S.

NO ACTIVITY PAYMENT WEEK1 WEEK2 WEEK3 WEEK4 WEEK5 WEEK6 WEEK7 WEEK8 WEEK9 WEEK10 WEEK11 WEEK12 WEEK13 WEEK14 WEEK15 WEEK16 WEEK17 WEEK18 WEEK19 WEEK20 WEEK21

1 Excavation of 6Pits Advance - 5L

2 PCC

3 Placing Mat & Column

4 Mat Concrete

5 Column Concrete upto plinth level

6 Excavation of remaining 6Pits

7 PCC for remaining 6Pits

8 Placing Mat & Column of remaining 6Pits

9 Mat Concrete of remaining 6Pits

10 Column Concrete upto plinth level Payment - 6L

11 Morrum filling

12 Plinth Bar bending & Concrete

13 Column and StairCase Barbending and Concrete

14 Slab Bar bending and Concrete

15 Curing , Deshuttering & Chipping

16 Brick Work payment - 5L

17 Electrical and Plumbing work

18 Plastering

19 Electrical and Plumbing work Payment - 4.5L

20 Windows and Doors work

21 Flooring work

22 painting work

23 finishing works remaining Balance - 50K