3.0 PURPOSE:
This procedure covered isolation steps for safe handover of ammonium nitrate evaporation circuit
17-2307/08/09 for maintenance purpose.
7.0 PREREQUISITE:
7.1 Inform UM CAN and Coordination engineer in event of heavy AN leakage or spillage.
7.2 Ensure the availability of fire water and fresh water supply.
7.3 Ensure full face gas masks and SCABA are in good health for immediate use in case of emergency.
7.4 The hose pipe should be certified and properly clamped.
7.5 Monitor the wind direction intermittently with reference to NAST.