Professional Documents
Culture Documents
AbutmentColumn
AbutmentColumn
Rev. Revised/
No. Form/Sheet No. Description on Revision Date Prepared by
No. Checked by
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
Comment
No. Check List Signed Date
(Nhaän
(Soá) (Danh muïc) (Kyù teân) (Ngaøy)
xeùt)
01 List of Acceptance Minutes for Abutment construction (Danh muïc nghieäm thu thi coâng Thaân Moá)
02 Inspection for Steel Bar, 1st Lift (Bieân baûn nghieäm thu coát theùp, Ñôït 1) OK
03 Inspection for Rebar and Formwork of 1st Lift (Bieân baûn nghieäm thu coát theùp vaø vaùn khuoân Ñôït 1) OK
04 Inspection for Position, Elevation of 1st Lift Formwork (B/baûn k/tra vò trí, cao ñoä vaùn khuoân Ñôït 1) OK
05 Inspection of Construction Preparation Work for 1 Lift (B/baûn k/tra cg taùc chuaån bò thi coâng Ñôït 1)
st OK
06 Inspection for Sampling of placed Concrete, 1st Lift (Bieân baûn kieåm tra laáy maãu beâ toâng, Ñôït 1) OK
07 Inspection for Concreting of Abutment, 1st Lift (Bieân baûn kieåm tra ñoå beâ toâng Thaân Moá Ñôït 1) OK
08 Inspection for Steel Bar, 2 Lift (Bieân baûn nghieäm thu coát theùp, Ñôït 2)
nd OK
09 Inspection for Rebar and Formwork of 2nd Lift (Bieân baûn nghieäm thu coát theùp vaø vaùn khuoân Ñôït 2) OK
10 Inspection for Position, Elevation of 2nd Lift Formwork (B/baûn k/tra vò trí, cao ñoä vaùn khuoân Ñôït 2) OK
11 Inspection of Construction Preparation Work for 2 Lift (B/baûn k/tra cg taùc chuaån bò thi coâng Ñôït 2)
nd OK
12 Inspection for Sampling of placed Concrete, 2 Lift (Bieân baûn kieåm tra laáy maãu beâ toâng, Ñôït 2)
nd OK
13 Inspection for Concreting of Abutment, 2nd Lift (Bieân baûn kieåm tra ñoå beâ toâng Thaân Moá Ñôït 2) OK
14 Inspection for Abutment Geometry after concreting (B/baûn k/tra h/hoïc Thaân Moá sau khi ñoå b/toâng) OK
Concrete Compressive Strength Test result (Keát quaû thí nghieäm neùn kieåm tra cöôøng ñoä beâ toâng) OK
Abutment ………
GENERAL VIEW OF ABUTMENT M1R SIDE VIEW ABUTMENT M1R
CL Of abutment CL Of bearing
+0.500
-1.500
Bearing pad
FOR CONTRACTOR
CONTRACTOR FOR CONSULTANT
CONSULTANT
NHÀ THẦU TƯ VẤN
QC Manager Project Manager Structural Engineer Resident Engineer
CONSTRUCTION TEAM Q.C OFFICE PROJECT MANAGER ENGINEER IN CHARGE APPROVED BY
Date: ĐỘI XÂY DỰNG Date:
QUẢN LÝ CHẤT LƯỢNG Date:ĐỐC DỰ ÁN
GIÁM Date:
KỸ SƯ PHỤ TRÁCH CHẤPTHUẬN BỞI
MINISTRY OF TRANSPORT Central Mekong Delta Region Connectivity Project (CMDCP) -
Dự án Kết nối Khu vực Trung tâm Đồng bằng Mê-kông
(CMDRCP)
Number
Dia -meter (mm) Length (mm)
Rebar No Đường kính (mm) Chiều dài (mm) Remark
Số lượng
Cốt thép số Design Actual Design Actual Design Actual Ghi nhận
Thiết kế Thực tế Thiết kế Thực tế Thiết kế Thực tế
Acceptance (Sự chấp thuận): Accepted (chấp thuận): Not accepted (không chấp thuận):
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
4. Construction Joint between Pile Cap & Stem (Moái noái thi coâng giöõa Beä moùng & Thaân moá)
Removal and cleaning of loose concrete
Removal and cleaning of harmful material
Overall Judgement Accepted (Chaáp thuaän) Not accepted (Khoâng chaáp thuaän)
Remark:
(Nhaän xeùt):
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
CL Of bearing
21 22 17
18
20 21 19
18 G5R G4R G3R G2R G1R
19
22
10 11
Bearing pad
9 10
12 11
Checking point 17 18 19 20
Coord. & Lev. X (North) Y (East) Z (Lev) X (North) Y (East) Z (Lev) X (North) Y (East) Z (Lev) X (North) Y (East) Z (Lev)
Design (m)
Actual (m)
Difference (mm)
Hor. Dev. (mm)
Tolerance (mm) ±5 ±10 ±5 ±10 ±5 ±10 ±5 ±10
Conclusion OK OK OK OK OK OK OK OK
Date(dd/mm/yy-ngaøy/thaùng/naêm):
Work Item (Haïng muïc): Preparation for concreting of Abutment Stem, 1st Lift (Chuaån bò ñoå beâ toâng Thaân Moá, Ñôït 1)
Abutment (Moá): Abutment ………... (Moá M…………...)
Remark:
(Nhaän xeùt)
FOR CONTRACTOR
CONTRACT0R FOR CONSULTANT
CONSULTANT
NHÀ THẦU TƯ VẤN
Const. Team Site Engineer Const. Manager Inspector
CONSTRUCTION TEAM SITE ENGINEER CONSTRUCTION INSPECTOR
ĐỘI XÂY DỰNG GIÁM SAT HIỆN TRƯỜNG MANAGER GIÁM SÁT VIÊN
GIÁM ĐỐC THI CÔNG
Br-IS-AA-06
TỔNG CÔNG TY ĐẦU TƯ PHÁT TRIỂN ĐƯỜNG CAO TỐC VIỆT NAM - VIET NAM EXPRESSWAY CORP.
BQLDA ĐƯỜNG CAO TỐC HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY
HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY EXPRESSWAY PROJECT MANAGEMENT UNIT
Project: NORTH - SOUTH EXPRESSWAY CONSTRUCTION PROJECT Package (Gói thầu): 1a
(HO CHI MINH CITY - DAU GIAY SECTION) Station: km 4+000 - km 7+500
(Tên dự án: Dự án đường cao tốc Bắc - Nam đoạn TP HCM - Dầu Giây) (Lý trình: km 4+100 - km 7+500)
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
Date (d/m/yy-ngày/tháng/năm):
Work Item (Hạng mục): Concreting of Abutment Stem, 1st Lift (Đổ bê tông Thân Mố, Đợt 1 )
Abutment (Mố) : Abutment ………... (Moá M…………...)
Temperatu
Number Air
Volume Name of Slump re of
No. Time Vehicle No. of temperatur Weather Remark
(m3) Sample (cm) concrete
Samples e
< 32º
Khối
Biển số xe Số lượng Độ sụt Nhiệt độ BT Nhiệt độ
Số Thời gian lượng Tên mẫu Thời tiết Ghi nhận
mẫu thử (cm) < 32º không khí
(m3)
1
2
3
4
5
6
7
8
9
10
11
12
Acceptance (Nghiệm thu): Accepted (Chấp thuận) Ö Not accepted (Không chấp thuận)
FOR CONTRACTOR
CONTRACT0R FOR CONSULTANT
CONSULTANT
NHÀ THẦU TƯ VẤN
Const. Team Site Engineer Const. Manager Inspector
CONSTRUCTION TEAM SITE ENGINEER CONSTRUCTION MANAGER INSPECTOR
ĐỘI XÂY DỰNG GIÁM SAT HIỆN TRƯỜNG GIÁM ĐỐC THI CÔNG GIÁM SÁT VIÊN
Br-IS-AA-07
TỔNG CÔNG TY ĐẦU TƯ PHÁT TRIỂN ĐƯỜNG CAO TỐC VIỆT NAM - VIET NAM EXPRESSWAY CORP.
BQLDA ĐƯỜNG CAO TỐC HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY
HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY EXPRESSWAY PROJECT MANAGEMENT UNIT
Project: NORTH - SOUTH EXPRESSWAY CONSTRUCTION PROJECT Package (Gói thầu): 1a
(HO CHI MINH CITY - DAU GIAY SECTION) Station: km 4+000 - km 7+500
(Tên dự án: Dự án đường cao tốc Bắc - Nam đoạn TP HCM - Dầu Giây(Lý trình: km 4+100 - km 7+500)
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
Date (d/m/yy-ngaøy/thaùng/naêm):
Work Item (Haïng muïc): Concreting of Abutment Stem, 1st Lift (Ñoå beâ toâng Thaân Moáï, Ñôït 1)
Abutment (Moá) : Abutment ………... (Moá M…………...)
General Information (Thoâng tin chung)
Concrete Class (Caáp beâ toâng) C30-(Design Mix Name - Teân caáp phoái)
Design Conc. Vol. (Khoái löôïng beâ toâng thieát keá) 0.00 m3 ; Actual Conc. Vol. (Kh/lg BT thöïc teá): 0.00 m3
Curing method (Phöông phaùp baûo döôõng) Bags + water (Bao boá + töôùi nöôùc)
Protection from raining (Baûo veä khi möa) Cover with plastic sheet (Che phuû baèng baït nhöïa)
Pouring method (Phöông phaùp ñoå) Pumping car (Xe bôm beâ toâng)
Total 0 0
Remark:
(Nhaän xeùt)
FOR CONTRACT0R
CONTRACTOR FORCONSULTANT
CONSULTANT
NHÀ THẦU TƯ VẤN
Const. Team Site Engineer Const. Manager Inspector
CONSTRUCTION TEAM SITE ENGINEER CONSTRUCTION MANAGER INSPECTOR
ĐỘI XÂY DỰNG GIÁM SAT HIỆN TRƯỜNG GIÁM ĐỐC THI CÔNG GIÁM SÁT VIÊN
Br-IS-AA-07
TỔNG CÔNG TY ĐẦU TƯ PHÁT TRIỂN ĐƯỜNG CAO TỐC VIỆT NAM - VIET NAM EXPRESSWAY CORP.
BQLDA ĐƯỜNG CAO TỐC HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY
HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY EXPRESSWAY PROJECT MANAGEMENT UNIT
Project: NORTH - SOUTH EXPRESSWAY CONSTRUCTION PROJECT Package (Gói thầu): 1a
(HO CHI MINH CITY - DAU GIAY SECTION) Station: km 4+000 - km 7+500
(Tên dự án: Dự án đường cao tốc Bắc - Nam đoạn TP HCM - Dầu Giây(Lý trình: km 4+100 - km 7+500)
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
Date (d/m/yy-ngaøy/thaùng/naêm):
Work Item (Haïng muïc): Concreting of Abutment Stem, 1st Lift (Ñoå beâ toâng Thaân Moáï, Ñôït 1)
Abutment (Moá) : Abutment ………... (Moá M…………...)
General Information (Thoâng tin chung)
Concrete Class (Caáp beâ toâng) C30-(Design Mix Name - Teân caáp phoái)
Design Conc. Vol. (Khoái löôïng beâ toâng thieát keá) 0.00 m3 ; Actual Conc. Vol. (Kh/lg BT thöïc teá): 0.00 m3
Curing method (Phöông phaùp baûo döôõng) Bags + water (Bao boá + töôùi nöôùc)
Protection from raining (Baûo veä khi möa) Cover with plastic sheet (Che phuû baèng baït nhöïa)
Pouring method (Phöông phaùp ñoå) Pumping car (Xe bôm beâ toâng)
Number
Dia -meter (mm) Length (mm)
Rebar No Đường kính (mm) Chiều dài (mm) Remark
Số lượng
Cốt thép số Design Actual Design Actual Design Actual Ghi nhận
Thiết kế Thực tế Thiết kế Thực tế Thiết kế Thực tế
Acceptance (Sự chấp thuận): Accepted (chấp thuận): Not accepted (không chấp thuận):
4. Construction Joint between 1st & 2nd Lift (Moái noái thi coâng giöõa Thaân moá Ñôït 1 & 2)
Removal and cleaning of loose concrete
Removal and cleaning of harmful material
Overall Judgement Accepted (Chaáp thuaän) Not accepted (Khoâng chaáp thuaän)
Remark:
(Nhaän xeùt):
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
34
PLAN OF ABUTMENT CL Of abutment SIDE VIEW - ABUTMENT
CL Of bearing
34 33
32 31
Anchor bar D25
29 32 29 30
33
30 31
G5R G4R G3R G2R G1R
Bearing pad
Remark :
(Nhaän xeùt)
FOR CONTRACTOR
CONTRACT0R FOR CONSULTANT
CONSULTANT
NHÀ THẦU TƯ VẤN
Const. Team Surveyor Const. Manager Surveyor
CONSTRUCTION TEAM SITE ENGINEER CONSTRUCTION MANAGER INSPECTOR
ĐỘI XÂY DỰNG GIÁM SAT HIỆN TRƯỜNG GIÁM ĐỐC THI CÔNG GIÁM SÁT VIÊN
Br-IS-AA-10
TỔNG CÔNG TY ĐẦU TƯ PHÁT TRIỂN ĐƯỜNG CAO TỐC VIỆT NAM - VIET NAM EXPRESSWAY CORP.
BQLDA ĐƯỜNG CAO TỐC HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY
HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY EXPRESSWAY PROJECT MANAGEMENT UNIT
Project: NORTH - SOUTH EXPRESSWAY CONSTRUCTION PROJECT Package (Gói thầu): 1a
(HO CHI MINH CITY - DAU GIAY SECTION) Station: km 4+000 - km 7+500
(Tên dự án: Dự án đường cao tốc Bắc - Nam đoạn TP HCM - Dầu Giây) (Lý trình: km 4+100 - km 7+500)
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
Date(dd/mm/yy-ngaøy/thaùng/naêm):
Work Item (Haïng muïc): Preparation for concreting of Abutment, 2nd Lift (Chuaån bò ñoå beâ toâng Thaân Moá, Ñôït 2)
Abutment (Moá): Abutment ………... (Moá M…………...)
Remark:
(Nhaän xeùt)
FORCONTRACT0R
CONTRACTOR FOR CONSULTANT
CONSULTANT
NHÀ THẦU TƯ VẤN
Const. Team Site Engineer Const. Manager Inspector
CONSTRUCTION TEAM SITE ENGINEER CONSTRUCTION MANAGER INSPECTOR
ĐỘI XÂY DỰNG GIÁM SAT HIỆN TRƯỜNG GIÁM ĐỐC THI CÔNG GIÁM SÁT VIÊN
Br-IS-AA-06
TỔNG CÔNG TY ĐẦU TƯ PHÁT TRIỂN ĐƯỜNG CAO TỐC VIỆT NAM - VIET NAM EXPRESSWAY CORP.
BQLDA ĐƯỜNG CAO TỐC HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY
HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY EXPRESSWAY PROJECT MANAGEMENT UNIT
Project: NORTH - SOUTH EXPRESSWAY CONSTRUCTION PROJECT Package (Gói thầu): 1a
(HO CHI MINH CITY - DAU GIAY SECTION) Station: km 4+000 - km 7+500
(Tên dự án: Dự án đường cao tốc Bắc - Nam đoạn TP HCM - Dầu Giây) (Lý trình: km 4+100 - km 7+500)
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
Date (d/m/yy-ngày/tháng/năm):
Work Item (Hạng mục): Concreting of Abutment Stem, 2nd Lift (Đổ bê tông Thân Mố, Đợt 2)
Abutment (Mố) : Abutment ………... (Moá M…………...)
Temperatu
Number Air
Volume Name of Slump re of
No. Time Vehicle No. of temperatur Weather Remark
(m3) Sample (cm) concrete
Samples e
< 32º
Khối
Biển số xe Số lượng Độ sụt Nhiệt độ BT Nhiệt độ
Số Thời gian lượng Tên mẫu Thời tiết Ghi nhận
mẫu thử (cm) < 32º không khí
(m3)
1
2
3
4
5
6
7
8
9
10
11
12
Acceptance (Nghiệm thu): Accepted (Chấp thuận) Ö Not accepted (Không chấp thuận)
FOR CONTRACT0R
CONTRACTOR FORCONSULTANT
CONSULTANT
NHÀ THẦU TƯ VẤN
Const. Team Site Engineer Const. Manager Inspector
CONSTRUCTION TEAM SITE ENGINEER CONSTRUCTION MANAGER INSPECTOR
ĐỘI XÂY DỰNG GIÁM SAT HIỆN TRƯỜNG GIÁM ĐỐC THI CÔNG GIÁM SÁT VIÊN
Br-IS-AA-11
TỔNG CÔNG TY ĐẦU TƯ PHÁT TRIỂN ĐƯỜNG CAO TỐC VIỆT NAM - VIET NAM EXPRESSWAY CORP.
BQLDA ĐƯỜNG CAO TỐC HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY
HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY EXPRESSWAY PROJECT MANAGEMENT UNIT
Project: NORTH - SOUTH EXPRESSWAY CONSTRUCTION PROJECT Package (Gói thầu): 1a
(HO CHI MINH CITY - DAU GIAY SECTION) Station: km 4+000 - km 7+500
(Tên dự án: Dự án đường cao tốc Bắc - Nam đoạn TP HCM - Dầu Giây(Lý trình: km 4+100 - km 7+500)
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
Date (d/m/yy-ngaøy/thaùng/naêm):
Work Item (Haïng muïc): Concreting of Abutment Stem, 2nd Lift (Ñoå beâ toâng Thaân Moá, Ñôït 2)
Abutment (Moá) : Abutment M1R (Moá M1R)
General Information (Thoâng tin chung)
Concrete Class (Caáp beâ toâng) C30-(Design Mix Name - Teân caáp phoái)
Design Conc. Vol. (Khoái löôïng beâ toâng thieát keá) 0.00 m3 ; Actual Conc. Vol. (Kh/lg BT thöïc teá): 0.00 m3
Curing method (Phöông phaùp baûo döôõng) Bags + water (Bao boá + töôùi nöôùc)
Protection from raining (Baûo veä khi möa) Cover with plastic sheet (Che phuû baèng baït nhöïa)
Pouring method (Phöông phaùp ñoå) Pumping car (Xe bôm beâ toâng)
Total 0 0
Remark:
(Nhaän xeùt)
FOR CONTRACT0R
CONTRACTOR FORCONSULTANT
CONSULTANT
NHÀ THẦU TƯ VẤN
Const. Team Site Engineer Const. Manager Inspector
CONSTRUCTION TEAM SITE ENGINEER CONSTRUCTION MANAGER INSPECTOR
ĐỘI XÂY DỰNG GIÁM SAT HIỆN TRƯỜNG GIÁM ĐỐC THI CÔNG GIÁM SÁT VIÊN
Br-IS-AA-11
TỔNG CÔNG TY ĐẦU TƯ PHÁT TRIỂN ĐƯỜNG CAO TỐC VIỆT NAM - VIET NAM EXPRESSWAY CORP.
BQLDA ĐƯỜNG CAO TỐC HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY
HỒ CHÍ MINH - LONG THÀNH - DẦU GIÂY EXPRESSWAY PROJECT MANAGEMENT UNIT
Project: NORTH - SOUTH EXPRESSWAY CONSTRUCTION PROJECT Package (Gói thầu): 1a
(HO CHI MINH CITY - DAU GIAY SECTION) Station: km 4+000 - km 7+500
(Tên dự án: Dự án đường cao tốc Bắc - Nam đoạn TP HCM - Dầu Giây(Lý trình: km 4+100 - km 7+500)
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
Date (d/m/yy-ngaøy/thaùng/naêm):
Work Item (Haïng muïc): Concreting of Abutment Stem, 2nd Lift (Ñoå beâ toâng Thaân Moá, Ñôït 2)
Abutment (Moá) : Abutment M1R (Moá M1R)
General Information (Thoâng tin chung)
Concrete Class (Caáp beâ toâng) C30-(Design Mix Name - Teân caáp phoái)
Design Conc. Vol. (Khoái löôïng beâ toâng thieát keá) 0.00 m3 ; Actual Conc. Vol. (Kh/lg BT thöïc teá): 0.00 m3
Curing method (Phöông phaùp baûo döôõng) Bags + water (Bao boá + töôùi nöôùc)
Protection from raining (Baûo veä khi möa) Cover with plastic sheet (Che phuû baèng baït nhöïa)
Pouring method (Phöông phaùp ñoå) Pumping car (Xe bôm beâ toâng)
Consultants (TV): CONSORTIUM OF NIPPON KOEI AND TEDIS Contractor (Nhà thầu): CHINA ROAD & BRIDGE CORP.
34
PLAN OF ABUTMENT CL Of abutment SIDE VIEW - ABUTMENT
CL Of bearing
34 33
32 31
Anchor bar D25
32
30
12
33
31
30 18
22
19
18 G5R G4R G3R G2R G1R
19
22
10 11
Bearing pad
10
12 11
Checking point 19 22 30 31
Coord. &
X (North) Y (East) Z (Lev) X (North) Y (East) Z (Lev) X (North) Y (East) Z (Lev) X (North) Y (East) Z (Lev)
Level
Design (m)
Actual (m)
Difference (mm)
Hor. Dev. (mm)
Tolerance (mm) ±5 ±5 ±5 ±5 ±5 ±5 ±5 ±5
Conclusion OK OK OK OK OK OK OK OK
Remarks
(Nhaän xeùt)