You are on page 1of 1

MUSIKOT MUNICIPALITY

Office of the Municipal Executive


Technical Branch, Wamitaksar, Gulmi.
Lumbini Province, Nepal.
Labour & Material Quantity
Name of Project: Goretobato Marmat Yojana
( Loresimal - Gedbas, Aaparukha, Thapatola-Khelmaidan, Gurjang ) F/Y: 2079-2080
Site Location: Musikot Municipality -
SN Item Name & Description Unit Quantity Rate Amount Remarks

A LABOUR 138,555.00
1 LABOUR ( कामदार )
1.1 Skilled Labour ( द िम ी ) M.D/ िदन 12.00 1,000.00 12,000.00
1.2 Unskilled Labour (अद िम ी ) M.D/ िदन 146.00 715.00 104,390.00
Total Amount 116,390.00

1 COMMUNITY CONTRIBUTUION (जन मदान )


2.1 Unskilled Labour (अद िम ी ) M.D/ िदन 31.00 715.00 22,165.00
Total Amount 22,165.00

B QUANTITY OF MATERIALS
1 Materials
1.1 Cement ( िसमे ट ) Bag/ बैग 25.00 - -
1.3 Sand ( बालवु ा) Cu.m / घ. िम 2.00 - -
1.4 Aggregates ( िग ी ) Cu.m / घ. िम 4.00 - -

Estimtate Amount 161,796.08


Valuation Amount 165,078.72

Prepared By Checked By Approved By