Dear Sir,
The above construction has been carried out by CECB since 11 th November 2016 and the
construction period will be lapsed on 11 th of November 2019. Therefor we would like to draw
your attention for following reasons which will be able to grant the time extension
No of
No Reason
Days
Project delay due the badly delay in receiving mobilization advance
01 payment and interim payments. Detail of payments was annexed ( Refer the 630
Annexure 1)
Heavy rain was prevailed during the working days by hindering the daily
02 60
progress
Delay due to the working restriction by Devi Balika Vidyala during the O/L
03 and A/L examinations. Exam time table and informing letters are attached
(Refer the Annexure 2)
3.1 Advance Level Examination 2017 August 22
No of
No Reason
Days
3.5 Advance Level Examination 2019 August 22
It is regretted to inform you that, still we are experiencing the delaying of interim payments
and it will be caused to further extending of project completion date.
Therefore, we shall be obliged if you grant time extension by 30 months duration and your
positive consideration would definite urge us to complete the construction to fulfill your
requirements.
Yours Faithfully,