SW-MS-HVAC-MEP-DRAIN
STERLING AND WILSON SAFE WORK METHOD STATEMENT FOR
PIPING AND DE-HUMIDIFIER
DRAIN PIPING AND DE-HUMIDIFIER LINE -07
LINE INSTALLATION
REV. No.: 001
PROJECT: STT DATA CENTRE @CHENNAI
INDEX
1. PURPOSE
2. SCOPE
3. REFERENCES
4. ABBBREVIATIONS
5. RESPONSIBILITIES
9. QUALITY
10. DISTRIBUTION
DOC. No.:
SW-MS-HVAC-MEP-DRAIN
STERLING AND WILSON SAFE WORK METHOD STATEMENT FOR
PIPING AND DE-HUMIDIFIER
DRAIN PIPING AND DE-HUMIDIFIER LINE -07
LINE INSTALLATION
REV. No.: 001
PROJECT: STT DATA CENTRE @CHENNAI
1. PURPOSE
The purpose of this SOP is to outline the method of storage, handling and installation of Drain
Piping & De-humidifier line for Equipment’s like AHU/CRAH/CSU/TFA and FCU etc.
2. SCOPE:
This method statement refers to various work procedures contained within Sterling and Wilson,
Design/Drawing/Contractual specifications/Customer Quality requirement which explain.
Contract specifications& covers the Installation of Drain & De-humidifier line works.
3. REFERENCE
4. ABBREVIATIONS
PMC : JLL
CLIENT : STT
Manpower details:
No. of
Sl. No. Designation
Persons
1 Project Manager 01
2 Site Engineer 01
3 Site Supervisor 01
Safety Requirement
1. Organize team meeting with work allocation for the activity completion;
3. To ensure necessary permit and area clearance prior to start the activity.
4. Monitoring and controlling operations and conduct necessary measure prevent non-
confirmation works.
5. Identified site quality engineer is responsible for preparation of project specific quality
documents in consultation and support from regional quality representative.
6. Make sure effective implementation of approved quality plans and quality control
procedure during execution of works.
7. Responsible for communicating with all site staff about quality requirement and responsible
for reviewing all related subjects.
8. Regional quality representative will be responsible for organizing Quality Audits with
coordination of site and project management.
9. Responsible for all corrective action in coordination with project team and close the non-
conformity identified during quality audits.
5.4 Safety Engineer
11. Collect relevant information from the subcontractor with respect to work, equipment and
personnel.
12. Check suitable safety requirements in place during operation of the works.
16. Signages..
Tools and equipment required for carry on the Drain line activities as listed below:
6.4 PP Rope 18mm for Lifeline & 10mm for PVC pipes lifting.
6.7 Cotton waste (for cleaning the pipe surface prior to apply adhesive for joint).
MATERIAL SPECIFICATION:
Sl.
Material Description Weight per unit Remarks
No.
1 PVC Pipe 5-40 Kg 25mm to 200mm dia
DOC. No.:
SW-MS-HVAC-MEP-DRAIN
STERLING AND WILSON SAFE WORK METHOD STATEMENT FOR
PIPING AND DE-HUMIDIFIER
DRAIN PIPING AND DE-HUMIDIFIER LINE -07
LINE INSTALLATION
REV. No.: 001
PROJECT: STT DATA CENTRE @CHENNAI
Before commencement of installation of Drain & De-Humidifier line the following activities are
required to be carried out:
7.1.1 Obtain the work Permit and competent workforce will be perform the task
7.1.2 Brief description of task and training of crew before start of work by site supervisor
and by safety supervisor
7.1.3 Vehicle mobilization to be done to the designated marked area on floor plan by
S&W site engineer.
7.1.4 Ensure Banksmen while unloading of the material from the vehicle
7.1.5 During night hours use batten light to control the vehicle
7.1.6 Driver has to maintain Vehicle speed limit at site 15km/h
7.1.7 Barricades and signage shall be placed around the activity area for unloading
Material to restrict unauthorized entry.
7.1.8 Ensure Banksmen while unloading of the material from the vehicle
7.1.9 When off-loading, pipes shall be lowered, not dropped to the ground. by manually
from the truck to respective floor, without hampering other agency activities.
DOC. No.:
SW-MS-HVAC-MEP-DRAIN
STERLING AND WILSON SAFE WORK METHOD STATEMENT FOR
PIPING AND DE-HUMIDIFIER
DRAIN PIPING AND DE-HUMIDIFIER LINE -07
LINE INSTALLATION
REV. No.: 001
PROJECT: STT DATA CENTRE @CHENNAI
7.1.10 Deploying 2-3 persons for unloading and shifting activity. One person shall be
available on truck to lift & hand over the Drain line materials to persons who
standing on ground level to shift to designated place.
7.1.11 Always be given adequate supports under the pipes and shall be stacked on a flat
surface for free from any sharp objects.
7.1.12 support of at least 3” wide shall be placed beneath the pipes with spacing not
greater than 2mtr. Closer supports will be required for sizes below 80mm.
7.1.13 Pipes shall not be stored under direct sunlight to avoid ultraviolet degradation.
7.1.14 Make sure adequate lighting availability
7.1.15 Provide proper scaffolding and ladder as approved by safety team.
7.1.16 All the power tools and incoming cable to be checked no joints b/w the cable.
7.1.17 Provide proper barricade and signage during lifting of materials and installation.
Installation Procedure:
7.1.18 Mark-up the pipe routing on the soffit of slab / floor as per the setting-out.
7.1.19 Install approved anchor fasteners for support as per the approved support distances
7.1.20 All supporting of pipes will be done as per recommended spacing both horizontally
and vertically. Supporting of both horizontal & vertical pipes shall be done in
accordance with the approved details and drawings.
7.1.21 Pipes will be run to below the floor slab with proper slope requirements as per the
approved shop drawing. (min 1 : 100 mm)
7.1.22 Proper Staging with access platform(Horizontal support tied up with Vertical ‘C’
struct support which supported with bottom of slab) will be provided above the Puff
slab panel in GF @ 1.5-2 mtr. Height, inline to access the floor slab for carrying
Drainpipe installation with necessary supports as per drawing and cut out provided
in the upper floors.
7.1.23 Life line rope 16mm shall be provided through the ‘C’ struct support at regular
DOC. No.:
SW-MS-HVAC-MEP-DRAIN
STERLING AND WILSON SAFE WORK METHOD STATEMENT FOR
PIPING AND DE-HUMIDIFIER
DRAIN PIPING AND DE-HUMIDIFIER LINE -07
LINE INSTALLATION
REV. No.: 001
PROJECT: STT DATA CENTRE @CHENNAI
DISTRIBUTION
protocol. ,
7.1.41 Distribution of documents shall be as per contractual specification and agreed
t.
1-- --0 --
___] l
u t.rop d•.tou:a
FIG 3