Select one:
a. Developing a new advertising program
b. Preparing the site for the Olympic Games
c. Designing a space station
d. Production of automobile tires
Certainty: C=1 (Unsure: <67%) C=2 (Mid: >67%) C=3 (Quite sure:
>80%)
e. products
Certainty: C=1 (Unsure: <67%) C=2 (Mid: >67%) C=3 (Quite sure:
>80%)
False
People who are part of the project team need to understand project
management because they
Select one:
a. Need to understand project priorities so they can make independent
decisions.
b. All of these are reasons it is important for project team members
to understand project management.
c. Work with others to create a schedule and budget.
d. Need to understand the project charter or scope statement that defines
the objectives and parameters of the project.
e. Organization politics
Certainty: C=1 (Unsure: <67%) C=2 (Mid: >67%) C=3 (Quite sure:
>80%)
rojects are usually classified into all but one of the following categories.
Which one is NOT one of the typical classifications?
Select one:
a. Political necessity
b. All of these are typical classifications.
c. Compliance and emergency
d. Operational
e. Strategic
Certainty: C=1 (Unsure: <67%) C=2 (Mid: >67%) C=3 (Quite sure:
>80%)
Companies are using which of the following for improving the estimating
process for future projects?
Select one:
a. Establishing an estimating training course for all employees
b. Benchmarking and using the experience of other companies
c. Adjusting estimates based on individual forecasting abilities
d. Creating historical databases of previous projects
False
If a project is internal to the company and relatively small, the bottom-up
approach to estimating time and costs for the project is the best choice.
Select one:
True
False
False
False
A _________ activity is one that has more than one activity taking place at the
same time.
Select one:
a. Burst
b. Merge
c. Dangling
d. Slack
e. Parallel
e. looping
False
In reality resource allocation generally occurs in a(n) ___________ environment
where the demands of one project have to be reconciled with the needs of
other projects.
Select one:
a. budget-constrained
b. risky
c. controlled
d. uncertain
e. multiproject
e. information.
e. equipment
In a resource-constrained project, the first, or primary, priority in assigning
resources is usually given to activities with the
Select one:
a. most slack.
b. least slack.
c. highest cost.
d. lowest identification number.
e. smallest duration.
This is used to compare the cost accounts between organizational units and
deliverables.
Select one:
a. Comparison Audit
b. Chart of Accounts
c. Earned Value
d. Project Schedule
False
High performing teams typically and often meet many of the characteristics
outlined in the text.
Select one:
True
False
Which of the following is NOT one of the tips for alleviating communication
problems of virtual teams?
Select one:
a. Share the pain when team members reside in different time zones.
b. Insist team members travel at least once during the project for a
face-to-face meeting.
c. Establish a code of conduct to avoid delays.
d. Establish clear norms and protocols for surfacing assumptions and
conflicts.
e. Keep team members informed on how well the overall project is going.
e. creative
During the delivery phase of a project's life cycle, the most significant source
of conflict is
Select one:
a. schedules.
b. costs.
c. priorities.
d. procedures.
e. technical.
Project managers are expected to ensure that appropriate trade-offs are
made between the time, cost, and __________ requirements of the project.
Select one:
a. quality
b. specifications
c. functional
d. performance
e. scope
This first chapter introduced some of the most rudimentary aspects of the
discipline, including definitions. A temporary endeavor undertaken to create
a unique product, service, or result is a(n) _________.
Select one:
a. All of these.
b. project
c. activity
d. undertaking
e. task
e. creative
At each gate a(n) _______ is made.
Select one:
a. assessment
b. evaluation
c. analysis
d. judgement
e. decision
______ change infrequently and may require revision only when the nature of
the business changes or shifts.
Select one:
a. Vision statements
b. Mission statements
c. Goals
d. Lessons learned
e. Objectives
One who endorses and lends political support for the completion of a specific
project is known as the
Select one:
a. Project lead.
b. Project manager.
c. Project sponsor.
d. Sacred cow.
e. CEO.
Multi-weighted scoring models include only quantitative criteria, not
qualitative.
Select one:
True
False
Which of the following is NOT one of the traditional components found in
mission statements?
Select one:
a. Target customers and markets
b. Major products and services
c. Profitability
d. Contribution to society
e. Geographic domain
Refining Estimates may be necessary for a number of reasons. For example,
a manager getting further into a project and obtaining a better
understanding of what needs to be done to accomplish a project and meet
the needs of the customer is an example of
Select one:
a. changes in project scope.
b. hidden interaction costs.
c. things going wrong on a project.
d. normal conditions not applying.
False