5 year Forward Maintenance Plan of SRCPL unit

Date of 1st Synchrinisation : GTG on 07.02.2007 and STG on 01.08.2007


Cumulative Running Hours as on 17.02.2009 : GTG = 17,155R.Hr. & STG = 12,684 R.Hr.
History of Overhaul 5 year Forward Maintenance Plan
Year (FY) 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14
At GTG R.Hours 13130 24000 36000 48000 60000
At STG R.Hours 8721
No. of Days 5¾ days 15 days 5 days 7 days 25 days 5 days
From 26.08.2008 ….Jan.2010 ….Aug2011 ….Jan.2013
To 31.08.2008
Major
Combustion Off line water Insp.,LGB&AGB Off line water
Gas Turbine HGP Insp Comb.Insp.
Inspection wash inspection,MOT wash
GTG unit cleaning
Generator Generator Generator
***
Generator Inspection Inspection Inspection
Boiler & Steam
Boiler
Boiler Boiler Inspection Boiler Inspection Turbine Major
Inspection
inspection

STG unit Turb.Brgs. & G/B


Turb.Brgs. & G/B
Turbine *** Insp. MOT
Insp.
cleaning
Generator Generator Generator
Generator ***
Inspection Inspection Inspection
Major Auxilaries
Power Power
Transformers oil Transformers oil
filtration & testing filtration & testing
Five Year Forward Maintenance Plan for SRPCPL
OVERHAUL SCHEDULES

Date of 1st Synchrinisation : GTG on 07.02.2007 and STG on 01.08.2007

Cumulative Running Hours as on 17.02.2009 : GTG = 17,155R.Hr. &


STG:hours
Unit = 12,684 R.Hr.

Financial System / Planned Outages April May June July August September October November December January February March
Year (FY) Unit Vs. Actual in % 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Planned 48 144 30
GTG
Actual 1.60% 39 133 28
2008-09
P
STG
A
P 48 30 360
GTG
A
2009-10
P
STG
A
P 48 30 30
GTG
A
2010-11
P
STG
A
P 48 144 30
GTG
A
2011-12
P
STG
A
P 48 30 600
GTG
A
2012-13
P
STG
A
P 48 30 30
GTG
A
2013-14
P
STG
A
Days

11

19

11

19