CHKLST-004 SHEET 1 OF 2

REVIEW CHECKLIST FOR SECTION LAYOUT

END CUSTOMER Torrent Power


PROJECT TITLE 132kV GIS Substation at Torrent Kazipur
OUR CLIENT
DRAWING NUMBER & REV NO. KZP-GIS-SIE-LAYOUT-E-001
Following points shall be verified by both Preparer and Reviewer and final signed checklist shall be maintained in project folder:
Review Status
SL. (Yes / NA / Deviation no.)
CHECK
NO.
Preparer Reviewer
Section no along with Bay descriptions are marked above each section view and
1 Yes
is matching with the section marking in Plan Layout
PD sensor shown at current locations as per PD Configuration rule book and is
2 Yes
matching with the location shown in gas SLD
3 All typical from plan layout is covered with the total number of section views Yes
4 Reference drawing table (including Gas SLD / Customer layout) is included Yes
Notes regarding “Compartment accessories, Location of PD Sensors, Maximum
5 Yes
weight of gas compartment” are included
6 Reference Axis-Z are marked, and all dimensions are linked with this Axis Yes
7 Internal clearance between GIS and nearest building wall is marked on both sides Yes
8 CB Removal / maintenance space is clearly marked as per Product type Yes
Standard IEC Notes “Ventilation requirement & Closed Operating area safety” are
9 Yes
included
10 Section marking is correctly matching with the orientation of section views Yes
Equipment legends (Q0, Q1, T1 etc.) are clearly marked and is correctly matching
11 Yes
with equipment sequence in Gas SLD
12 Minimum Crane Tonnage and hook height requirements are clearly marked Yes
13 FGL & FFL levels are clearly marked and is verified with Customer layout Yes
14 Centralized / Decentralized Gas monitoring is matching with Gas SLD Yes
15 Equipment legend table is included, and all equipment’s are covered Yes
16 Typical details of Busduct wall opening is included for projects with Busducts NA
17 Dimension from top of GIS to bottom of crane hook is marked Yes
18 Busbar & LCC heights are marked Yes
19 LCC is shown as Floor mounted / Integrated as per data pool and plan layout Yes
20 Reversing Module is not used on either of DS for 400kV GIS Configuration NA
21 Circuit symbols are added in section view and configuration verified with SLD Yes

Remarks for any deviation point:

Gupta Digitally signed by Gupta


Debasmit
DN: cn=Gupta Debasmit, c=DE, o
=Siemens, email=debasmit.gupta
Debasmit @siemens.com
Date: 2023.04.08 15:41:22 +05'30'

Debasmit Gupta Gourab Sil


Preparer Reviewer

RC-IN SE GP T SP EXE EN CHKLST-004 Rev. 01