METHOD
AOA/CPM
A B C
AON/PDM
A B C
2) Kegiatan Predecessor
A -
B A
C A
AOA/CPM
3
B
A
1 2
C 4
AON/PDM
B
A
C
3) Kegiatan Predecessor
A -
B -
C A, B
AOA/CPM
1 A
C
3 4
2 B
AON/PDM
A
C
B
4) Kegiatan Predecessor
A -
B A
C A
D B
E C
AOA/CPM
D
3 5
B
A
1 2 E
C 4 6
AON/PDM
B D
A
C E
5) Kegiatan Predecessor
A -
B A
C A
D B
E B, C
AOA/CPM D
3 5
B
A
1 X
2
E
C 4 6
AON/PDM
B D
A
C E
6) Kegiatan Predecessor
A -
B A
C A
D B, C
E B, C
3
B
A
1 X 5
AOA/CPM 2 D
C 4 E
6
B
AON/PDM A D
C
E
7) A B
1 2 3
AOA/CPM X
C D
4 5 6
A B
AON/PDM
C D
F
8) 5 6
D
AOA/CPM E
3
B X
A C
1 2 4
AON/PDM
B D
A F
C E
9)
AOA/CPM B
X
A D
C
AON/PDM
B
A D
C
AON/PDM mempunyai hubungan logis ketergantungan
yang bervariasi. Jika di AOA/CPM hanya terdapat
hubungan logis/konstrain FS = 0 dan SS = 0, maka pada
AON/PDM ada 4 macam hubungan logis/konstrain yang
bervariasi, yaitu.
1) Finish to Finish (FF) yaitu hubungan yang menunjukkan
bahwa selesainya (Finish) kegiatan berikutnya (Successor)
tergantung pada selesainya (Finish) kegiatan sebelumnya
(Predecessor)
FFij
i
j
i
j FFij = O
FFij =0, artinya selesainya
kegiatan i dan j secara bersamaan
FFij = x, artinya kegiatan j selesainya setelah kegiatan i selesai.
j
x
2) Finish to Start (FS) yaitu hubungan yang menunjukkan
bahwa mulainya (Start) kegiatan berikutnya (Successor)
tergantung pada selesainya (Finish) kegiatan sebelumnya
(Predecessor)
FS ij
i j
i
j
FS ij=0
FSij = x → kegiatan j dimulai setelah x hari kegiatan i selesai
SSij
j
SSij = 0 j
SSij = x → kegiatan j dimulai setelah x hari kegiatan i dimulai.
x
4) Start to Finish (SF) yaitu hubungan yang menunjukkan
bahwa selesainya (Finish) kegiatan berikutnya
(Successor) tergantung pada mulainya (Start) kegiatan
sebelumnya (Predecessor)
i SFij
1 ES EF
Act Activity
Duration
No Discription
LS LF
2 ES Duration EF
Activity Number
Activity Discription
LS TF LF
3 Activity Number TF
Activity OD
Discription RD
ES EF
OD = Original Duration
RD = Remaining Duration
Activity Dur TF
4 Number
Activity Discription
ES EF
LS LF
3.2 Perhitungan PDM
Pada dasarnya perhitungan PDM sama
dengan CPM, yaitu menggunakan
perhitungan ke muka (forward pass) untuk
menentukan Earlies Start(ES) dan Earliest
Finish (EF). Dan menggunakan
perhitungan ke belakang (backward pass)
untuk menentukan Latest Finish (LF) dan
Latest Start (LS) berdasarkan hubungan
logis/ketergantungan yang ada antar
kegiatan
3.2.1 Perhitungan ke Muka (Forward Pass)
Untuk AON/PDM kegiatan awal (start) merupakan
suatu aktifitas dalam bentuk node yangdurasinya =
0 dan ES, EF, LS dan LF nya juga sama dengan nol
ES D EF
kegiatan
LS TF LF
0 0 0 0
Start A
1. Hubungan Kegiatan Finish to Finish (FF)
FFij
EF j = EF i + FF ij
ES j = EF j - Dj
FF = 5
5 10 15
A
12 8 20
B
EF B = EFA + FF AB = 15 + 5 = 20
ES B = EF B – DB = 20 - 8 =12
Jika lebih dari satu kegiatan Predecessor (yang mendahului):
FF 3
8 6 14
A
FF 5
10 5 15
14 8 22
B
P
FF6
i j
ES j = EF i + FS ij
EF j = ES j + Dj
5 10 15 FS2 17 8 25
A B
EF B = EF A + FS AB = 15 + 2 = 17
ES B = EF B + DB = 17 + 8 = 25
Jika lebih dari satu kegiatan Predecessor
9 6 15
A FS4
10 5 15 19 8 27
FS2
B P
6 10 16 FS3
C
ESP = max EFA+FSAP = 15+4 =19
EFB+FSBP = 15+2 =17
EFC+FSCP = 16+3 =19
EFP = ESPmax+ DP
=19 + 8 =27
3. Hubungan Kegiatan Start to Start (SS)
i j
SSij
5 10 15 9 8 17
B B
SS4
10 5 15
B SS5 15 8 23
P
6 10 16
C
SS6
SFij
5 10 15 4 8 12
A B
SF7
SF7
10 5 15 9 8 17
B P
6 10 16
C
SF8
FFij
Dj Dj
i j
LSi LFi LSj LFj
A B
25 35 40
FF5 8
P
40
6 7
M Q
26 32 42
FF4
10
LFM = min LFP - FFPM = 40 - 5 = 35
R
LFQ - FFQM = 42 - 4 = 38
LFR - FFRM = 38 - 6 = 32 38
LSM = LFMmiN- DM = 32 - 6 = 26 FF6
2. Hubungan Finish to Start (FS)
Dj
FSij
i j
LSi LFi LSj
6 8
FS5
A B
21 27 32 40
LFA = LFB - FFBA = 32 – 5 = 27
LSA = LFA - DA = 27 - 6 = 21
Dj
i j
LSi LFi LSj
SSij
LSi = LSi - FSij
LFi = LFj + Dj
6 8
A B
28 34 32 40
SS4
Dj
i j
LSi LFj
SFij
LSi = LFj - SFij
LFi = LSi + Di
6 8
A B
30 36 32 40
SF10
1 FS14 = 1 4
29
17 19 11 30 30
28
18
19
17
2 FS24 = 0
19
SS34 = 3
3
14
HITUNGAN KE BELAKANG
j FS14 = 1 2
17 19
8 31
23 31 35
34
28
FS13 = 0
3
19
31
SS14 = 2
30
Contoh:
No Kegiatan Durasi D Predecessor Hubungan/ Lag/Lead
konstrain
1 A 5 - - -
2 B 6 A FF 4
3 C 4 A FS 2
4 D 4 B SS 2
5 E 9 B SS 3
6 F 6 B, C FS, FF 0;2
7 G 3 D SF 4
8 H 6 E, F SS, SF 1;4
9 I 4 G, H FF, SS 5,2
SS2
SF4
3 6 9
B 5 4 9
3 9 D FF5
5 9 6 3 9
G
FF4 6 9
0 5 5 6 9 15 10 4 14
SS3 SS2
A E I
0 5 7 16 10 14
SS1 7 6 13
FS2 FS0 H
8 14
7 4 11 9 6 15
C F
10 14 10 16
FF2
SF4
Hitungan ke Muka
Titik A:
ESA = 0
EFA = 0 + 5 = 5
Titik B:
EFB = EFA + FFAB = 5+4 = 9
ESB = EFB – DB = 9-6 = 3
Titik C
ESC = EFA + FSA = 5 +2 = 7
EFC = ESC + DC = 7 + 4 = 11
Titik D
ESD = ESB + SSBD = 3 + 2 = 5
EFD = ESD + DD =5+4=9
Titik E
ESE = ESB + SSBE = 3 + 3 = 5
EFE = ESE + DE = 6 + 9 = 15
Titik F
Dari C → EFF = EFC + FFCF = 11 + 2 = 13
ESF = EEF + DF = 13 - 6 = 7
Dari B → ESF = EFB + FSBF = 9+0 =9
EFF = ESF + DF = 9 + 6 = 15
Titik H:
Dari E → ESH = ESE + SSEH = 6 + 1 = 7
FH = EEF + DF = 7 + 6 = 13
Titik I:
Dari G → EFI = EFG + FFGI = 9 + 5 = 14
ESI = EFI - DI = 14 – 4 = 10
Titik G:
LFG = LFI – FFGI = 14 – 5 = 9
LSG = LFG – DG = 9 – 3 = 6
Titik F:
LSF = LFH – SFHF = 14 -4 = 9
LSF = LSF + DF = 10 + 6 = 16
Titik E:
LSE = LSH – SSHE = 8 -1 = 7
LFE = LSE + DE = 7 + 9 = 16
Titik D:
LSE = LSH – SSHE = 9 - 4 = 5
LFE = LSE + DE =5+4 =9
Titik C:
LFC = LFF – FFFB = 16 - 2 = 14
LSC = LFC – DC = 14 – 4 =10
Titik B:
Dari titik F → LFB = LSF - FSFB = 10 – 0 = 10
LSB = LSB – DB = 10 – 6 = 4
Dari titik E → LSB = LSB + DB = 10 – 6 = 4
LFB = LSB + DB = 4 + 6 = 10
Dari titik D → LSB = LSD – SSDB =5–2 =3
LFB = LSB + DB =3+6 =9
Hitungan ke belakang (lanjutan)
Jalur Kritis :
A–B–D–G–I
Lama Proyek = 14 minggu