You are on page 1of 16

Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

Chapter 5

Erosion and
Sediment Control

July 2002 i
Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

Manual Contents

Chapter 1
Overview

5 Chapter 2
Site Assessment

Chapter 3
Hydrology and Design Criteria

Chapter 4
Design

Chapter 5
Erosion and Sediment Control

Chapter 6
Maintenance and Remediation

Chapter 7
Worked Examples

Chapter 8
References

ii July 2002
Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

Table of Contents

5.1 Introduction 5-1

5.2 Erosion and Sedimentation 5-1

5.3 Erosion and Sediment Control Plans 5-2


5.3.1
5.3.2
An ESCP Overview
Benefits
5-2
5-2
5
5.3.3 Timing and Acceptance 5-2
5.3.4 ESCP 5-4

5.4 Preparing ESCPs 5-4


5.4.1 Step 1 - Review Site Characteristics 5-5
5.4.2 Step 2 - Identify Areas of Construction Disturbance 5-5
5.4.3 Step 3 - Selection of Controls 5-6

5.5 Design of Control Measures 5-9

5.6 Installation of Control Measures 5-9

5.7 Maintenance of Control Measures 5-11

5.8 Removing Control Measures 5-11

5.9 Monitoring, Auditing and Reporting ESC 5-12

5.10 Revegetation 5-12

5.11 Design References 5-12

Appendix 5A: ESC Fact Sheets Index 5-13

Appendix 5B: Revegetation Guidelines 5-67

Appendix 5C: Site Inspection Checklist 5-87

Appendix 5D: ESCP Checklist 5-91

Appendix 5E: Principles for Erosion and Sediment Control


during Construction 5-97

Appendix 5F: Example ESCP 5-101

July 2002 iii


Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

5
Chapter 4
Design
Chapter 6
Maintenance &
Remediation

Introduction
Revegetation

Removing Control Erosion and Sedimentation


Measures

Maintenance of Control
Measures
Chapter 5 Erosion and Sediment
Control Plans
• Benefits
EROSION AND • Timing
• Report
Installation of Control SEDIMENT CONTROL • Drawings
Measures
• Monitoring

Design of Control
Measures
Preparing ESCPs
• Site Characteristics
• Areas of Disturbance
• Control Selection

iv July 2002
Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

Chapter 5
Erosion and Sediment
Control
5.1 Introduction 5.2 Erosion and

5
Sedimentation
Chapter 5 is designed to assist contractors (and
those working with contractors) in managing Construction of road drainage infrastructure has
drainage and preventing erosion and the potential to cause environmental harm if not
sedimentation whilst undertaking road or drainage properly managed. One of the most common
works. This is achieved by preparing and environmental impacts of drainage construction is
implementing Erosion and Sediment Control the erosion of soil and subsequent sedimentation
Plans (ESCP). of watercourses or drainage infrastructure.
In preparing erosion and sediment control plans or The loss of soil from a construction site can also
undertaking construction activities, legislative be costly in terms of remediation and replacement
approvals relating to erosion and sediment control costs. Removal of deposited sediment will often
(ESC) may be required. These may include incur high costs.
permits for undertaking works in watercourses,
taking of water from a watercourse or removing Sediment deposition and suspension within water
vegetation from a watercourse. These legislative courses has direct impacts on water quality and
requirements are outlined in Section 1.3 and aquatic wildlife. This could include fauna
are further detailed in the Environmental mortality, habitat damage and disturbance to
Legislation Register (Main Roads, 2001). breeding patterns. Soil loss can also have impacts
on adjacent properties such as farms and urban
Chapter 5 can be applied to the preparation of residential properties.
ESCPs for either construction or maintenance
works.

The process outlined in this chapter relies heavily


on the site assessment process undertaken in
Chapter 2.

The philosophy for Chapter 5 of the Manual


is that site data from Chapter 2 and concept
measures from Chapter 3 should be used to
identify and implement the most suitable
temporary drainage, erosion and sediment
control measures to minimise potential
environmental harm and asset loss during
construction. It is important that the
philosophy of catering for drainage and
preventing erosion is adopted ahead of
providing sediment controls. That is,
sediment controls should be adopted only
when drainage and erosion controls will not
be sufficient.

July 2002 5-1


Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

5.3 Erosion and Sediment allocation of resources to ESC.


Control Plans Regardless of the ESC budget, a number of
fundamental ESC principles need to be applied
5.3.1 An ESCP Overview whilst preparing and implementing the ESCP.
These are further described in Section 5.4.
Erosion and Sediment Control Plans (ESCPs)
detail how the potential impacts of erosion and
sedimentation will be managed for a project. 5.3.2 Benefits

5
ESCPs are dynamic or ‘living’ documents that ESCPs offer a number of benefits, including:
should change with each stage of a project. They
should be reviewed and modified regularly such • providing a systematic approach to ESC;
as when new information and products become
available, construction procedures change or • providing subcontractors (who read or use the
when there is a change in resource availability. ESCP) with an understanding of ESC
requirements;
The Main Roads Standard Specification
MRS11.51 “Environmental Management” • providing cost effective methods and timing for
requires a contractor to take all reasonable ESC;
precautions to prevent soil erosion from any lands
• the ability to reduce downtime associated with
used or occupied. It then requires the contractor to
wet weather, clean-up costs and delays in
submit an ESCP seven (7) days prior to land
project completion;
disturbance.
• reducing off-site impacts (eg. social,
environmental and economic impacts); and

• demonstrating compliance with relevant


legislation and contract documentation and
therefore providing an aid for auditing,
monitoring and maintaining site performance in
relation to ESC.

5.3.3 Timing and Acceptance

The ESCP is a requirement of the Contract


documentation and a hold point in MRS11.51.
ESCPs are prepared by the Contractor as part of
the EMP (Construction) which is submitted to the
Project Superintendent for acceptance following
the award of contract.

The timing for ESCP preparation and approval is


provided in Figure 5.1. The actual number of
days will be determined during detailed design
and should be specified in the contract.

ESCPs will vary in content and detail depending


on the scale of works and the physical
characteristics of the project site. The other major
determining factor is the project budget and the

5-2 July 2002


Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

Tender documents
issued
5
Contractor
submits tender

Contract
Award

ESCP Contractor submits


(7 days prior to EMP(Construction)
site disturbance) (typically 28 days from
HOLD POINT award of contract)

14
DAYS
Project Superintendent notifies
acceptance or otherwise of
EMP & ESCP
7
ACCEPTANCE NON-ACCEPTANCE
DAYS

Commence Revised Contractors’ EMP


construction (Construction) &/or ESCP

Figure 5.1 EMP (Construction) and ESCP Acceptance Process

July 2002 5-3


Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

5.3.4 ESCP advance of, or in conjunction with, clearing


and grubbing operations;
All ESCPs should contain drawings as a
minimum requirement (ie. some projects may (d) An order of works based upon construction
not need an ESCP Report). ESCPs may contain and stabilisation of all culverts and surface
the following information: drainage works at the earliest practical
stage;
Site Characteristics
(e) Proposed time schedules for construction of
• Catchment Description; structures and implementation of permanent

5 • Topography;
• Soils;
and temporary measures to control erosion
and sedimentation; and

• Hydrology; (f) Relevant construction/ maintenance/


removal notes;
• Vegetation;
• Water Quality. These drawings should be attached as Appendix A
of the ESCP report or used as the ESCP if no
Selection of Control Measures report is required. Each drawing should also
contain the following items:
Design, Installation, Maintenance and Removal
of Control Measures • Drainage paths;

Monitoring, Auditing and Reporting • Vegetation;

Appendices • Stockpiles;
• ESCP Drawings; • Receiving waterways;
• Fact Sheets for ESC measures;
• North Point;
• Calculations (eg. hydrology or sediment basin
sizing); • Scale (preferred scale between 1:500 to
1:2,500);
• ESCP Checklist;
• Supporting Data (aerial photos, construction • Title Block (should include Project Name,
program, EMP requirements, revegetation ESCP Title, Plan No., Date, Chainage); and
specification).
• Legend (should include standard symbols for
A Document Control Status and Revision No. control measures).
must also be inserted in the front of the ESCP
report.
5.4 Preparing ESCPs
In accordance with MRS 11.51, the ESCP shall
consist of scale diagrams indicating the following: The ESCP is written by the Contractor (or
(a) Features of the site including contours and Consultant) for the Contractor. It is the
drainage paths; Contractor's commitment to erosion and sediment
control for the project. As such, it needs to be
(b) Relevant construction details of all erosion prepared in a format and to a level that can be
and sediment control structures; easily understood and implemented by the
Contractor’s staff.
(c) All permanent and temporary erosion and
sediment control measures, including the A number of steps are generally followed when
control measures to be implemented in preparing ESCPs, as described in the following
sections. The steps have been ordered in a logical

5-4 July 2002


Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

way such that an understanding of ESC reduce potential ESC impacts of the project.
requirements is obtained up front. This will also Relevant information must be provided in the
ensure relevant information is reviewed prior to contract documents.
the selection and installation of appropriate
control measures, and the selection of monitoring Existing site characteristics should be presented
and maintenance procedures. on an overlay of the construction plans.

The following references are provided to assist Step 1


with preparing an ESCP. These are:
If applicable, ensure the following items are

5
• Appendix 5A - Fact Sheets for designing, marked on an overlay of the construction
constructing and maintaining control measures; drawings:

• Appendix 5B - Revegetation Guidelines; 1. existing and proposed permanent drainage


structures;
• Appendix 5C - ESC Site Inspection Checklist;
2. limits of site (from Contract Documents);
• Appendix 5D - ESCP Checklist;
3. contours (from Contract Documents, REF or
• Appendix 5E - Construction Principles; and site assessment data);

• Appendix 5F - Example ESCP. 4. catchment boundaries, watercourses, drainage


lines and waterbodies within and adjacent to
Preparation of an ESCP will also require a review the site (from site data and REF);
of the data obtained using Chapter 2, and
reference to general principles for drainage, 5. existing vegetation (obtained from REF);
erosion and sediment control, and revegetation
should be incorporated into the ESCP. 6. soil types and properties (from REF and using
Chapter 2);
Typically, an ESCP may comprise both drawings
and a report. This will depend on the allocated 7. special conditions (refer Chapter 3); and
ESC budget. An example structure of an ESCP is
8. erosion risk zones (refer Chapter 2).
given in Clause 5.3.4.
If an ESCP report is being prepared, the above
information can be documented in the Site
5.4.1 Step 1 - Review Site Characteristics section of the ESCP report. This
Characteristics may include important information which cannot
be readily mapped.
Step 1 in preparing an ESCP is to obtain an
understanding of the site’s physical features. This
involves identifying physical constraints and 5.4.2 Step 2 - Identify Areas of
construction opportunities. A thorough Construction Disturbance
understanding of the proposed changes to the site
is also required to enable effective planning and The overlay in Step 1 should depict the major
design of appropriate temporary ESC measures. physical characteristics of the site which may
affect or be affected by erosion and sedimentation.
Much of the required information for Step 1 will
have been obtained from the processes undertaken The purpose of Step 2 is to obtain an
using Chapters 2 and 3 of this manual. Relevant understanding of what land changes may result
information will also be available from the project from construction. An overlay may be prepared
Review of Environmental Factors (REF). The that contains relevant construction information
EMP (Planning) may also be a key source of such as staging, locations for stockpiles,
information relevant to mitigation measures to compounds and access tracks including ancillary

July 2002 5-5


Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

activities. • potential for environmental harm;

When this information is overlaid on the • the preferred order of controls (i.e. drainage,
construction drawings and site characteristics velocity, erosion, sedimentation).
overlay, it should be possible to visualise how and
where construction works may lead to erosion and These are discussed further below.
sedimentation.
Constraints and Opportunities
Step 2
The Contractor should identify ESC constraints

5
If applicable, ensure the following items are and opportunities appropriate to the project. This
marked on an overlay of the construction may include consideration of:
drawings:
1. cut and fill locations; • available resources (eg. surplus rock, access for
hydromulching);
2. construction stages; and
• topography (eg. opportunities to divert water);
3. location of site access points, parking areas, site
compounds, storage areas, and stockpile areas. • receiving waterways;

• budget; and
5.4.3 Step 3 - Selection of
Controls • timing of construction.

Steps 1 and 2 have involved collation of the The duration of construction and the life of
following information: control measures must be considered in addition
to the availability of measures.
• construction plans (including details of cross
and longitudinal drainage); One of the key criteria to be considered when
selecting ESC measures is the timing of
• environmental information overlay (eg. soils, construction. Where construction is scheduled to
vegetation, water courses); occur during peak rainfall months, the potential
for erosion will be at a maximum. Hence, it will
• construction information overlay (eg. timing of be necessary to:
stages); and
1. commit a higher budget to ESC, and
• Contract Documents.
2. minimise the time of exposure of any part of
Step 3 involves using the above information to the site, and/or
assist in the selection of appropriate control
measures for the project. Use should also be made 3. reschedule construction.
of the ESC selection tables from Chapter 3.
Selected measures should be marked on Potential for Environmental Harm
construction drawings that are suitable for use in
the field. Standard symbols for control measures The Contractor should identify the activities
are contained in standard drawings and should be likely to cause most environmental harm, the
used where practicable. If the project involves areas at most risk, and the extent of potential
staging, standard symbols will need to be marked impacts. The project REF will assist in providing
on the construction drawings for each stage. such information. For example, disturbance to an
area of dispersive soil upstream of a sensitive
The following factors should be considered prior watercourse would be a high risk activity.
to selecting ESC measures:
Such activities/areas/impacts should be given
• constraints and opportunities; highest priority in terms of ESC. This will ensure

5-6 July 2002


Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

that most effort is given to the areas likely to Table 5.1 Measures for Drainage Control
cause most environmental harm.
Practice Velocity Application
Range
Drainage Controls Diversion Low - Diversion of flow
Banks Medium away from
Drainage paths where stormwater enters the site disturbed areas.
will have been identified and mapped on the Diversion Medium Large drainage
Channel/Drain areas.
overlay during Step 1. This information should be
Chutes High Passage of flow
used to select and locate appropriate drainage

5
down steep slopes or
controls. embankments.
Drop Pipes High Conveyance of flow
Where practicable, overland drainage flow should down long or irregular
be intercepted and conveyed around or through grades.
the site without flowing across disturbed areas. Grass-lined Low - Alternative to
Channels Medium hard channel linings
Use of existing stable flow paths (ie. watercourses in urban environment.
or drains) is preferable, however in the absence of Reinforced Medium - Alternative to
these, it will be necessary to: Grass-lined High hard channel linings
Channels in urban environment.
(a) construct temporary drains or watercourses; Geotextile Medium - Areas requiring
Lined Channels High quick establishment.
or
Rock Lined Medium Temporary and
(b) construct permanent waterways prior to the Channels permanent channels.
commencement of other works. Rock Mattress High/ Areas with turbulent
Channels Turbulent flow or high velocity.
Can be used as a
permanent measure.
Channels with High Protection against
impervious linings high velocity
Straw Low Only for short term or
Bales emergency protection
during storm events
Temporary Low - High Most types of
Watercourse watercourses
Crossings subject to
environmental
imapcts.

Velocity Controls
Measures available to control drainage are The quantity of soil eroded is generally
outlined in Table 5.1, whilst detailed Fact Sheets proportional to soil erosivity and the velocity and
for most types of ESC are provided as Appendix duration of runoff. That is, the longer runoff
5A. occurs for, the lower the acceptable velocty is, and
the greater the potential for soil erosion.

Reducing flow velocity is thus a key method for


minimising the potential for soil erosion and
subsequent sedimentation.

July 2002 5-7


Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

Erosion Controls

Erosion control practices can protect exposed soil


or reduce the duration of soil exposure.

A review of the soils data mapped in Step 1 will


help identify those areas currently disturbed. Step
2 identified areas of the site that are planned for
disturbance (ie. areas of cut and fill).

5
Knowledge of soil types and risk ratings is very
important in the selection of erosion control
measures. For example, sodic soils are highly
Sand bag check dam erosive and will readily mobilise if not protected.
Hence, best practice requires that disturbance to
these soils is minimised and a high degree of
Areas within the site likely to be subject to erosive protection be provided. This will reduce the
flow velocities should be identified and potential for sediment mobilisation and deposition
appropriate control measures selected. in watercourses and drainage lines.

Measures available for velocity control are Measures for controlling erosion are outlined in
outlined in Table 5.2. Most rely on roughening the Table 5.3. These practices are the most common
flow surface or decreasing the longitudinal for road projects in Queensland. A combination of
gradient of the flow path. these control measures and those used to control
flow velocity can increase effectiveness.
Detailed Fact Sheets of ESCs are provided in
Appendix 5A.
Table 5.3 Measures for Erosion Control

Table 5.2 Measures for Velocity Reduction Practice Application


Chemical Surface Dust control on large areas
Practice Application Stabilisers such as haul roads and
Check Dams access tracks. Some products
• Rock Act as a physical can be used as an alternative
• Recessed Rock barrier and reduce to erosion control blankets.
• Gravel/Sand Bag gradient through ponding. Erosion Control Protection against raindrop
Drop Structures Can be created using rock, Blankets erosion and sheet flow down
timber or geotextile. Reduce batters.
gradient of channel, but Mulching Protection against raindrop
require stabilisation at base - timber erosion in conjunction with
of drop. - rock revegetation.
Lengthen Flowpath Where sufficient room exists, - straw
velocities may be reduced - hydro
through lengthening of the - bitumen emulsion
flowpath. This may be Erosion Control Used to line channels where
achieved using bunds or Mats/Geotextiles medium to high velocities are
baffles. expected.
Increase Roughness Increase roughness through Outlet Protection Control of erosion at outlets.
of Flowpath vegetation, gravel or other Reduces velocity and
barriers to shallow flow. dissipates energy.
However, this will not always Temporary Disturbed, cleared or graded
be cost effective, and Revegetation areas and stockpiles.
calculations will be required (refer Appendix 5B) Provides surface protection
to ensure roughness and soil stability.
treatment remains in place Surface Roughening Increases surface infiltration,
during flow. minimises rutting and reduces
wind erosion.

5-8 July 2002


Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

Note: Detailed Fact Sheets of ESCs are provided in


Appendix 5A.

Sediment Trapping Controls

Sediment is only exported when erosion occurs


with the most efficient form of sediment control
being the prevention of erosion. Hence, sediment

5
controls are selected only after first choosing
effective drainage, velocity and erosion controls.

When soil is eroded, sediment particles are


suspended in runoff and are subject to movement In addition, the techniques shown in Tables 5.5
and deposition. Sediment deposition can have and 5.6 may be used for de-watering and in-
significant impacts on drainage systems and stream sediment control.
aquatic wildlife. Loss of soil and land degradation
are also of concern, as is the cost of cleaning out
drainage structures or clearways. 5.5 Design of Control
Measures
Measures available for sediment control are
outlined in Table 5.4. Some control measures, such as temporary
sediment basins require formal design. Whilst
Table 5.4 Measures for Sedimentation Control ESC measures will not always require formal
design, relevant factors which need to be
Practice Application considered are provided in the Fact Sheets in
Buffer Zones Filtering and trapping of sediment Appendix 5A.
runoff in areas of sheet flow. Most
effective on sandy soils.
Much of the information required to undertake
Grassed Filter Filtering and trapping of sediment
Strips from sheet runoff. Most effective on
formal design will have already been undertaken
sandy soils. when applying earlier Chapters of the manual. For
Construction Removal and trapping of sediment example, estimates of rainfall and runoff needed
Exits from vehicles leaving site. for sizing measures such as diversion banks and
Sediment Used to reduce velocity and pond culvert outlet dissipaters will have been calculated
Fences runoff to promote settlement of
in Chapters 2, 3 and 4. This may reduce the need
entrained sediment. Not to be used
in concentrated flow paths. for additional calculations.
Rock Sediment Placed in gullies and other flow
Trap paths to trap entrained sediment.
Use to form small sediment ponds.
Sediment Used to pond water and settle
5.6 Installation of Control
Basins sediment-laden runoff. Measures
Sediment Weirs Used to intercept concentrated flow,
reduce gully erosion and trap The installation of control measures should be
sediment.
coordinated with the projects’ construction works.
Portable Used in small areas where space for
Sediment sediment basins is limited. Measures should be installed prior to and during
Tanks Used in combination with chemical clearing and grubbing, topsoil stripping and
dosing. stockpiling, installation of access tracks and
Drop Inlet and Used to trap entrained sediment compounds, and cut and fill operations.
Pipe Inlet prior to entering drain
Protection inlet.
General principles for construction site
Note: Detailed Fact Sheets of ESCs are provided in management are provided in Chapter 1. These
Appendix 5A.

July 2002 5-9


Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

Table 5.5 De-watering Sediment Control Techniques

Practice Description Application


Filter bag Large reinforced, non-woven, geotextile fitter Only suitable for low to medium flow
bags attached to the end of a hose or pump rates depending on the sediment
content of the water and the total
surface area of the filter.
Filter pond An enclosed sediment trap into which Only suitable for low to medium
sediment-laden water is pumped. Sediment flow rates depending on the sediment
is filtered from the water as it passes through content of the water and the total
the side walls of the trap. The side walls may surface area of the filter.

5
formed from many of the filter mediums used
in the design of field or drop inlet sediment
traps, such as:
(i) sediment fence
(ii) sediment fence internally lined with straw
bales
(iii) sediment fence internally lined with
aggregate-filled sand bags
(iv) rock and aggregate (rock filter dam)
(v) block and aggregate
Portable The tanks usually contain one or more Tanks may be sized according to the
sediment compartments that trap sediment and allow the stilling pondde sign rules, with due
tanks chemical dosing. consideration given to the soil type
and expected flow rate.
Stilling ponds Typically a temporary above-ground pond The primary action is that of
formed by an earth embankment, however it gravitational settlement of the
can be below ground effectively making it a sediment, thus these ponds are
sediment basin. The low-flow outlet system usually significantly larger than
may consist of a rock filter dam, otherwise it Filter Ponds. They are normally
may have no formallow-flow outlet system used for long-term or high-flow
other than de-watering via a pump. de-watering jobs.

Table 5.6 In-Stream Sediment Control Techniques

Practice Description
Floating Silt Geotextile filter fabric (silt curtain} suspended vertically in a water body between contaminated
Curtain and uncontaminated water.
Rock Filter Dam A rock dam constructed across a drainage channel or small watercourse. The dam is formed
primarily from coarse rock with a filter layer on the upstream face. The upstream filter layer
may consist of geotextile filter cloth or a layer of clean agregate.
Sediment Filter Filter cages consist of a prefabricated wire cage anchored to the bed of a channel and filled
Cage with filter material such as straw bales. An earth bank or sandbags are used to each side of the
cage to prevent flow bypassing the filter. Woven sediment fence fabric is placed along the
upstream face of the cage.
Sediment Weir Sediment weirs are formed by constructing two or more parallel wire mesh fences across the
channel, lining the fences with fabric, then placing a filter medium between the fences. An
aggregate filter dam may be placed immediately upstream of the weir. Alternatively, woven
sediment fabric may be placed on the upstream fence to reduce the potential for sediment
blockage of the filter medium. Gravel bags partially filled with gypsum and agregate may be
placed upstream of the weir to assist in turbidity control.
Silt Sock A long geotextile filter tube sealed at the downstream end and connected to a solid open pipe
at the upstream end. The solid pipe is installed through a low-permeability earth or aggregate
weir placed across the stream bed. Sediment-Iaden low-flows are directed into the open end of
the pipe and through the geotextile filter which is simply placed along the bed of the channel
downstream of the weir.
Staked Sediment A standard sediment fence staked across the channel. Woven or non-woven fabric may be
Fence used depending on the expected stream flow and duration of use. A wire mesh backing is
normally placed behind the fabric to provide additional support.

5-10 July 2002


Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

assist in planning construction activities and additional or alternative controls. If a control


deciding when particular control measures should measure is to be replaced, its replacement should
be installed. be chosen based on the compatibility of the
objectives outlined in the EMP (Construction).

Better control of site access and sound


5.7 Maintenance of Control management practices can minimise the need for
Measures repair and replacement.

Regular maintenance of drainage, erosion and All temporary control measures should be
sediment controls is as important as correct
installation. The ESCP report or drawings should
therefore document proposed maintenance
inspected and maintained where necessary
immediately after a rainfall event. Areas adjacent
to creeks and drainage paths should have priority
5
activities for each control measure selected. with respect to inspection and protection followed
by devices protecting stormwater inlets.
Requirements for self-auditing the effectiveness
of measures and compliance with the ESCP An example ESC maintenance table is provided
should also be documented. This should include as Table 2 in Appendix 5F.
details of the frequency of all maintenance and
auditing activities.

For maintenance of ESCs during construction, the


5.8 Removing Control
defects liability period and the “on-maintenance” Measures
phase, there are two basic requirements. These are
outlined below. All temporary control measures should be
removed after the site is stabilised. This should
Regular Clean-Out generally be specified in the contract. In addition,
any specific requirements for removing control
The frequency of maintaining and/or replacing measures should be documented in the ESCP
control measures should be based on the type of report or on the ESCP drawings. Generic
measure, type of soil, and expected runoff guidelines are provided below:
characteristics. The accessibility of a control
measure after a rainfall event must also be taken • check for evidence of erosion prior to removal
into account when determining the frequency of to ensure erosion will not be increased through
cleaning and hence the required size of the the removal of control measures;
control. As a general rule, control measures
should be cleaned out when 60% full. • remove and dispose of any deposited sediment
in an appropriate manner;
The sediment removed from control measures
should be properly disposed of in accordance with • clean and store ESC materials where
the Contract requirements. These should also state practicable for re-use on other projects;
the location for sediment disposal. Removed
• dispose of waste materials from control
sediment must be prevented from returning to the
measures (ie. damaged sediment fence fabric)
ESC device or to other drainage lines or
in nominated waste disposal areas;
watercourses during subsequent rain events.
• ensure that any machinery used to remove
Repair and Replacement
control measures does not cause excessive
The second key maintenance requirement ground disturbance; and
includes the repair and replacement of
• ensure any revegetation of the area has
deteriorated materials within the control measure
stabilised prior to ESC removal.
(eg. sediment fence fabrics). Controls that are
continually damaged may indicate the need for

July 2002 5-11


Road Drainage Design Manual Chapter 5: Erosion and Sediment Control

Where it is evident that a temporary control should 5.10 Revegetation


not be removed, then the contractor will need to
seek direction from the superindendant. Vegetation is one of the most effective means of
controlling erosion and subsequent sedimentation.
The link between a Revegetation Plan and a ESCP
5.9 Monitoring, Auditing is therefore frequently critical.
and Reporting ESC
Monitoring, auditing and reporting of ESCP

5 implementation is a requirement of the MRS11.51


- Environmental Management. This is part of
Main Roads environmental reporting
responsibilities under the Environmental
Protection Act to notify of actual or potential
environmental harm.

All ESCs are to be inspected weekly and within


24 hours of a rain event or as often as specified in
the Contract specifications. All defects are to be
rectified as soon as practicable and within 7 days
of detection. A generic ESC Site Inspection Revegetation guidelines are provided in Appendix
Checklist is contained in Appendix 5C. This can 5C to assist in selecting appropriate revegetation
be adapted to site specific project conditions and techniques for erosion and sediment control and
the project ESCP. to provide a higher level of understanding to the
The Contractor shall record all non-conformances ESCP author.
on the Site Inspection Checklist. Where a non-
conformance is repeated, the Contractor shall
advise the Superintendent and provide a copy of 5.11 Design References
the relevant non-conformance reports.
Additional design information may be obtained
All monitoring details and Site Inspection from NSW Department of Housing (1998),
Checklists shall be reported in the Monthly Frankcombe et al. (2001).
Environment Report. This shall be submitted to
the Superintendent no later than 7 days after the
end of the month.

The Contractor is also required to establish a


process of auditing the performance of the ESCP.
Such audits must be undertaken by suitably
qualified and experienced personnel. Details of
the audit process (ie. audit frequency, audit
criteria, and Auditor’s details) should be
documented in the EMP.

The ESCP should be reviewed monthly in light of


non-conformances and construction progress.
Revised copies of the ESCP shall be issued to the
Superintendent for acceptance.

5-12 July 2002

You might also like