2023/04/PCC/01
0

MINIMUM ONCE IN A WEEK

OBSERVATION DITAILS

Corrective / Prevetive action taken on


(Date)

SIGNATURE