Request For Inspection

Date: 27 Aug.2023
Request no. RFI-CSCEC-D01-ME-ML-0103-00
Project No. & Title: E21110-0100S - Alamein Downtown Towers

Employer: Engineer: Contractor:

We request your attendance to inspect the following works :


1. Type : PLUMBING (water supply ) Electrical ✘ Mechanical installations
2. Inspection Time : 10:00 AM Date :28/Aug/2023
3. Location: Zone Road Stations Structure Other
D01 1 Raft
4. Inspection : First Second Third

5. Purpose of Inspection :
1. Electrical 2. Mechanical
Setting out Light fittings ✘ Mechanical installations
Furniture elect. culvert Sub-stations Pumping stations
MV cables Civil works & finishings Civil works & finishings
Street lighting cables
Street lighting poles
Telephone duct Bank
TV cables

Others (specify) Testing of PPR water supply system )

Particular Details PPR pipes of water supply at 4th floor at zone1 exclude the (main valves ,water meter and relief valves ) as following drawing :

(SHD-CSCEC-D01-ME-PL-01-04-00-0001-0000-04)

Submitted by : Ali Elkahlawy Signature:

6. Inspection report : Signature

Surveyor
Elect. Eng.
Mech. Eng.
Civil Eng.

Date/time of inspection :

7. Engineer's Representative Comments:

The works are : Approved Approved as Noted Rejected

Signature Date :