Professional Documents
Culture Documents
Chapter 5
Erosion and
Sediment Control
July 2002 i
Road Drainage Design Manual Chapter 5: Erosion and Sediment Control
Manual Contents
Chapter 1
Overview
5 Chapter 2
Site Assessment
Chapter 3
Hydrology and Design Criteria
Chapter 4
Design
Chapter 5
Erosion and Sediment Control
Chapter 6
Maintenance and Remediation
Chapter 7
Worked Examples
Chapter 8
References
ii July 2002
Road Drainage Design Manual Chapter 5: Erosion and Sediment Control
Table of Contents
5
Chapter 4
Design
Chapter 6
Maintenance &
Remediation
Introduction
Revegetation
Maintenance of Control
Measures
Chapter 5 Erosion and Sediment
Control Plans
• Benefits
EROSION AND • Timing
• Report
Installation of Control SEDIMENT CONTROL • Drawings
Measures
• Monitoring
Design of Control
Measures
Preparing ESCPs
• Site Characteristics
• Areas of Disturbance
• Control Selection
iv July 2002
Road Drainage Design Manual Chapter 5: Erosion and Sediment Control
Chapter 5
Erosion and Sediment
Control
5.1 Introduction 5.2 Erosion and
5
Sedimentation
Chapter 5 is designed to assist contractors (and
those working with contractors) in managing Construction of road drainage infrastructure has
drainage and preventing erosion and the potential to cause environmental harm if not
sedimentation whilst undertaking road or drainage properly managed. One of the most common
works. This is achieved by preparing and environmental impacts of drainage construction is
implementing Erosion and Sediment Control the erosion of soil and subsequent sedimentation
Plans (ESCP). of watercourses or drainage infrastructure.
In preparing erosion and sediment control plans or The loss of soil from a construction site can also
undertaking construction activities, legislative be costly in terms of remediation and replacement
approvals relating to erosion and sediment control costs. Removal of deposited sediment will often
(ESC) may be required. These may include incur high costs.
permits for undertaking works in watercourses,
taking of water from a watercourse or removing Sediment deposition and suspension within water
vegetation from a watercourse. These legislative courses has direct impacts on water quality and
requirements are outlined in Section 1.3 and aquatic wildlife. This could include fauna
are further detailed in the Environmental mortality, habitat damage and disturbance to
Legislation Register (Main Roads, 2001). breeding patterns. Soil loss can also have impacts
on adjacent properties such as farms and urban
Chapter 5 can be applied to the preparation of residential properties.
ESCPs for either construction or maintenance
works.
5
ESCPs are dynamic or ‘living’ documents that ESCPs offer a number of benefits, including:
should change with each stage of a project. They
should be reviewed and modified regularly such • providing a systematic approach to ESC;
as when new information and products become
available, construction procedures change or • providing subcontractors (who read or use the
when there is a change in resource availability. ESCP) with an understanding of ESC
requirements;
The Main Roads Standard Specification
MRS11.51 “Environmental Management” • providing cost effective methods and timing for
requires a contractor to take all reasonable ESC;
precautions to prevent soil erosion from any lands
• the ability to reduce downtime associated with
used or occupied. It then requires the contractor to
wet weather, clean-up costs and delays in
submit an ESCP seven (7) days prior to land
project completion;
disturbance.
• reducing off-site impacts (eg. social,
environmental and economic impacts); and
Tender documents
issued
5
Contractor
submits tender
Contract
Award
14
DAYS
Project Superintendent notifies
acceptance or otherwise of
EMP & ESCP
7
ACCEPTANCE NON-ACCEPTANCE
DAYS
5 • Topography;
• Soils;
and temporary measures to control erosion
and sedimentation; and
Appendices • Stockpiles;
• ESCP Drawings; • Receiving waterways;
• Fact Sheets for ESC measures;
• North Point;
• Calculations (eg. hydrology or sediment basin
sizing); • Scale (preferred scale between 1:500 to
1:2,500);
• ESCP Checklist;
• Supporting Data (aerial photos, construction • Title Block (should include Project Name,
program, EMP requirements, revegetation ESCP Title, Plan No., Date, Chainage); and
specification).
• Legend (should include standard symbols for
A Document Control Status and Revision No. control measures).
must also be inserted in the front of the ESCP
report.
5.4 Preparing ESCPs
In accordance with MRS 11.51, the ESCP shall
consist of scale diagrams indicating the following: The ESCP is written by the Contractor (or
(a) Features of the site including contours and Consultant) for the Contractor. It is the
drainage paths; Contractor's commitment to erosion and sediment
control for the project. As such, it needs to be
(b) Relevant construction details of all erosion prepared in a format and to a level that can be
and sediment control structures; easily understood and implemented by the
Contractor’s staff.
(c) All permanent and temporary erosion and
sediment control measures, including the A number of steps are generally followed when
control measures to be implemented in preparing ESCPs, as described in the following
sections. The steps have been ordered in a logical
way such that an understanding of ESC reduce potential ESC impacts of the project.
requirements is obtained up front. This will also Relevant information must be provided in the
ensure relevant information is reviewed prior to contract documents.
the selection and installation of appropriate
control measures, and the selection of monitoring Existing site characteristics should be presented
and maintenance procedures. on an overlay of the construction plans.
5
• Appendix 5A - Fact Sheets for designing, marked on an overlay of the construction
constructing and maintaining control measures; drawings:
When this information is overlaid on the • the preferred order of controls (i.e. drainage,
construction drawings and site characteristics velocity, erosion, sedimentation).
overlay, it should be possible to visualise how and
where construction works may lead to erosion and These are discussed further below.
sedimentation.
Constraints and Opportunities
Step 2
The Contractor should identify ESC constraints
5
If applicable, ensure the following items are and opportunities appropriate to the project. This
marked on an overlay of the construction may include consideration of:
drawings:
1. cut and fill locations; • available resources (eg. surplus rock, access for
hydromulching);
2. construction stages; and
• topography (eg. opportunities to divert water);
3. location of site access points, parking areas, site
compounds, storage areas, and stockpile areas. • receiving waterways;
• budget; and
5.4.3 Step 3 - Selection of
Controls • timing of construction.
Steps 1 and 2 have involved collation of the The duration of construction and the life of
following information: control measures must be considered in addition
to the availability of measures.
• construction plans (including details of cross
and longitudinal drainage); One of the key criteria to be considered when
selecting ESC measures is the timing of
• environmental information overlay (eg. soils, construction. Where construction is scheduled to
vegetation, water courses); occur during peak rainfall months, the potential
for erosion will be at a maximum. Hence, it will
• construction information overlay (eg. timing of be necessary to:
stages); and
1. commit a higher budget to ESC, and
• Contract Documents.
2. minimise the time of exposure of any part of
Step 3 involves using the above information to the site, and/or
assist in the selection of appropriate control
measures for the project. Use should also be made 3. reschedule construction.
of the ESC selection tables from Chapter 3.
Selected measures should be marked on Potential for Environmental Harm
construction drawings that are suitable for use in
the field. Standard symbols for control measures The Contractor should identify the activities
are contained in standard drawings and should be likely to cause most environmental harm, the
used where practicable. If the project involves areas at most risk, and the extent of potential
staging, standard symbols will need to be marked impacts. The project REF will assist in providing
on the construction drawings for each stage. such information. For example, disturbance to an
area of dispersive soil upstream of a sensitive
The following factors should be considered prior watercourse would be a high risk activity.
to selecting ESC measures:
Such activities/areas/impacts should be given
• constraints and opportunities; highest priority in terms of ESC. This will ensure
that most effort is given to the areas likely to Table 5.1 Measures for Drainage Control
cause most environmental harm.
Practice Velocity Application
Range
Drainage Controls Diversion Low - Diversion of flow
Banks Medium away from
Drainage paths where stormwater enters the site disturbed areas.
will have been identified and mapped on the Diversion Medium Large drainage
Channel/Drain areas.
overlay during Step 1. This information should be
Chutes High Passage of flow
used to select and locate appropriate drainage
5
down steep slopes or
controls. embankments.
Drop Pipes High Conveyance of flow
Where practicable, overland drainage flow should down long or irregular
be intercepted and conveyed around or through grades.
the site without flowing across disturbed areas. Grass-lined Low - Alternative to
Channels Medium hard channel linings
Use of existing stable flow paths (ie. watercourses in urban environment.
or drains) is preferable, however in the absence of Reinforced Medium - Alternative to
these, it will be necessary to: Grass-lined High hard channel linings
Channels in urban environment.
(a) construct temporary drains or watercourses; Geotextile Medium - Areas requiring
Lined Channels High quick establishment.
or
Rock Lined Medium Temporary and
(b) construct permanent waterways prior to the Channels permanent channels.
commencement of other works. Rock Mattress High/ Areas with turbulent
Channels Turbulent flow or high velocity.
Can be used as a
permanent measure.
Channels with High Protection against
impervious linings high velocity
Straw Low Only for short term or
Bales emergency protection
during storm events
Temporary Low - High Most types of
Watercourse watercourses
Crossings subject to
environmental
imapcts.
Velocity Controls
Measures available to control drainage are The quantity of soil eroded is generally
outlined in Table 5.1, whilst detailed Fact Sheets proportional to soil erosivity and the velocity and
for most types of ESC are provided as Appendix duration of runoff. That is, the longer runoff
5A. occurs for, the lower the acceptable velocty is, and
the greater the potential for soil erosion.
Erosion Controls
5
Knowledge of soil types and risk ratings is very
important in the selection of erosion control
measures. For example, sodic soils are highly
Sand bag check dam erosive and will readily mobilise if not protected.
Hence, best practice requires that disturbance to
these soils is minimised and a high degree of
Areas within the site likely to be subject to erosive protection be provided. This will reduce the
flow velocities should be identified and potential for sediment mobilisation and deposition
appropriate control measures selected. in watercourses and drainage lines.
Measures available for velocity control are Measures for controlling erosion are outlined in
outlined in Table 5.2. Most rely on roughening the Table 5.3. These practices are the most common
flow surface or decreasing the longitudinal for road projects in Queensland. A combination of
gradient of the flow path. these control measures and those used to control
flow velocity can increase effectiveness.
Detailed Fact Sheets of ESCs are provided in
Appendix 5A.
Table 5.3 Measures for Erosion Control
5
controls are selected only after first choosing
effective drainage, velocity and erosion controls.
5
formed from many of the filter mediums used
in the design of field or drop inlet sediment
traps, such as:
(i) sediment fence
(ii) sediment fence internally lined with straw
bales
(iii) sediment fence internally lined with
aggregate-filled sand bags
(iv) rock and aggregate (rock filter dam)
(v) block and aggregate
Portable The tanks usually contain one or more Tanks may be sized according to the
sediment compartments that trap sediment and allow the stilling pondde sign rules, with due
tanks chemical dosing. consideration given to the soil type
and expected flow rate.
Stilling ponds Typically a temporary above-ground pond The primary action is that of
formed by an earth embankment, however it gravitational settlement of the
can be below ground effectively making it a sediment, thus these ponds are
sediment basin. The low-flow outlet system usually significantly larger than
may consist of a rock filter dam, otherwise it Filter Ponds. They are normally
may have no formallow-flow outlet system used for long-term or high-flow
other than de-watering via a pump. de-watering jobs.
Practice Description
Floating Silt Geotextile filter fabric (silt curtain} suspended vertically in a water body between contaminated
Curtain and uncontaminated water.
Rock Filter Dam A rock dam constructed across a drainage channel or small watercourse. The dam is formed
primarily from coarse rock with a filter layer on the upstream face. The upstream filter layer
may consist of geotextile filter cloth or a layer of clean agregate.
Sediment Filter Filter cages consist of a prefabricated wire cage anchored to the bed of a channel and filled
Cage with filter material such as straw bales. An earth bank or sandbags are used to each side of the
cage to prevent flow bypassing the filter. Woven sediment fence fabric is placed along the
upstream face of the cage.
Sediment Weir Sediment weirs are formed by constructing two or more parallel wire mesh fences across the
channel, lining the fences with fabric, then placing a filter medium between the fences. An
aggregate filter dam may be placed immediately upstream of the weir. Alternatively, woven
sediment fabric may be placed on the upstream fence to reduce the potential for sediment
blockage of the filter medium. Gravel bags partially filled with gypsum and agregate may be
placed upstream of the weir to assist in turbidity control.
Silt Sock A long geotextile filter tube sealed at the downstream end and connected to a solid open pipe
at the upstream end. The solid pipe is installed through a low-permeability earth or aggregate
weir placed across the stream bed. Sediment-Iaden low-flows are directed into the open end of
the pipe and through the geotextile filter which is simply placed along the bed of the channel
downstream of the weir.
Staked Sediment A standard sediment fence staked across the channel. Woven or non-woven fabric may be
Fence used depending on the expected stream flow and duration of use. A wire mesh backing is
normally placed behind the fabric to provide additional support.
Regular maintenance of drainage, erosion and All temporary control measures should be
sediment controls is as important as correct
installation. The ESCP report or drawings should
therefore document proposed maintenance
inspected and maintained where necessary
immediately after a rainfall event. Areas adjacent
to creeks and drainage paths should have priority
5
activities for each control measure selected. with respect to inspection and protection followed
by devices protecting stormwater inlets.
Requirements for self-auditing the effectiveness
of measures and compliance with the ESCP An example ESC maintenance table is provided
should also be documented. This should include as Table 2 in Appendix 5F.
details of the frequency of all maintenance and
auditing activities.