PT SUMBAWA JUTARAYA INP-CIV-RPT-025 Juli 2023

Report No. Page.


PANGULIR GOLD DEVELOPMENT PROJECT 1001-123 -QAC-ITR-CTE- 0f

Subject: Verticality Checking Project No. 1001-000-PPM-POI-4103

Location :Emergecy Reclaim Feed Bin(123) Equipment Type :Column of Building

Ref.Drawing :- Discipline :Steel Structure

TOLERANCE
CODE DESIGN COORDINATE
ACTUAL COORDINATE TOP DEVIATION ≤H/500 Taken RESULT
NAME BOTTOM HIGH
≤25mm smaller REMARKS
(mm)
E N E N
E N E N E N
(mm) (mm) (mm) (mm)
1A 559393.093 9009010.624 559393.100 9009010.627 5200 +7 +3 10 10 OK OK
2A 559393.093 9009004.474 559393.095 9009004.475 5200 +2 +1 10 10 OK OK
1B 559397.493 9009010.624 559397.501 9009010.626 5200 +8 +2 10 10 OK OK
2B 559397.493 9009004.474 559397.492 9009004.471 5200 -1 -3 10 10 OK OK

NOTE=R(Repair) dilakukan jika nilai verticality melewati batas toleransi.

Prepared by Checked by Approved by


PT KONKA NEW BUILDING
PT. CITEC ENGINEERING PMC SJR
MATERIALS INDONESIA
NAME

SIGNATURE

DATE
PT SUMBAWA JUTARAYA Date.
INP-SRV-RPT-023 Juli 2023

PANGULIR GOLD Report No. Page.


1001-123-QAC-
DEVELOPMENT PROJECT ITR-CTE- of
Subject : Elevation Check (TOP Beam) Project No. 1001-000-PPM-POI-4103

Location :Emergency Reclaim Feed Bin(123-6) Equipment Type :TOP Beam of Building

Ref.Drawing :- Discipline :Steel Structure

DESAIGN ACTUAL DEVIASI


COLOUMN ELEVATION ELEVATION (mm) SKETCH
(mm) (mm)
1A-1B +5500 +5503 +3
1A-2A +5500 +5505 +5
1B-2B +5500 +5502 +2
2A-2B +5500 +5506 +6

Prepared by Checked by Approved by


PT KONKA NEW BUILDING
PT. CITEC ENGINEERING PMC SJR
MATERIALS INDONESIA
NAME

SIGNATURE

DATE