Professional Documents
Culture Documents
C3 Jet Propulsion
C3 Jet Propulsion
Submitted By:
The severity is 5.
Cons: Cons:
1) Based on the available data from the case, We would choose not to launch and delay the
project for the next 24 months. There might be cost overrun in the project, but considering
the probability of 80% success (95% of success is recommended by the risk review committee)
delaying the project is the better choice. Meanwhile, we could get better data from the orbiter
2) Risk review committee formed by NASA that is well experienced and technically sound
persons is a good move. The heat map methodology of assessing the risk is one of the best
practices in project management. Constant reviewing of the ongoing process and re-assessing
the risk mitigation plans are common, the risk review committee should have also come up