You are on page 1of 3

Risk Assessment for Laying of Pipes

Project No.: Location: Report No.:


____________________________________________________________________________________
Project Name: __________________________________________ Date:
____________________________________________________________________________________

SEVERITY: 1 – Slightly Harmful, 2 – Harmful, 3 – Extremely Harmful; LIKELIHOOD: 1 – Unlikely, 2 – Likely, 3 – Very Likely; RISK LEVEL: 1 – Trivial, 2 – Low, 2 to 4 – Medium, 4
to 6 – High, Above 6 – Extremely High.

Risk
Residual Risk
Evaluation

Likelihood

Likelihood

Risk Level
Risk Level
Sr. No. Activity Hazard Effect / Harm Control Measures Monitoring Mechanism

Severity

Severity
1.Entrapment due 1. Operator trained to
to fall/ roll of pipe. Personnel injury, loss of 3 3 9 the Approved CPCS 1 3 L Safety personnel
assets, health impact, surveillance, giving
2. Operators body injury. (Construction Plant first aid, & proper
direct field of Competence toolbox talk.
vision obscured by Scheme) standard as Induction training.
load leading to per the
Laying of Pipes
1.
contact with other 2. Construction
3.persons or plant. Regulations.
4.Failure of lifting 3. Vehicles should
equipment. never be overloaded.
5.Inadequate Loads should be
supervision. equally distributed,
6.Untrained secured and not
Operatives protruding, tilting
7.Use of mobile beyond the sides or
phones by back of the vehicle.
operators. 4. Reverse beeper,
8.Displacement of flashing beacon,

Prepared by: Name: Noted by: Name:


HSE Department Signature & Date: Project Department Signature & Date:

Doc. No.: Rev. No.: 001 Date: 30/05/2020 Page 1 of 3


Risk Assessment for Laying of Pipes
Project No.: Location: Report No.:
____________________________________________________________________________________
Project Name: __________________________________________ Date:
____________________________________________________________________________________

SEVERITY: 1 – Slightly Harmful, 2 – Harmful, 3 – Extremely Harmful; LIKELIHOOD: 1 – Unlikely, 2 – Likely, 3 – Very Likely; RISK LEVEL: 1 – Trivial, 2 – Low, 2 to 4 – Medium, 4
to 6 – High, Above 6 – Extremely High.

load CCTV and or mirrors


9.The person being fitted
struck by a 5. Defective skids
suspended pipe removed
causing serious immediately from
injury or harm. the line.
10. Defective 6. Heavy-duty gloves to
and broken skids be worn by
causing crushing operatives handling
of limbs of skids.
entrapment of 7. All engines guards
body parts. and covers to be in
11. Manual position and
Handling. secured.
8. Windows, lights,
mirrors and camera
lens to be kept clean
at all times
9. The cab floor to be
kept clean and free
from any obstacles
which may affect the
safe operation of the

Prepared by: Name: Noted by: Name:


HSE Department Signature & Date: Project Department Signature & Date:

Doc. No.: Rev. No.: 001 Date: 30/05/2020 Page 2 of 3


Risk Assessment for Laying of Pipes
Project No.: Location: Report No.:
____________________________________________________________________________________
Project Name: __________________________________________ Date:
____________________________________________________________________________________

SEVERITY: 1 – Slightly Harmful, 2 – Harmful, 3 – Extremely Harmful; LIKELIHOOD: 1 – Unlikely, 2 – Likely, 3 – Very Likely; RISK LEVEL: 1 – Trivial, 2 – Low, 2 to 4 – Medium, 4
to 6 – High, Above 6 – Extremely High.

Machine.
10. Groundworkers to
wear Hi-Visibility
Vests at all times and
Hard-Hats.
11. Warning signs will
be erected to alert
pedestrians of
Unloading/Loading
Operations.
12. Traffic
management must
be in the place
where
loading/unloading is
being carried out on
public roads.
13. Loads to be tipped
only on suitably level
ground to prevent
overturning of skip

Prepared by: Name: Noted by: Name:


HSE Department Signature & Date: Project Department Signature & Date:

Doc. No.: Rev. No.: 001 Date: 30/05/2020 Page 3 of 3