MASONRY

12 Stone Masonary (P/1) 1-7


Balochistan Composite Shedule of Rates Chapter -12, (Stone Masonry)
Vol - 1, 2023

Rate (Rs.)
Sr.No Description Units
Labour Composite
Providing, dressing and laying dry uncoursed rubble masonry in
12-1-1 Cu.m 4,392.00 6,945.12
retaining or compound walls including scaffolding.
Cu.ft 124.37 196.66
Providing, dressing and laying dry coursed rubble masonry in
12-2-1 Cu.m 5,406.00 7,929.78
retaining or compound walls including scaffolding.
Cu.ft 153.08 224.55
Providing, dressing and laying dry coursed or uncoursed rubble
12-3-1 Cu.m 4,437.00 6,761.93
pitching of any thickness
Cu.ft 125.64 191.48
Providing, dressing and laying uncoursed rubble masonry in
12-4 - -
foundation, plinth and basement including scaffolding and curing.
a) In mud mortar Cu.m 4,104.00 6,316.61
Cu.ft 116.21 178.87
b) In cement, sand mortar
i) 1 : 3 Cu.m 4,104.00 12,196.22
Cu.ft 116.21 345.36
ii) 1 : 4 Cu.m 4,104.00 10,879.24
Cu.ft 116.21 308.07
iii) 1 : 6 Cu.m 4,104.00 9,534.56
Cu.ft 116.21 269.99
iv 1 : 8 Cu.m 4,104.00 8,862.23
Cu.ft 116.21 250.95
Providing, dressing and laying coursed rubble masonry in foundation,
12-5
plinth and basement including scaffolding and curing.
a) In mud mortar Cu.m 7,080.00 11,708.30
Cu.ft 200.48 331.54
b) In cement, sand mortar
i) 1 : 3 Cu.m 7,752.00 17,069.67
Cu.ft 219.51 483.36
ii) 1 : 4 Cu.m 7,752.00 16,104.67
Cu.ft 219.51 456.03
iii) 1 : 6 Cu.m 7,752.00 14,995.32
Cu.ft 219.51 424.62
iv 1 : 8 Cu.m 7,752.00 14,440.64
Cu.ft 219.51 408.91
Providing, dressing and laying random rubble stone masonry in
12-6 - -
foundation, plinth and basement including scaffolding and curing.
a) In mud mortar Cu.m 5,412.00 8,071.20
Cu.ft 153.25 228.55
b) In cement, sand mortar
i) 1 : 3 Cu.m 5,412.00 13,163.54
Cu.ft 153.25 372.75
ii) 1 : 4 Cu.m 5,412.00 12,063.50
Cu.ft 153.25 341.60
iii) 1 : 6 Cu.m 5,412.00 10,886.92
Cu.ft 153.25 308.28

12 Stone Masonary (P/2) 2-7


Balochistan Composite Shedule of Rates Chapter -12, (Stone Masonry)
Vol - 1, 2023

Rate (Rs.)
Sr.No Description Units
iv 1 : 8 Cu.m 5,412.00 10,298.62
Cu.ft 153.25 291.62
Providing dressing and laying Ashlar Fine masonry in foundation,
12-7 - -
plinth and basement including scaffolding and curing.
a) In cement, sand mortar
i) 1 : 3 Cu.m 28,646.04 36,478.83
Cu.ft 811.16 1,032.96
ii) 1 : 4 Cu.m 28,646.04 35,974.58
Cu.ft 811.16 1,018.69
iii) 1 : 6 Cu.m 28,646.04 35,649.27
Cu.ft 811.16 1,009.47
Providing dressing and laying Ashlar rough tooled or blocks in course
12-8 masonry in foundation, plinth and basement including scaffolding - -
and curing.
a) In cement, sand mortar
i) 1 : 3 Cu.m 25,916.04 33,200.89
Cu.ft 733.86 940.14
ii) 1 : 4 Cu.m 25,916.04 32,427.70
Cu.ft 733.86 918.25
iii) 1 : 6 Cu.m 25,916.04 31,654.51
Cu.ft 733.86 896.35
Providing dressing and laying Ashlar rock rustic or quarry faced
12-9 masonry in foundation, plinth and basement including scaffolding - -
and curing.
a) In cement, sand mortar
i) 1 : 3 Cu.m 17,295.00 23,635.52
Cu.ft 489.74 669.28
ii) 1 : 4 Cu.m 17,295.00 22,855.60
Cu.ft 489.74 647.20
iii) 1 : 6 Cu.m 17,295.00 22,075.69
Cu.ft 489.74 625.11
Providing dressing and laying Ashlar chamferred masonry in
12-10 - -
foundation, plinth and basement including scaffolding and curing.
a) In cement, sand mortar
i) 1 : 3 Cu.m 20,131.20 27,804.11
Cu.ft 570.05 787.32
ii) 1 : 4 Cu.m 20,131.20 27,107.47
Cu.ft 570.05 767.60
iii) 1 : 6 Cu.m 20,131.20 26,334.28
Cu.ft 570.05 745.70
Providing dressing and laying Ashlar fine stone masonry in plain or
12-11 chequerred tread or risers of steps in course masonry in foundation, - -
plinth basement & ground floor, including scaffolding and curing.
a) In cement, sand mortar
i) 1 : 3 Cu.m 27,134.40 34,050.91
Cu.ft 768.36 964.21
ii) 1 : 4 Cu.m 27,134.40 33,546.66
Cu.ft 768.36 949.93

12 Stone Masonary (P/3) 3-7


Balochistan Composite Shedule of Rates Chapter -12, (Stone Masonry)
Vol - 1, 2023

Rate (Rs.)
Sr.No Description Units
iii) 1 : 6 Cu.m 27,134.40 33,042.41
Cu.ft 768.36 935.66
Providing, dressing and laying uncoursed rubble masonry in
12-12 - -
superstructure including scaffolding and curing in ground floor.
a) In mud mortar Cu.m 3,803.23 6,006.81
Cu.ft 107.70 170.09
b) In cement, sand mortar Cu.m
Cu.ft - -
i) 1 : 3 Cu.m 6,006.00 14,155.28
Cu.ft 170.07 400.83
ii) 1 : 4 Cu.m 6,006.00 12,838.30
Cu.ft 170.07 363.54
iii) 1 : 6 Cu.m 6,006.00 11,493.62
Cu.ft 170.07 325.46
iv) 1 : 8 Cu.m 6,006.00 10,821.29
Cu.ft 170.07 306.42
Providing, dressing and laying coursed rubble masonry in
12-13 superstructure including scaffolding and curing in ground floor (steel - -
reinforcement if used will be paid separately)
a) In mud mortar Cu.m 6,615.00 11,229.35
Cu.ft 187.32 317.98
b) In cement, sand mortar
i) 1 : 3 Cu.m 6,757.50 16,189.69
Cu.ft 191.35 458.44
ii) 1 : 4 Cu.m 6,757.50 15,080.34
Cu.ft 191.35 427.03
iii) 1 : 6 Cu.m 6,757.50 13,970.98
Cu.ft 191.35 395.61
iv) 1 : 8 Cu.m 6,757.50 13,416.30
Cu.ft 191.35 379.91
Providing, dressing and laying random rubble stone masonry in
12-14 - -
superstructure including scaffolding and curing in ground floor.
a) In mud mortar Cu.m 7,660.00 10,386.64
Cu.ft 216.91 294.12
b) In cement, sand mortar
i) 1 : 3 Cu.m 7,562.50 15,378.55
Cu.ft 214.15 435.47
ii) 1 : 4 Cu.m 7,562.50 14,278.52
Cu.ft 214.15 404.32
iii) 1 : 6 Cu.m 7,562.50 13,101.93
Cu.ft 214.15 371.01
iv) 1 : 8 Cu.m 7,562.50 12,513.64
Cu.ft 214.15 354.35
Providing, dressing and laying ashlar fine masonry in superstructure
12-15 - -
including scaffolding and curing in ground floor.
a) In cement, sand mortar
i) 1 : 3 Cu.m 34,699.20 42,713.59

12 Stone Masonary (P/4) 4-7


Balochistan Composite Shedule of Rates Chapter -12, (Stone Masonry)
Vol - 1, 2023

Rate (Rs.)
Sr.No Description Units
Cu.ft 982.57 1,209.51
ii) 1 : 4 Cu.m 34,699.20 42,209.33
Cu.ft 982.57 1,195.23
iii) 1 : 6 Cu.m 34,699.20 41,705.08
Cu.ft 982.57 1,180.96
Providing, dressing and laying ashlar rough tooled or blocks in course
12-16 masonry in superstructure including scaffolding and curing in ground - -
floor.
a) In cement, sand mortar
i) 1 : 3 Cu.m 19,895.00 26,999.22
Cu.ft 563.36 764.53
ii) 1 : 4 Cu.m 19,895.00 26,226.03
Cu.ft 563.36 742.64
iii) 1 : 6 Cu.m 19,895.00 25,452.84
Cu.ft 563.36 720.74
Providing, dressing and laying ashlar rock rustic or guary faced
12-17 masonry in superstructure including scaffolding and curing in ground - -
floor.
a) In cement, sand mortar
i) 1 : 3 Cu.m 18,697.50 25,080.09
Cu.ft 529.45 710.19
ii) 1 : 4 Cu.m 18,697.50 24,300.17
Cu.ft 529.45 688.10
iii) 1 : 6 Cu.m 18,697.50 23,520.27
Cu.ft 529.45 666.02
Providing, dressing and laying ashlar fine chamferred masonry in
12-18 - -
superstructure including scaffolding and curing in ground floor.
a) In cement, sand mortar
i) 1 : 3 Cu.m 22,708.20 30,458.42
Cu.ft 643.02 862.49
ii) 1 : 4 Cu.m 22,708.20 29,761.78
Cu.ft 643.02 842.76
iii) 1 : 6 Cu.m 22,708.20 28,988.59
Cu.ft 643.02 820.86
Providing, dressing and laying ashlar fine stone masonry punched
12-19 work in superstructure including scaffolding and curing in ground - -
floor. (Gross measurement will be made).
a) In cement, sand mortar
i) 1 : 3 Cu.m 33,121.35 41,792.53
Cu.ft 937.89 1,183.43
ii) 1 : 4 Cu.m 33,121.35 43,699.98
Cu.ft 937.89 1,237.44
iii) 1 : 6 Cu.m 33,121.35 43,195.73
Cu.ft 937.89 1,223.17
Providing, dressing and laying ashlar fine stone masonry in sink or
moulded work upto & sectional area of 50 Sq.in. (325 Sq.cm) in
12-20 - -
cornice, coping and architrave etc. in superstructure including
scaffolding and curing in ground floor.
a) In cement, sand mortar

12 Stone Masonary (P/5) 5-7


Balochistan Composite Shedule of Rates Chapter -12, (Stone Masonry)
Vol - 1, 2023

Rate (Rs.)
Sr.No Description Units
i) 1 : 3 R.M. 1,280.64 1,536.20
R.ft 390.44 468.35
ii) 1 : 4 R.M. 1,280.64 1,553.52
R.ft 390.44 473.63
iii) 1 : 6 R.M. 1,280.64 1,547.76
R.ft 390.44 471.88
Providing, dressing and laying ashlar fine stone masonry in sink or
moulded work above sectional area of 50 sq.in. to 100 sq.in. (325
12-21 - -
sq.cm to 650 sq.cm ) in cornice, coping and architrave etc. in
superstructure including scaffolding and curing in ground floor.
a) In cement, sand mortar
i) 1 : 3 R.M. 2,594.18 3,068.43
R.ft 790.91 935.50
ii) 1 : 4 R.M. 2,594.18 3,133.58
R.ft 790.91 955.36
iii) 1 : 6 R.M. 2,594.18 3,122.12
R.ft 790.91 951.87
Dressing stones (Dressed face shall be considered for measurement).
12-22 - -
a) Random rubble hammer dressed Sq.m 1,289.13 1,295.79
Sq.ft 119.76 120.38
b) Ashlar rough tool dressed Sq.m 2,735.28 2,735.28
Sq.ft 254.12 254.12
c) Ashlar chisel dressed Sq.m 3,379.85 3,379.85
Sq.ft 314.00 314.00
d) Ashlar fine dressed Sq.m 7,598.45 7,598.45
Sq.ft 705.92 705.92
Extra for providing, dressing and laying stone masonry for arches of
12-23 any kind of walls including scaffolding, formwork and its removal, Cu.m 1,848.00 2,398.32
raking out joints and curing.
Cu.ft 52.33 67.91
12-24 a) Extra for first floor over item No.12 - 11 to 12 - 14 Cu.m 1,411.50 1,453.85
Cu.ft 39.97 41.17
Extra for every additional floor above first floor on item 12 - 24 (a)
b Cu.m 1,095.00 1,127.85
Cu.ft 31.01 31.94
12-25 a) Extra for first floor over item No.12 - 15 to 12 - 18. Cu.m 1,810.50 1,864.82
Cu.ft 51.27 52.81
Extra for every additional floor above first floor on item 12 - 25 (a)
b) Cu.m 1,229.40 1,266.28
Cu.ft 34.81 35.86
12-26 a) Extra for punched work in first floor on item No.12 - 19. Cu.m 1,558.50 1,605.26
Cu.ft 44.13 45.46
Extra for every additional floor above first floor on item 12 - 26 (a).
b) Cu.m 1,187.40 1,223.02
Cu.ft 33.62 34.63
12-27 a) Extra for first floor on item 12 - 20. R.M. 16.13 16.62
R.ft 4.92 5.07
Extra for every additional floor above first floor on item 12 - 27 (a).
b) R.M. 12.51 12.89

12 Stone Masonary (P/6) 6-7


Balochistan Composite Shedule of Rates Chapter -12, (Stone Masonry)
Vol - 1, 2023

Rate (Rs.)
Sr.No Description Units
R.ft 3.82 3.93
12-28 a) Extra for first floor on item 12 - 21. R.M. 41.15 42.38
R.ft 12.55 12.92
Extra for every additional floor above first floor on item 12 - 28 (a).
b) R.M. 27.94 28.78
R.ft 8.52 8.77
Extra for stone masonry of any description in any floor or other than
12-29-1 building for every 5 ft. (1.5 m.) height or part thereof beyond 15 ft. Cu.m - 2,025.46
(4.5m) height.
Cu.ft - 57.35
Extra for stone masonry in cornice, coping and architrave in any floor
12-30-1 or other than building for every 5 ft.( 1.5m) height or part thereof R.M. 13.77 14.18
beyond 15ft. (4.5m) on item 12-21
R.ft 4.20 4.32
Extra for stone masonry in cornice, coping and architrave in any floor
12-31-1 or other than building for every 5 ft. (1.5m) height or part thereof R.M. 20.38 20.99
beyond 15ft. (4.5m) on item 12-22
R.ft 6.21 6.40