You are on page 1of 1

Regulation System pumps for Chillers Task List

Description: VFD Regulation system of pumps Location:


PPM Schedule: Equipment Tag:
Quarterly Model No:
Work Order No Start Time: Date of Performance:
Finish Time: Date of Finish:

Safety Checklist Tick Box to be completed


1. Ensure Suitable PPE is used.
2. Secure Permit To Work (PTW).
3. Provide specific safety warning sign’s before performing the preventive maintenance task.
4. Ensure all hand tools are in good condition and fit for purpose.
5. Disconnect the power supply to unit, whether for periodic inspections or emergency repairs.

Tick √ if
Task Details REMARKS
Done
1. Check condition & operation of regulation system of pumps
2. Check the voltage ________ amperes_______ Herts______
3. Check condition pilot lights and alarm system
4. Check the VFD cooling fans
5. Clean the inlet air filter and outlet air filter
6. Clean and tight all electrical controller
7. Check all control relays
8. Check the door locks change if necessary
9. Check the operation of VFD Local mode and auto mode through DDC, BMS

Materials Used:
SR No Name Qty

Additional Information :

Performed By: Supervised By:


Sign: Sign:
Date: Date:

ESOM –Operation Template


Approved: Project Director Revision: 00
Doc. Owner: Operations-HVAC Doc. ESOM-FMS/HVC-04-E140003-165 Page 1 of 1