Professional Documents
Culture Documents
And nowadays in the field too much competition for the job, but during the
college course if you have studied well and have good knowledge in civil then
there is a chance that you can get the job.
Still, in a fresher mind, they don’t know which are the main point should know
about civil works, so today here we are going to tell you some essential points
about the site by which you can understand civil works properly.
Basically, in the slab, first of all, we use the main bars, and then to keep the
main bars in the position we use the distribution bar, and in a two-way slab,
we consider the distribution bar as the main bar. In the slab, there is one way
or two-way slab, for identity which is one way or which is two way there is a
basic formula
Longer span/ shorter span < 2 , so this is a two-way slab and if it comes
greater than 2 then it’s a one-way slab.
For example, if the slab length is 6m and the breadth is 2m then according to
the formula it comes greater than 2m which means it’s a one-way slab.
And in the two-way slab, we can see the load distribution around the slab.
This is also an important point at a site what is the weight of the rod per meter
length? because you will see at site lots of bars there for use in different
structure so for civil engineers it’s important that they should know how to
calculate the weight of the bar .so here is the formula:
Here d is indicated for the diameter of the bar & l for the length of the bar
So by this formula easily can calculate the bar weight .and at the site during
the BBS it is very helpful for calculating the weight.
And there is some more point which is related to bars. L for column main rod
in footing is 300 mm minimum. and there is also a formula by which can get
the length which is equal to the 50d, where d is indicated for the diameter of
the bar. And the hook length for the stirrups is 9d.
. Concrete grade
M10 1 3 6
M15 1 2 4
M20 1 1.5 3
M25 1 1 2
M30 1 1 3
concrete work
. Parapet Wall
and some points which are related to the pipes and electrical conduct are also
important to know, so the sanitary pipes and electrical conduct will not be
installed in between the column and beam.
. chair bars
In the construction of the slab, we are providing the chair bars, so 1 chair bar
is provided every 1m^2 area that’s means spacing not more than 1 meter. And
the bars which are used for making the chair they’re a minimum diameter will
be 12mm.
Rebar work
foundation
1. Shallow foundation
2. Deep foundation
And before we go pipe foundation we should know that the pipe foundation is
adopted when the soil bearing capacity is less than 24KN/M^3.
.Masonry works
construction wall
A mason can cover 25 to 30 m^3 bricks work in a day, the works progress also
depends on the skill of the mason and their knowledge .a mason is responsible
for the bricks works, plaster works, finishing, concrete, etc.
And mason leads the helpers to complete the work in the proper ways. A
well-skilled mason has some basic knowledge. They should know how to use
the measurement tap, their common use tools, etc.
In masonry works it’s important to know that the inner wall plaster size is
12mm, for roof plaster it should be 6-8 mm, and the outer wall should be
14mm -16mm, but it is also not fixed can change also according to the
structure.