1. Site clearance General worker (earthworks)


1. Excavation
2. Compaction to floor slab surface and
sidewalk drain
3. Formwork to floor slab
4. Concrete to floor slab
5. Steel mesh to floor slab Steel fixer
6. Mortar screed to floor
7. Brickwork to meter chamber Bricklayer
8. 16mm dia. HDPE pipe Plumber
9. 20mm dia. g.m.s pipe
10. Stopcock
11. Water meter
12. Crushed stone
13. 600mm dia. concrete pipe
14. 25mm mortar screed to chamber roof
15. 80-100mm dia. treated gumpole
16. Metal strap fastener
17. 15mm dia. heavy duty brass bibtaps
18. C.I. manhole cover to meter box

Wednesday, 03 May 2017


1.70 Excavation
1.20
0.215
0.439 m3 to floor

0.40
0.40
0.40 0.064 m3 to meter chamber
0.503 m3 total

2/ 1.70 Concrete
0.1
0.15 0.051
m3 to floor nib

1.00
0.1
0.15 0.015 m3 to floor
0.066 m3 total

Mesh steel
1.60
1.00 1.60 m2

4/ 0.40 110mm brickwork to meter chamber


0.40 0.64
m2
0.40
0.40 0.16 m2 400

0.80 m2 total

400