Laporan Perhitungan Bobot Pekerjaan Dinding Sungai Badera Tanggal : 17-Oct-2022 S/D 23-Oct-2022

PEKERJAAN DINDING SUNGAI BADERA Sub Kont : JEFRYSHU


HELVETIA MEDAN Lokasi STA : B113 - B114
MINGGU LALU MINGGU INI S/D MINGGU INI
No Uraian Pekerjaan Volume Bobot Keterangan
Progres Bobot Progres Bobot Progres Bobot

1 2 3 5 6 7 8 9 10 11 12

01 Pekerjaan Galian Tanah Mekasnis 2.568,00 M³ 4,76% 0% 0% 95% 4,52% 95% 4,52%

02 Pekerjaan Timbunan kembali 1.108,00 M³ 8,45% 0% 0% 0% 0,00% 0% 0,00%

03 Pekerjaan Stripping 469,00 M³ 7,00% 0% 0% 45% 3,15% 45% 3,15%

04 Pekerjaan Pembesian 11.852,00 M³ 23,14% 0% 0% 85% 19,67% 85% 19,67%

05 Pekerjaan Pembetonan K250 444,00 M³ 11,71% 0% 0% 70% 8,20% 70% 8,20%

06 Pekerjaan Bekisting Tie Rod 1.947,00 M³ 21,53% 0% 0% 30% 6,46% 30% 6,46%

07 Pekerjaan Perancah 1.947,00 M³ 10,25% 0% 0% 0% 0,00% 0% 0,00%

08 Pekerjaan Pasir Urug Sloof 160,00 M³ 3,22% 0% 0% 75% 2,42% 75% 2,42%

09 Pipa Suling 94,00 M³ 0,35% 0% 0% 65% 0,23% 65% 0,23%

10 Pekerjaan Waterstop Dinding Saluran 100,00 M³ 0,32% 0% 0% 0% 0,00% 0% 0,00%

11 Beton Capping Linning Atas 8,00 M³ 0,76% 0% 0% 0% 0,00% 0% 0,00%

12 Bekisting Beton Capping 71,00 M³ 1,09% 0% 0% 0% 0,00% 0% 0,00%

13 Precast (1x1.75x0.3) K300 200,00 M³ 2,39% 0% 0% 0% 0,00% 0% 0,00%

14 Pemasangan Precast 200,00 M³ 3,89% 0% 0% 0% 0,00% 0% 0,00%

15 Waterstop lantai Precast 300,00 M³ 1,09% 0% 0% 0% 0,00% 0% 0,00%

16 Pasir Urug Lantai Precast 117,00 M³ 0,05% 0% 0% 0% 0,00% 0% 0,00%

17 Beton Dinding atas

18 Pembesian Dinding Atas

19 Beskisting Dinding Atas

20 Perancah Dinding Atas

100,00% 0,00% 44,64% 44,64%

Disetujui Oleh Dibuat Oleh

JEFRYHSU
Project Manager Sub kontraktor