LUASAN DINDING BATAKO LANTAI 1

 AS 1 A-B = 5,7 m x 3,55 m = 20,235 m²


 AS 1 B-C = 3,595 m x 3,55 m = 12,76 m²
 AS 7 A-B = 5,7 m x 3,55 m = 20,235 m²
 AS 7 B-C = 3,595 m x 3,55 m = 12,76 m²
 AS A 1-2 = 4,7 m x 3,55 m = 16,685 - 1,935 – 3,72 = 11,03 m²
( Pintu = 2,15 x 0,9 = 1,935 m² )
( Jendela = 1,55 x 1,2 = 1,86 m² x 2 = 3,72 m² )
 AS A 2-3 = 4,7 m x 3,55 m = 16,685 - 1,935 – 3,72 = 11,03 m²
( Pintu = 2,15 x 0,9 = 1,935 m² )
( Jendela = 1,55 x 1,2 = 1,86 m² x 2 = 3,72 m² )
 AS A 3-4 = 1,8 m x 3,55 m = 6,39 + 2,75 = 9,14 – 1,935 = 7,205 m²
( 0,775 m x 3,55 m = 2,75 m²)
 AS A 4-5 = 2,775 m x 3,55 m = 9,85 + 4,199 + 1,56 =16,61 – 7,2= 9,41 m²
(1,183 m x 3,55 m = 4,199 m²)
(0,442 m x 3,55 m = 1,56 m ²)
(Boven = 0,6 x 0,6 = 3,6 m²)
 AS A 5-6 = 2,775 m x 3,55 m = 9,85 + 4,199 + 1,56 =16,61 - 7,2 - 3,72= 5,69 m²
(1,183 m x 3,55 m = 4,199 m²)
(0,442 m x 3,55 m = 1,56 m ²)
(Boven = 0,6 x 0,6 = 3,6 m² x 2 = 7,2 m²)
(Jendela = 1,55 x 1,2 = 1,86 m² x 2 = 3,72 m² )
 AS A 6-7 = 4,7 m x 3,55 m = 16,685 m² - 3,73 m² – 1,935 m²= 11,02 m²
(Jendela = 1,55 x 1,2 = 1,86 m² x 2 = 3,72 m² )
( Pintu = 2,15 x 0,9 = 1,935 m² )
 AS A-B 3-4 = 4,75 m x 3,55 m = 16,86 m²
 AS A-B 4-5-6
1,45 m x 3,55 m = 5,15 m²
3,43 m x 3,55 m = 12,18 m²
1,183 m x 3,55 m x 3 = 12,6 m² - (0,72 x 2,15 x 3) = 7,94 m²
1,775 m x 3,55 m x 2 = 12,6 m²
4,325 m x 3,55 m = 15,35 m²
1,45 m x 3,55 m = 5,15 m²
Total = 58,99 m²
 AS C 1-2 = 4,62 m x 3,55 m = 16,4 - 3,72 - 1,935 = 10,75 m²
(Jendela = 1,55 x 1,2 = 1,86 m² x 2 = 3,72 m² )
( Pintu = 2,15 x 0,9 = 1,935 m² )
 AS C 2-3 = 4,75 m x 3,55 m = 16,86 – 3,72 = 13,14 m²
(Jendela = 1,55 x 1,2 = 1,86 m² x 2 = 3,72 m² )
 AS C 2-3 = 4,75 m x 3,55 m = 16,86 – 3,72 = 13,14 m²
 AS C 3-4 = 1,825 m x3,55 m=6,5 m²+1,33 m²=7,83 m²-1,935 m²=5,9 m²
( Pintu = 2,15 x 0,9 = 1,935 m² )
 AS C 4-5= 4,325 m x 3,55 m = 15,36 m² -1,935 m² - 1,86 m² =11,565 m²
( Pintu = 2,15 x 0,9 = 1,935 m² )
( Jendela = 1,55 x 1,2 = 1,86 m²)
 AS C 5-6 = 4,75 m x 3,55 m = 15,36 m² - 1,86 m² = 13,5 m²
( Jendela = 1,55 x 1,2 = 1,86 m²)
 AS C 6-7 = 4,75 m x 3,55 m = 15,36 m² - 1,86 m² = 13,5 m²
( Jendela = 1,55 x 1,2 = 1,86 m²)
TOTAL LUASAN DINDING BATAKO =
=20,235 m² + 12,76 m² + 20,235 m² + 12,76 m² + 11,03 m² + 7,205 m² + 9,41 m² + 5,6
9 m² + 11,02 m² + 16,86 m² + 58,99 m² + 10,75 m² + 13,14 m² + 13,14 m² + 11,565 m²
+ 13,5 m² + 13,5 m² = 359,8 ~ 360 m²
TOTAL KEBUTUHAN BATAKO
=360 m² x 23 buah = 8280 buah ~ 8300 buah

LUASAN DINDING BATAKO LANTAI 2


 AS 1 A-B = 5,725 m x 3,55 m = 20,32 m²

 AS 1 B-C = 3,9 m x 3,55 m = 13,845 m²

 AS 7 A-B = 5,725 m x 3,55 m = 20,32 m²

 AS 7 B-C = 3,9 m x 3,55 m = 13,845 m² - 3,6 m² = 10,245 m²

(Boven = 0,6 x 0,6 = 3,6 m²)


AS A 1-2 = 4,992 m x 3,55 m = 17,73 m² - 3,72 m² = 14,01 m²
(Jendela = 1,55 x 1,2 = 1,86 m² x 2 = 3,72 m² )
AS A 2-3 = 4,992 m x 3,55 m = 17,73 m² - 1,86 m² = 15,87 m²
(Jendela = 1,55 x 1,2 = 1,86 m² )
AS A 3-4 = 4,992 m x 3,55 m = 17,73 m² - 1,86 m² = 15,87 m²
(Jendela = 1,55 x 1,2 = 1,86 m² )
AS A 4-5 = 4,992 m x 3,55 m = 17,73 m² - 1,86 m² = 15,87 m²
(Jendela = 1,55 x 1,2 = 1,86 m² )
AS A 5-6 = 4,992 m x 3,55 m = 17,73 m² - 1,86 m² = 15,87 m²
(Jendela = 1,55 x 1,2 = 1,86 m² )
AS A 6-7 = 4,992 m x 3,55 m = 17,73 m² - 3,72 m² = 14,01 m²
(Jendela = 1,55 x 1,2 = 1,86 m² x 2 = 3,72 m² )
AS C 1-2 = 4,992 m x 3,55 m = 17,73 m² - 3,72 m² = 14,01 m²
(Jendela = 1,55 x 1,2 = 1,86 m² x 2 = 3,72 m² )
AS C 2-3 = 4,992 m x 3,55 m = 17,73 m² - 1,86 m² = 15,87 m²
(Jendela = 1,55 x 1,2 = 1,86 m² )

AS C 3-4 = 3,925 m x 3,55 m = 13,93 m² - 1,86 m² = 12,07 m²


(Jendela = 1,55 x 1,2 = 1,86 m² )
AS C 4-5 = 1,95 m x 3,55 m = 6,93 m²
AS C 5-6 = 4,992 m x 3,55 m = 17,73 m² - 3,72 m² = 14,01 m²
(Jendela = 1,55 x 1,2 = 1,86 m² x 2 = 3,72 m² )
AS C 6-7 = 4,992 m x 3,55 m = 17,73 m² - 3,72 m² = 14,01 m² - 10,8 m² = 3,21 m²
(Boven = 0,6 x 0,6 = 3,6 m² x 3 = 10,8 m²)
AS B-C 6-7 = 14,2 + 3,195 + 3,73 + 6,93 + 9,05 + 5,15 = 42,26 m²
= 4 m x 3,55 m = 14,2 m²
= 0,9 m x 3,55 m = 3,195 m²
= 1,05 m x 3,55 m = 3,73 m²
= 1,95 m x 3,55 m = 6,93 m²
= 0,85 m x 3,55 m x 3 = 9,05 m²
= 1,45 m x 3,55 m x 2 = 5,15 m²
TOTAL LUASAN DINDING BATAKO = 20,32 m² + 13,845 m² + 20,32 m² + 10,245 m² +
14,01 m² + 15,87 m² + 15,87 m² + 15,87 m² + 15,87 m² + 14,01 m² + 14,01 m² +
15,87 m² + 12,07 m² + 6,93 m² + 14,01 m² + 3,21 m² + 42,26 m² = 264, 59 ~ 265 x 11
buah
TOTAL KEBUTUHAN BATAKO
= 265 m² x 23 buah / m² = 6095 ~ 6100 buah