INSPECTION REQUEST

IR No.: Date :

Project:

The following elements of work will be available for inspection / witnessing of test on the date and time
mentioned below:

Discipline:
- Civil / Structural - Architectural - MEP - Others (Specify)

Description :

Location:

Drawing / Specification Reference:

DRAWINGS : Attached

Date of Inspection: Time of Inspection:

Work to follow: concrete

Inventure Engineer - QA/QC Engineer:

Project Manager Safety Engineer:

Inspection Request Received by Engineer on (Date): ……../……../……… Time:…….:…….hrs

Approved Approved with Comments Rejected / Resubmit

Engineer's Comments:
………………………..………………………………………………………………………………………………………………………………………………………….
………………………..………………………………………………………………………………………………………………………………………………………….
………………………..………………………………………………………………………………………………………………………………………………………….
………………………..………………………………………………………………………………………………………………………………………………………….
………………………..………………………………………………………………………………………………………………………………………………………….
………………………..………………………………………………………………………………………………………………………………………………………….

………………………..………………………………………………………………………………………………………………………………………………………….

Resident Engineer: ……………………………………………….. Date: ………. / ………. / …………..

Contractor Received by: Signature: Date:

Note: Engineer’s approval does not relieve the contractor from contract obligation and responsibilities.