You are on page 1of 2

REQUEST FOR APPROVAL FORM – RFA

BOMI E & C CONSORTIUM


ESTABLISHMENT OF KENYA ADVANCE INSTITUTE OF SCIENCE AND
TECHNOLOGY (EKAIST)
RFI Number:

CONTRACTOR’S REQUEST RFI Issue Date:


FOR INSPECTION
Inspection Requested By:

REQUEST FOR INSPECTION


Building Req. for Inspection No.

Element
Drawing No.
Material/s
Ready for:  Inspection  Testing  Measurement  Formwork
 Others (specify):
Date ready for Inspection Date
Inspection

SUBMITTED BY: …………………………………….. RECEIVED BY: …………………………………….……


Signature: ……………….. Date: ……………………… Signature: ……………….. Date: …………………….
Contractor: BOMIO E & C CONSORTIUM Consultant: ……………………………………………..

REMARKS
Comments:
………………………………………………………………………………………………………………
……………………………………………………………………………………………….
……………………………………………………………………………………………………………….
……………………………………………………………………………………………………………….

Approved By: ………………………………… Received By: ……………………..………...


REQUEST FOR APPROVAL FORM – RFA

BOMI E & C CONSORTIUM


Signature: ……………………………………… Signature: ………………………………….…
Date: …………………………………………… Date: ……………………………………….…..