16.10.

2019

Deputy Director General (Logistics),


Ministry of Health, Nutrition & Indigenous Medicine,
No 385, Rev. Baddegama Wimalawansa Thero Mawatha,
Colombo 10.

Dear Sir,

DESIGN AND CONSTRUCTION OF HEAD OFFICE BUILDING COMPLEX FOR


MINISTRY OF HEALTH

Reference: Requesting for Time Extension

The above construction has been carried out by CECB since 11 th November 2016 and the
construction period will be lapsed on 11 th of November 2019. Therefor we would like to draw
your attention for following reasons which will be able to grant the time extension

No of
No Reason
Days
Project delay due the badly delay in receiving mobilization advance
01 payment and interim payments. Detail of payments was annexed ( Refer the 630
Annexure 1)
Heavy rain was prevailed during the working days by hindering the daily
02 60
progress
Delay due to the working restriction by Devi Balika Vidyala during the O/L
03 and A/L examinations. Exam time table and informing letters are attached
(Refer the Annexure 2)
3.1 Advance Level Examination 2017 August 22

3.2 Ordinary Level Examination 2017 December 9

3.3 Advance Level Examination 2018 August 22

3.4 Ordinary Level Examination 2018 December 9

No of
No Reason
Days
3.5 Advance Level Examination 2019 August 22

04 Project delay due to the Easter Sunday Terrorist Attack 60

Delay occurred due to additional work of construction of storm water


05 drainage path (CMC drain line). Letter submitted to the ministry regarding 45
this matter was attached. (Refer the Annexure 3)
Delay occurred due to the interruption to movements, access and excavation
06 came across with parallel works of CMC drain line construction project by 30
Edward & Christie
Total Days 909

It is regretted to inform you that, still we are experiencing the delaying of interim payments
and it will be caused to further extending of project completion date.

Therefore, we shall be obliged if you grant time extension by 30 months duration and your
positive consideration would definite urge us to complete the construction to fulfill your
requirements.

Yours Faithfully,

CENTRAL ENGINEERING CONSULTANCY BUREAU

Eng. H.M.T.N. Dhanawaradane


Additional General Manager (EPC-WP2)
ANNEXURES
ANNEXURE 1
ANNEXURE 2
ANNEXURE 3