PT.

Multi Ocean Shipyard


DAILY REPORT
Project Name PRIMA NUSANTARA X
Date 15 Agustus 2023
Department / Team Piping

A. RENCANA KERJA
1 Piping hydraulic system plough (Hydraulic) 20/08/23
2 Piping hydraulic system CDE 14/08/23 – 20/08/23
3 Piping hydraulic system DOHB 14/08/23 – 20/08/23
4 Piping hydraulic system plough umbilical winch 20/08/23

B. PELAKSANAAN

ITEM START (item sudah mulai kerja - continue)

NO ITEM PICTURE REMARKS


1 Piping hydraulic system plough Welding & grending
(Hydraulic) support & pipe system
plough area di main deck
(buritan).

2 Piping hydraulic system CDE Prepare press test


hydraulic line loose CDE
ke HPU.

3 Piping hydraulic system DOHB Prepare press test


hydraulic line return,
drain & boost.
PT. Multi Ocean Shipyard
4 Piping hydraulic system plough Welding penetrasi
umbilical winch system plough umbilical
winch di main deck

ITEM BELUM START (item belum mulai kerja sesuai Plan Start)

NO ITEM PICTURE REMARKS


1 Piping Hydroulic System A Frame Belum tersedia
manpower.

2 Piping Hydroulic System LCE Belum tersedia


(Linear Cable Engine) manpower.

3 Piping Hydroulic System Rov A Frame Belum tersedia


manpower.

4 Piping Hydroulic System HPU Belum tersedia


(Hydraulic Power Unit) Container manpower.

5 Piping Hydroulic System Hyd Power Belum tersedia


Station manpower.

6 Piping Hydroulic System HPU Belum tersedia


(Rov A Frame) manpower.
PT. Multi Ocean Shipyard

ITEM DELAY (item pekerjaan lewat tgl target finish)

NO ITEM PICTURE
1

2 1.

C. INSPECTION

ITEM INSPECTION (item pemeriksaan oleh QC, OS / Class) di tgl daily report di buat

NO ITEM PICTURE REMARKS


1
2

D. Kendala project

NO ITEM PICTURE REMARKS


1
2