Six Sigma Yellow Belt Project Charter

Project Name OEE Improvement at Assembly Line A


Today’s Date 16/7/2023
Project Start Date 18/07/2023
Target Completion 30/09/2023
Date

Project Element Response


Problem Statement The last 4 month's OEE of line A is 45%. So the manufacturing
 Includes time, cost of the product is higher
measurable item, gap
and business impact
Business Case The improvement in OEE by 20% will reduce the manufacturing
 Why is this project cost per product by 25% that will improve our profitability by
important to do now? 25% directly.
 What is the project’s
To Improve the OEE of Line A from the current baseline of 45%
financial impact?
 What is the impact on
to 65% in the next six months. It will give the tangible benefits
DPMO/ Sigma level? of 50 lakh
 What is the impact on
customer service
Goal Statement To Improve the OEE of Line A from the current baseline of 45%
 Specific to 65% in the next six months. It will give the tangible benefits
 Measurable of 50 lakh
 Achievable
 Realistic
 Time-bound
List of Improvement Goals Measure (units) Baseline Goal
1OEE % 45 65
2.Rate of Availability % 70 82
3.Rate of Performance % 70 80
4.Rate of Quality % 92 99
5.
6.
Process Process: Manufacturing Process
 Describe the process Sub Process: Assembly Line A
in which the problem The last 4 month's OEE of line A is 45%. So the manufacturing
exists
cost of the product is higher
Six Sigma Yellow Belt Project Charter

Project Scope Improving OEE Reliability


 What part of the Productivity
process will be Quality
addressed? Performance of Product
 What are the Without Compromising Safety aspect of employee and
boundaries of the customer,
project or process? Improve Productivity and reliability to meet customer demand
 What areas are
inside or outside the
team’s focus or
authority?
 Attach a SIPOC
diagram if necessary
Team Member Name
Project Sponsor Sanjay patil
Key Stakeholders Samir pandya
Team Lead Youdishter gupta
Team Members Ankit Tiwari
Process Owner Aman Sharma
Other Akshay Giri
Timeline by Project Stage Milestone Target Completion Date
Define Project Charter and kickoff 16/7/2023
Measure Define and collect data 31/07/2023
Analysis Find causes 15/08/2023
Improve Fix causes 31/08/2023
Control Standardize the fix 30/09/2023

Project Title

Expectation Example Team Rule


Attendance is
required at all
team meetings.
Changes in
Attendance meeting times
must be made
at least 24
hours ahead of
time.   Responsibility :- aman
Team members
may not be
substituted
Participation
unless
approved by
team leader.  Youdishter
Six Sigma Yellow Belt Project Charter
We will stay on
task and on
topic, using the
Project Charter
as our guide. A
Focus
meeting agenda
will be
publishedat
least one day in
advance.   Ankit
Interruptions for
emergencies
Interruptions
only. Phones
turned to silent.   Samir
All deliverables
are expected to
be completed in
a timely
Preparation manner. Each
meeting will
have a
published
agenda.   Sanjay
Meetings will
Timeliness begin promptly
as scheduled.   Youdishter
We will choose
the best
decision-
making method
Decisions for each
situation. We
will support
decisions made
by the team.   ALL member
We will rely on
Data data to make
decisions.   All member
We welcome
honest
disagreements,
as long as
everyone is
Conflict treated with
respect. A
facilitator will
be used if
conflict cannot
be resolved. Team leader Youdishter
Other
Six Sigma Yellow Belt Project Charter

Team Member Role Signature


Sanjay patil Project Sanjay
Sponsor
Samir pandya Key Samir
Stakeholders
Youdishter gupta Team Lead Y.g

Ankit Tiwari Team Members A.tiwari

Aman Sharma Process Owner A sharma

Akshay Giri Other A giri

5.HYPOTHESIS The hypothesis is that the mean of the internal diameter of milled gears is
different from 1,100 inches. So null and alternative hypothesis are: 𝐻0: 𝑢 = 1,100 𝐻𝑎: 𝑢 ≠ 1,100

6. REFLECTIONS ABOUT THE COURSE For me this was a very useful course that taught me the
fundamentals of the six-sigma method which will help my professional development in my
organization. I believe now I’m able to be part of a team and use the knowledge gained from
this course