Professional Documents
Culture Documents
Quantitative Chapter 6 - Time and Work
Quantitative Chapter 6 - Time and Work
ii) If there is more than one person (or members of 6.02. Fifteen men take 20 days to complete a job working
"workforce") carrying out the work, it is assumed that 8 hours a day. How many hours a day should
each person (or members of the workforce), unless 20 men work to complete the job in 12 days?
otherwise specified, does the same amount of work
each day. This means they share the work equally. Sol: Since 15 men take 20 days at 8 hours per day,
the total man hours required for the job is
If two people together can do the work in 8 days it means 15 × 20 × 8 = 2400. If 20 men are working on the
that one man can do it in 16 days. This, in turn means, same job, the number of man hours required for
each person can do 1/16th of the work per day. the job will still be the same. Hence the number
of hours they should work per day is 2400 /
If a man works three times as fast as a boy does, the man (20) (12) = 10.
takes one-third of the time the boy takes to complete the Therefore, 20 men can complete the work in
work. If the boy takes 12 days to complete the work, then 12 days working 10 hours per day.
the man takes 4 days to complete the work.
Hence, in general we can say that
This method is known as "UNITARY METHOD", i.e., the
time taken per "Unit Work" or number of persons required
to complete "Unit Work" or work completed by "Unit Person" If M1 men can do W1 work in D1 days working
in "Unit Time", etc., is what is first calculated. H1 hours per day and M2 men can do W2 work
in D2 days working H2 hours per day (where
We should recollect the fundamentals on variation (direct all men work at the same rate), then
and inverse) here. M1 D1 H1 M D H
- Time remaining constant, Work and Men are directly = 2 2 2
W1 W2
proportional to each other, i.e., if the work increases
the number of men required to complete the work in
the same number of days increases proportionately 6.03. A piece of work can be done by 24 men in
and vice-versa. 4 days working 10 hours a day. How many men
are needed to complete another work which is
- Work remaining constant, Men and Days are
twice as large as the first one in 48 days working
inversely proportional, i.e., if the number of men
8 hours a day?
increases, the number of days required to complete
the same work decreases in inverse proportion and Sol: The problem can be solved by using the man
vice-versa. days concept as shown in 6.02 example, or using
- The number of workingmen remaining constant, the following formula.
Work and Days are directly proportional i.e., if the M1D1H1 M2 D2 H2
=
work increases, the number of days required to W1 W2
complete the work with the same number of working Here W 1 = 1 and W 2 = 2, M1 = 24, H1 = 10, D1 = 4
men also proportionately increases and vice-versa. H2 = 8, and D2 = 48
The concept of MANDAYS is very important and useful 24 × 10 × 4 M2 × 48 × 8
here. The number of men multiplied by the number of days = ⇒ M2 = 5.
1 2
that they take to complete the work will give the number
Triumphant Institute of Management Education Pvt. Ltd. (T.I.M.E.) HO: 95B, 2nd Floor, Siddamsetty Complex, Secunderabad – 500 003.
Tel : 040–40088400 Fax : 040–27847334 email : info@time4education.com website : www.time4education.com SM1002106/66
If two persons A and B can individually do some work in p 6.07. A and B together can do a piece of work in
and q days respectively, we can find out how much work 36 days, B and C can do it in 48 days and A and
can be done by them together in one day. Since A can do C can do it in 72 days. How long would each take
1/pth part of the work in one day and B can do 1/qth part of to do the work?
the work in one day, the two of them together do (1/p +
1/q)th part of the work in one day. Sol: Work done by A and B together in one day
From this we can find out the number of days that they = 1/36th ------ (1)
take to complete the work. Work done by B and C together in one day
= 1/48th ------ (2)
Work done by A and C together in one day
If A can do a piece of work in p days and B can do it
= 1/72th ------ (3)
in q days then A and B together can complete the
Adding (1) + (2) + (3), we get 2 (A + B + C)'s
pq 1 days work
same work in days.
p+q 1 1 1 9 1
= + + = =
36 48 72 144 16
A, B and C together can finish, in 1 day,
6.04. A can do a piece of work in 10 days. B can do the
1
ቀ ቁ = th part of the work.
1 1
same work in 15 days. In how many days can the
work be completed if A and B work together? 2 16 32
Work done by A in 1 day
Sol: As A can do the work in 10 days in one day he 1 1 1
= − = .
can complete 1/10th of the work. Similarly work 32 48 96
done by B in one day Therefore, A alone can do it in 96 days.
= 1/15th. Work done by B in 1 day
∴The work done by A and B in one day 1 1 5
= − = .
1 1 1 32 72 288
= + =
10 15 6 Therefore B alone can do it in 288/5 i.e., 573/5
∴ They can complete it in 6 days. days.
Alternately, using the formula, Work done by C in 1 day
A and B together can do the work in 1 1 1
= − = .
10 × 15 150 32 36 288
= = 6 days.
10 + 15 25 Therefore, C alone can do it in 288 days.
6.05. A and B together can do a piece of work in 24 6.08. A and B can do a work in 18 days. B and C can
days and A alone can complete the work in 36 do it in 24 days and A and C can do it in 36 days.
days. How long will B alone take to complete the They all work together for 4 days and then A left.
work? In how many more days can B and C finish the
remaining work?
Sol: In a day, A and B together can do 1/24th part of
the work. In a day, A alone can do 1/36th part of Sol: By using a procedure similar to previous
the work. In a day, work done by B alone is example, we get 2 (A + B + C)’s 1 day’s work
(work done by A and B) – (work done by A) 1 1 1 9 1
1 1 1 = + + = = . A, B and C can finish
i.e. − = . 18 24 36 72 8
24 36 72 the work in 16 days. Work done by A, B and C in
Therefore, B alone can complete the work in 4 days
72 days. = 4 × 1/16 = 1/4th.
∴Work remaining = 1 – 1/4 = 3/4
6.06. Girish and Harish can complete a job in B and C can finish the remaining work in
24 days working together. Girish alone can 3/4 × 24 = 18 more days.
complete it in 32 days. Both of them worked
together for 8 days and then Girish left. How long 6.09. A can do a work in 18 days. When he had worked
will Harish take to complete the remaining work? for 2 days, B joined him. If both A and B complete
the remaining work in 4 more days, in how many
Sol: Work done in one day by both together days can B alone finish the whole work?
= 1/24th
∴ Work done by them in 8 days Sol: Work done by A in one day = 1/18th.
= (8) × (1/24) = 1/3rd Number of days A worked = 2 + 4 = 6.
1 2 Therefore, total work done by A
Remaining work = 1 − = .
3 3 = 6 × 1/18
Work done by Harish in 1 day = 1/3rd.
1 1 1 The remaining two-thirds, of the total work is
= − = . done by B in 4 days.
24 32 96
Therefore, B takes 4 × 3/2 = 6 days to finish the
Since only two-thirds work is left, Harish will do
whole work.
the remaining work in (2/3) × 96 = 64 days.
Triumphant Institute of Management Education Pvt. Ltd. (T.I.M.E.) HO: 95B, 2nd Floor, Siddamsetty Complex, Secunderabad – 500 003.
Tel : 040–40088400 Fax : 040–27847334 email : info@time4education.com website : www.time4education.com SM1002106/67
6.10. A and B together can do a piece of work in ⇒ 1m = 5w/3
16 days. B and C together can do the same work Now 5m + 3w = 5(5w/3) + 3w
in 32 days. After A worked for 4 days, 25 w 9 w 34 w
B for 12 days, C takes up the work and finishes = + =
3 3 3
it alone in 48 days. In how many days will each If 5 women can do the work in 68 days, (34/3)
of them complete the work? women can finish it in 5 × 68 × (3/34) = 30 days.
Sol: Work done by A and B in 1 day = 1/16th 6.13. If 15 boys and 20 men take 4 days to do a piece
Work done by B and C in 1 day = 1/32nd of work and 12 boys and 13 men take 6 days to
A worked for 4 days, B worked for 12 days and C do the same work, find the time taken by 2 men
worked for 48 days to complete the work. and 8 boys to complete the same work.
Denoting work done by A, B and C in one day as
a, b and c, we have 4a + 12b + 48c = 1 Sol: Given 15 boys + 20 men can do the work in 4
⇒ 4a + 4b + 8b + 8c + 40c = 1 days and 12 boys + 13 men can do the same
1 1 work in 6 days. Let m and b be the works done by
4 + 8 + 40c = 1
16 32 a man and a boy in one day respectively. As the
persons in both the cases are doing the same
1 1 1 1
+ + 40c = 1 ; 40c = ⇒ c = . work, number of mandays will be same.
4 4 2 80
Therefore, 4(15b + 20m) = 6(12b + 13m)
C takes 80 days to finish the work.
⇒ m = 6b. Hence [15b + 20m] is equal to [15b +
1 1 3
B’s 1 day work = − = 120b] i.e. 135b.
32 80 160 Time taken by 2 men and 8 boys i.e.
Hence B takes 160/3 i.e., 531/3 days to finish the 12b + 8b = 20b, to complete the work
work. = (135 × 4) / 20 = 27 days.
1 3 7
A’s 1 day work = − = .
16 160 160 6.14. A certain number of men can do a work in
6
Hence A takes 160/7 i.e., 22 /7 days to finish the 24 days. If there were 3 more men, the work can
work. be done in 6 days less. How many men were
there?
6.11. To do a certain work, C alone takes thrice as long
as A and B together. A alone would take twice as Sol: Let the initial number of men be P. Number of
long as B and C together. All three together days is 24. So number of man days is 24 P. If
complete the work in 3 days. How long would there are 3 more men i.e., P + 3 men, it is
each take separately? completed in 24 – 6 = 18 days. So 24P = (P + 3)
18
Sol: As C takes thrice as long as A and B together, ⇒ P = 9. Therefore, there were 9 men.
(A + B)’s one day work = 3 times of C’s one day
work. 6.15. X is 4 times as fast as Y and is able to complete
Adding 1 time C’s one-day work to both sides, the work in 90 days less than Y. Find the time in
4 times C’s one day work which they can complete the work working
= (A + B + C)’s one day work i.e. 1/3rd. together.
Hence C’s one day work = 1/12th.
As A takes twice as long as B and C together, Sol: As X is 4 times as fast as Y, if Y does the work in
(B + C)’s one day work = 2 times of A’s one day 4 days, X does it in 1 day i.e. the difference is 3
work. Adding 1 time A’s one day work to both days.
sides, 3 times A’s one day work If the difference is 3 days, X takes 1 day and Y
= (A + B + C)’s 1 day work i.e. 1/3rd. takes 4 days. If the difference is 90 days (i.e.
A’s one day work = 1/9th. 30 times), X takes 30 days and Y takes 120 days.
B’s one day work Let time taken by them working together to
1 1 1 12 − 3 − 4 5 complete the work is t days (say).
= − + = = .
3 12 9 36 36 ଵ 1 1 5 1
= + = =
Hence A alone takes 9 days to complete the ୲ 30 120 120 24
work, B alone takes 36/5 i.e., 71/5 days to t = 24
complete the work and C alone takes 12 days to
complete the work. 6.16. Savita, can finish a work in 48 days working
9 hours a day. Rani can finish the same work in
6.12. Three men or five women can construct a wall in 36 days working 16 hours a day. In how many
68 days. How long will it take for 5 men and days can they finish it working together for
3 women to complete the same work? 75/7 hours a day?
Triumphant Institute of Management Education Pvt. Ltd. (T.I.M.E.) HO: 95B, 2nd Floor, Siddamsetty Complex, Secunderabad – 500 003.
Tel : 040–40088400 Fax : 040–27847334 email : info@time4education.com website : www.time4education.com SM1002106/68
Number of hours taken by Rani 8 / 15
= 36 × 16 = 576. = = 5 days. Hence, B left after 5 days from
8 / 75
Together they will do, ( 432 + 576 ) the start of work.
( 432 )( 576 )
7 6.19. A contractor decided to complete a work in
= th work in 1 hour.
1728 60 days and employed 60 men at the beginning
Hence they will take (1728/7) hours i.e. working and 30 men additionally after 20 days and got the
1 hour a day, (1728/7) days. Therefore, working work completed as per schedule. If he had not
75/7 hours a day they can complete the work in employed the additional men, how many extra
1728 7 days would he have needed to complete the
× = 32 days. work?
7 54
Triumphant Institute of Management Education Pvt. Ltd. (T.I.M.E.) HO: 95B, 2nd Floor, Siddamsetty Complex, Secunderabad – 500 003.
Tel : 040–40088400 Fax : 040–27847334 email : info@time4education.com website : www.time4education.com SM1002106/69
Time taken by A to finish 1/15th part of the work 1 1 1
= (1/15) / (1/12) = 4/5 days. = : : = 2 : 3 : 4.
6 4 3
So, total time taken to complete the work is 144/5
Hence C’s share = (4/9) (540) = `240.
days.
6.25. A, B and C contract a work for `7,500. A and B
6.23. A and B working separately complete a work in 8 together complete 2/5th of the work and then C
days and 12 days respectively. They work on takes over and finishes the work. What is the
alternate days A works on the first day. In how amount received by C?
many days will the work be completed?
Sol: Work done by C alone = 1 − (2/5) = 3/5.
Sol: In a period of 2 days, work done by A and B Therefore, C’s share = (3/5) (7500)
1 1 5 = `4,500.
= + = .
8 12 24
In 4 such time periods of 2 days i.e. 8 days. (we are 6.26. Wages for 80 women for 60 days are `43,200.
considering 4 periods because in the fraction How many men must work for 40 days to earn
5/24 the numerator 5 goes 4 times in the `57,600, if the daily wages for a man is four times
denominator 24), work done is 20/24th. that of a woman?
20 4 1
Remaining work = 1 − = = . 43,200
24 24 6 Sol: Daily Wages of a woman = = `9.
Now it is A’s turn, since 4 whole number of 80 × 60
periods are over. Daily Wages of a man = 4 × 9 = `36.
But A can do only 1/8th part of the work in a day. 57,600
So the remaining work after A works for 1 day Therefore, number of men = = 40 .
36 × 40
1 1 1
= − = .
6 8 24 6.27. A, B and C together can earn `3,240 in
Now it is B’s turn to do 1/24th part of the work; and 18 days. A and C can earn `1,200 in 10 days
he takes (1/24) / (1/12) = (1/2) a day. whereas B and C can earn `1,820 in 14 days.
Total number of days taken Find the daily earnings of C.
= (4 × 2) + 1 + 1/2 = 91/2 days.
Sol: Daily Wages of (A + B + C)
When people work together and earn money for the work, = 3240/18 = 180 ----- (1)
the money has to be shared by all the people doing the Daily Wages of (A + C)
work. = 1200/10 = 120 ------ (2)
Daily Wages of (B + C)
Wages
= 1820/14 = 130 ------ (3)
In general, money earned should be shared by people (2) + (3) − (1), leads to:
doing the work together in the ratio of the SHARE OF (A + C) + (B + C) − (A + B + C)
WORK done by each of them. = 120 + 130 – 180 ⇒ C = 70
For example, if A does 2/5th of the work, then he should 6.28. Two men undertake a work for `480. They can
get 2/5th of the total earnings for the work. If the remaining do the work individually in 24 days and 40 days.
3/5th of the work is done by B and C in the ratio of 1 : 2, If they complete the work in 10 days with the help
of a boy, how should they divide the total amount
then the remaining 3/5th of the earnings (after paying A)
paid to them?
should be shared by B and C in the ratio of 1 : 2. Suppose
`500 is paid to A, B and C together for doing the work, Sol: The 1st man can do 1/24th of the work in 1 day
then A will get `200 (which is 2/5 of `500), B will get `100 and since he works for 10 days, he does
and C, `200 (because the remaining `300 after paying A (10) (1/24) = 5/12th of the work. So he should get
is to be divided in the ratio 1 : 2 between B and C). (5/12) (480) = `200
The 2nd man can do 1/40th part of the work in
When people work for the same number of days each, 1 day and since he works for 10 days, he does
then the ratio of the total work done will be the same as (10) (1/40) = 1/4th of the work. So he should get
the work done by each of them PER DAY. Hence, if all the (1/4) (480) = `120.
people involved work for the same number of days, then Since the two men earned a total of `200 + `120
the earnings can directly be divided in the ratio of work = `320, the balance of `480 − `320 = `160 will
done per day by each of them. be paid to the boy.
Sol: Part of the tank filled by A in 1 minute = 1/30th. Part Sol: B works for 36 minutes. In 1 min, B fills 1/60th part
of the tank filled by B in 1 minute = 1/45th. Part of the of the tank i.e. in 36 minutes, it fills 36(1/60)
tank filled by both A and B in one minute = 3/5. The remaining 2/5th is filled by A. Since A
1 1 1 fills the tank fully in 40 minutes, it takes (2/5) × 40
= + = .
30 45 18 = 16 minutes to fill 2/5th part of the tank. So A
The tank can be filled in 18 minutes. should be closed after 16 minutes.
6.30. Pipe A can fill an empty tank in 24 minutes, pipe 6.33. Three taps A, B and C together can fill an empty
B in 36 minutes and pipe C can empty a full tank tank in 4 hours. A, B and C are opened
in 72 minutes. If all of them work together, find simultaneously. After 1 hour, C is closed and the
the time taken to fill the tank. tank is filled in 6 more hours. Find the time in
which C alone can fill the tank.
Sol: Work done by the pipes A, B and C together in 1
1 1 1 1 Sol: Work done by A, B and C in 1 hour = 1/4th.
minute = + − = . Remaining part of the tank = 1 − (1/4) = 3/4
24 36 72 18 Time taken by (A and B) to fill this 3/4th part of the
So, the empty tank can be filled in 18 minutes. tank = 6 hours.
⇒ A and B together fill the tank in 6/(3/4)
6.31. Two pipes can fill an empty tank in 40 minutes 8 hours. Now, we know A, B and C take 4 hours
and 60 minutes respectively. There is an outlet and A and B take 8 hours.
pipe C. If all the 3 pipes are opened Part of the tank filled by C in 1 hour
simultaneously, the empty tank can be filled in 48
1 1 1
minutes. How much time will it take for C alone = − = .
to empty the full tank? 4 8 8
So, C alone can fill the tank in 8 hours.
Triumphant Institute of Management Education Pvt. Ltd. (T.I.M.E.) HO: 95B, 2nd Floor, Siddamsetty Complex, Secunderabad – 500 003.
Tel : 040–40088400 Fax : 040–27847334 email : info@time4education.com website : www.time4education.com SM1002106/71
Concept Review Questions
Directions for questions 1 to 20: For the Multiple Choice Questions, select the correct alternative from the given choices.
For the Non-Multiple Choice Questions, write your answer in the box provided.
1. If 30 men can do a job in 30 days, find the part of the 12. X and Y can complete a job in 15 days working
job that can be completed by 1 man in 1 day. together. Y and Z can complete the job in 20 days
1 1 working together. X and Z can complete the job in 30
(A) (B) days working together. Who is the slowest of the 3
30 90
workers?
1 (A) X (B) Y
(C) (D) None of these
900 (C) Z (D) Cannot be determined
2. If a man completes a job in 6 days working 6 hours a 13. 9 men can complete a job in 20 days. If a woman
day, in how many days can he complete the job works at one-third the rate of a man, in how many
working 9 hours a day? days can 15 women complete the job?
1. P and Q can complete a job in 12 days working 9. A certain quantity of work can be completed by A, B
together. If P alone can complete it in 20 days, in how and C in 20, 15 and 30 days respectively and an
many days can Q alone complete it? amount of `4000 is paid for that work. Another
(A) 32 (B) 24 (C) 20 (D) 30 quantity of work can be completed by A, B and C in
15, 25, 10 days respectively and an amount of
2. A can do a piece of work in 24 days and B in `10,000 is paid for this work. If both the works are
48 days. B joins A after A had worked alone for completed by A, B and C together, who got the
6 days. In how many more days would the work get minimum amount of the three?
completed? (A) A (B) B
(C) C (D) Cannot be determined
10. Mahesh, Suresh and Naresh together can complete a
3. Rajesh and Rakesh working alone can complete a work in 4 days. The wages paid to Mahesh, Suresh
piece of work in 12 and 24 days respectively, Rajesh and Naresh for completing the work are `6300, `7350
started the work and after a few days Rakesh joined and `8400 respectively. Find the number of days in
him and the work was completed in 10 days. After which Naresh alone can complete the work.
how many days did Rakesh join Rajesh?
Triumphant Institute of Management Education Pvt. Ltd. (T.I.M.E.) HO: 95B, 2nd Floor, Siddamsetty Complex, Secunderabad – 500 003.
Tel : 040–40088400 Fax : 040–27847334 email : info@time4education.com website : www.time4education.com SM1002106/74
Exercise – 6(b)
Directions for questions 1 to 40: For the Multiple Choice Questions, select the correct alternative from the given choices.
For the Non-Multiple Choice Questions, write your answer in the box provided.
1. If x men can produce p units in k days working 10. 20 men can finish a piece of work in 30 days. After
h hours a day, then how many men can produce how many days should 5 men leave the work so that
m units in h days working k hours a day? it is finished in 35 days?
(A) m p/x (B) mpx
(C) mx/p (D) mx
2. 30 men working 7 hours per day can do a piece of 11. A group of 25 workers are assigned a task of
work in 18 days. In how many days can 21 men 330 units. Each worker can do 1 unit / day. They start
working 8 hours a day do the same piece of work? the task. After every day one more worker joins the
(A) 223/5 (B) 222/5 group. The task is completed in x days. Find x.
(C) 221/2 (D) None of these (A) 10 (B) 9 (C) 11 (D) 12
3. A tap can fill a tank in 3 hours and another tap can 12. A and B together completed a job in 9 days. Had A
empty it in 4 hours. When the tank is empty and both worked at half his speed and B worked at twice his
taps are opened simultaneously, how long will it take speed, it would have taken 6 days to complete the
to fill the tank (in hours)? job. How much time would it take for B to do the job?
27 27
(A) days (B) days
4 5
4. Two pipes A and B can fill a tank in 10 minutes and 27
(C) days (D) 27 days
20 minutes respectively. If both pipes are opened 2
simultaneously, after how many minutes should
B be closed so that the tank is full in 8 minutes? 13. Hari can finish a work in 18 days working 6 hours a
day. Raghu can finish the same work in 12 days
working for 3 hours a day. In how many days can they
finish it working together 21/2hours a day?
5. A and B can do a piece of work in 12 days, B and C
can do it in 15 days, C and A can do it in 20 days.
They all work together for 4 days and then C leaves.
In how many days can A and B finish the remaining 14. P can complete a piece of work in 24 days.
work? P worked for 4 days and then Q joined him. The two
(A) 36/7 (B) 18/4 (C) 36/5 (D) 36/3 persons worked for 4 more days and then R took over
from them. R finished the remaining 1/3rd of the work
6. A and B can do a piece of work in 15 days and in 22/3 days. In how many days can Q alone complete
20 days respectively. They worked on alternate days the work?
with A starting the work. In how many days will the
work be completed?
8. A man, a woman and a boy can do a piece of work in 17. Sanjay can do in 16 hours as much work as Vijay can
3, 4 and 12 days respectively. How many boys must do in 24 hours. Ajay can do the same work in
assist one man and one woman to complete the work 32 hours. If the three of them work together, they can
in one and a half days? complete a certain work in 24 hours. In how many
(A) 12 (B) 6 hours can Ajay alone complete the work?
(C) 1 (D) 3
Triumphant Institute of Management Education Pvt. Ltd. (T.I.M.E.) HO: 95B, 2nd Floor, Siddamsetty Complex, Secunderabad – 500 003.
Tel : 040–40088400 Fax : 040–27847334 email : info@time4education.com website : www.time4education.com SM1002106/75
19. There is a group of persons each of whom can 28. A, B and C working individually can complete a piece
complete a piece of work in 16 days, when they are of work in 16, 18 and 20 days respectively.
working individually. On the first day one person If they worked together and earned `1089 for the
works, on the second day another person joins him, work, then what is the share of B (in `)?
on the third day one more person joins them and this
process continues till the work is completed. In how
many days would the work get completed?
(A) 3¼ (B) 4 1/3 (C) 51/6 (D) 61/5 29. A, B and C, working individually can complete a piece
of work in 10, 15 and 20 days respectively. They
20. 3 men and 5 women can complete a work in completed the work in 4 days with the help of D. If
12 days, which 5 men and 12 women can complete they earned `3750 for the entire work, how much did
in 6 days. In how many days can 4 men and D earn for his work (in `)?
4 women complete the same work?
23. A can eat 3 apples in 5 days while B can eat 32. Pipes P and Q can fill a tank in 20 minutes and
6 apples in 4 days. In how many days can the 25 minutes respectively. Both were opened
two persons consume 21 apples? simultaneously. After 4 minutes, P was closed. Find the
time taken from then to fill the tank (in minutes).
26. Four persons A, B, C and D produced 256 pieces of 35. Pipe A can fill a tank in 12 hours and pipe B can empty
item P in 8 hours. B is twice as efficient as A. D is the tank in 18 hours. Both pipes are opened at 6 am
25% less efficient than A but is three times as efficient and after some time B is closed, and the tank is full at
as C. How many pieces of P did B produce? 8 pm on the same day. At what time was B closed?
(A) 128 (B) 64 (C) 48 (D) 16 (A) 10 am (B) 8 am
(C) 9 am (D) 11 am
27. Ram, Shyam and Tarun can complete a job in
4 days, 8 days and 16 days respectively. They start 36. Three taps A, B and C together can fill a tank in
the work and Ram leaves after a day. The other two 6 hours. All the taps are opened simultaneously. After
complete the job. Tarun got `24000 out of the total 2 hours C was closed and the tank was filled in 8
`90000 paid to the three. As Ram was unwell on the more hours. Find the time (in hours) in which C can
first day, he could not work at his usual capacity. Find fill the tank.
the percentage of his usual capacity at which he
worked on the first day.
(A) 60% (B) 75% (C) 80% (D) 90%
Triumphant Institute of Management Education Pvt. Ltd. (T.I.M.E.) HO: 95B, 2nd Floor, Siddamsetty Complex, Secunderabad – 500 003.
Tel : 040–40088400 Fax : 040–27847334 email : info@time4education.com website : www.time4education.com SM1002106/76
37. Pipes A and B can fill a tank in 20 minutes and 43. 10 soldier ants take 6 hours to build an anthill. How
30 minutes respectively and C can empty it in long does it take for 5 queen ants to build the anthill?
15 minutes. A is opened for a minute and then closed. Ι. A queen ant works at half the working rate of a
B is then opened for a minute and then closed. C is soldier ant.
then opened for a minute and then closed. This ΙΙ. 5 soldier ants and 5 queen ants together take 7½
process is repeated until the tank is filled. Find the hours to build the ant hills.
time taken to fill the tank (in minutes).
(A) 169 (B) 170 (C) 167 (D) 166 44. How long did Tarun work to construct the wall?
38. A is 80% more efficient than B who is 60% more Ι. Piyush, Rohan, Saurabh and Tarun can
efficient than C. A takes 40 days less than B to individually construct the wall in 10, 15, 20 and
complete a work. A starts the work and works for 30 days respectively.
25 days and then B takes over. B then works for the ΙΙ. Initially Piyush started the work. After three days,
next 30 days and then C takes over. In how much Rohan and Saurabh joined him and the three
more time can C complete the remaining work? together worked for two days, then Tarun joined
(A) 20 days (B) 24 days them and all of them worked until the wall is
(C) 32 days (D) 40 days constructed.
39. A piece of work can be completed by A and B in
10 days, B and C in 12 days and C and A in 45. Who among Arun, Bhargav and Chadda is the most
15 days. A, B and C started working together and efficient?
then B left after 4 days. C left 3 days after that and Ι. To complete a work, Chadda takes 5 times as
then immediately B joined A again to complete the much time as Arun and Bhargav take working
remaining work. In how many days was the work together.
completed? ΙΙ. To complete a work Arun takes as much time as
Bhargav and Chadda take working together.
1. C 7. C 14. B
2. 4 8. D 15. 3000
3. (i) A 9. 12 16. C
(ii) 16 10. C 17. A
4. B 11. 10 18. A
5. B 12. C 19. 24
6. 50 13. 36 20. D
Exercise – 6(a)
Exercise – 6(b)
Triumphant Institute of Management Education Pvt. Ltd. (T.I.M.E.) HO: 95B, 2nd Floor, Siddamsetty Complex, Secunderabad – 500 003.
Tel : 040–40088400 Fax : 040–27847334 email : info@time4education.com website : www.time4education.com SM1002106/78