RN GLASS/BUILDERS

DATE: AUGUST 15,2023


LOCATION: GAISANO GRAND SILAY
TRHU: ENGR. VINCENNT SEDURIFA

SCOPE OF WORKS:

1. WATER PROOFING & REPAIR IF FLOOR DRAINS SECOND FLOOR AHU RM


AREA. (47 SQ.M. x ₱850.00 = ₱31,365.00)

2. CEILING REPAIR & PAINTING WORKS MEAT PREP. GROUND FLOOR


SUPERMARKET AREA. (69.7 SQ.M. x ₱450.00 = ₱31,365.00)

3. GYPSUM CEILING REPAIR & PAINTING WORKS HALLWAY GROUND FLOOR


MALL AREA. (50 SQM. X ₱450.00 = ₱22,500.00)

4. GRANITE TILES INSTALLATION (WALL)


FRESH AREA – 24 SQ.M x ₱550.00 = ₱13,000.00
CR (FEMALE) – 22 SQ.M x ₱550.00 = ₱12,100.00

TOTAL PROJECT COST: ₱119,115.00