SAPL-III Revision No 01
Vendor Selection & Control Date 03.11.2015
Page No 1 to 13
1.0 Purpose
The purpose of this procedure is to detail the steps to be followed during Vendor Selection,
Approval and their control.
2.0 Scope
This procedure is applicable to existing and new suppliers for the procurement of raw
Materials related to production and for sub-contracting works like machining,
Surface Treatment, Heat Treatment & BO Parts.
4.0 Procedure
Reviewed By : Approved By :
Date : Date :
Quality System Procedure Doc. No.: SAPL-III / QSP /0703
SAPL-III Revision No 01
Vendor Selection & Control Date 03.11.2015
Page No 2 to 13
Start - - - -
Incoming
Potential vendor will be evaluated as per Purchase Quality Office
Vendor Rating Guidelines & Recorded in Incoming- T + 22
4.1.4 Vendor (QMS) sheet. Min required 80 % in Ins / MR SAPL-III/F/12
QMS Audit. (Vendor
Follow the Evaluation)
Step no 4.1.9
Incoming
Ok Quality Office
GM-Op & T + 22
4.1.5 Review Incoming-
Not Ok Ins
Reviewed By : Approved By :
Date : Date :
Quality System Procedure Doc. No.: SAPL-III / QSP /0703
SAPL-III Revision No 01
Vendor Selection & Control Date 03.11.2015
Page No 3 to 13
Sl.No Activity Resp Time Location Format
(Max)
A
Incoming- T + 37 Days Incoming -
4.1.6 Ins, Quality Office
Purchase
Countermeasure report will be obtained Executive
from Potential vendors.
Incoming-
Ins / MR ,
Purchase T + 52 Days Incoming SAPL-III/F/46
4.1.7 Executive Quality Office ( Corrective
Final audit will be conducted after the action )
Implementation of corrective action on the
Finding of First audit.
4.1.8
End
4.1.9
4.1.10
-
Completion of Commercials with Purchase Incoming-
Purchase T + 30 Days Office
Time
Sl.No Activity Resp Location Format
(Max)
Reviewed By : Approved By :
Date : Date :
Quality System Procedure Doc. No.: SAPL-III / QSP /0703
SAPL-III Revision No 01
Vendor Selection & Control Date 03.11.2015
Page No 4 to 13
B Not ok
END
Incoming
Initial samples will be obtained from the Ins
4.1.12 vendor. T + 37 Days Incoming-
Office -
Incoming
Ins
4.1.13 Samples Validation as per Relevant T + 39 Days Incoming
Spec. / Std. Office
Follow step
Step no 4.1.17 -
AGM &
Incoming
Ok Ins
4.1.14 Not okRevie T + 40 Days Incoming
w Office
Purchase
Obtain Fresh samples after implementation Executive
4.1.15 of Countermeasure Max. No. of Times: 03 T + 47 Days Incoming
for samples meeting the spec. Office
Time
Sl.No Activity Resp Location Format
(Max)
Reviewed By : Approved By :
Date : Date :
Quality System Procedure Doc. No.: SAPL-III / QSP /0703
SAPL-III Revision No 01
Vendor Selection & Control Date 03.11.2015
Page No 5 to 13
Not meeting the spec after 3 samples reject Incoming-Ins T + 48 Days Incoming -
4.1.16 the Vendor &Purchase Office
Executive
END
Purchase
1) For New Projects samples as per Trial Executive & T + 50 Days Incoming -
PD Team Office
4.1.17 quantity in Project Plan.
2) For existing Product LVPT run.
Not ok
Incoming-Ins
T+52 Incoming -
4.1.18 Ok
Review Days Office
PD
Team ,Purch
ase T + 59 Incoming- -
HVPT run. &Incoming Days Office
4.1.19
PD Team &
Purchase T + 60 Incoming -
4.1.20 PPAP / ISAR Samples Obtained.
Days Office
T + 67 days
Incoming & to Incoming -
4.1.21
Validation of PPAP / ISAR Samples PD Team T + 82days Office
In case of
corrective
action
Time
Sl.No Activity Resp Location Format
(Max)
Reviewed By : Approved By :
Date : Date :
Quality System Procedure Doc. No.: SAPL-III / QSP /0703
SAPL-III Revision No 01
Vendor Selection & Control Date 03.11.2015
Page No 6 to 13
END
Reviewed By : Approved By :
Date : Date :
Quality System Procedure Doc. No.: SAPL-III / QSP /0703
SAPL-III Revision No 01
Vendor Selection & Control Date 03.11.2015
Page No 7 to 13
Start
Incoming-
Ins , Once In Incoming Supplier Audit
4.2.1 Purchase Year Office Plan
Executive
All existing vendors will be evaluated as per
Plan. Expect Raw Material Vendors
Time
Sl.No Activity Resp Location Format
(Max)
Reviewed By : Approved By :
Date : Date :
Quality System Procedure Doc. No.: SAPL-III / QSP /0703
SAPL-III Revision No 01
Vendor Selection & Control Date 03.11.2015
Page No 8 to 13
End
Reviewed By : Approved By :
Date : Date :
Quality System Procedure Doc. No.: SAPL-III / QSP /0703
SAPL-III Revision No 01
Vendor Selection & Control Date 03.11.2015
Page No 9 to 13
Sl.No Activity Resp Time Location Format
(Max)
- - - -
Start
Vendor Selection
Review
4.3.3 Purchase - T Admin Office -
Asst
Existing vendor from
4.3.4 the list of approved Dir - Op T Admin Office -
vendor
A
4.3.5 Dir - Op T+2 Admin Office -
Days
Submission of Design
Time
Sl.No Activity Resp Location Format
(Max)
Reviewed By : Approved By :
Date : Date :
Quality System Procedure Doc. No.: SAPL-III / QSP /0703
SAPL-III Revision No 01
Vendor Selection & Control Date 03.11.2015
Page No 10 to 13
X
NO Follow the Step
No : 43.6 Dir – Op
4.3.7 & NPD En T + 21 Admin Office -
Days
Design
Yes
Approval
Dir – Op
4.3.9 & NPD En T + 28 Admin Office -
Days
Progress Review
- - - -
END
Time
Sl.No Activity Resp Location Format
(Max)
Reviewed By : Approved By :
Date : Date :
Quality System Procedure Doc. No.: SAPL-III / QSP /0703
SAPL-III Revision No 01
Vendor Selection & Control Date 03.11.2015
Page No 11 to 13
Time
Sl.No Activity Resp Location Format
(Max)
Reviewed By : Approved By :
Date : Date :
Quality System Procedure Doc. No.: SAPL-III / QSP /0703
SAPL-III Revision No 01
Vendor Selection & Control Date 03.11.2015
Page No 12 to 13
X
4.3.22 Dir –Op & T + 22 Admin Office -
NPD En Days
Progress Review
-
END
Reviewed By : Approved By :
Date : Date :
Quality System Procedure Doc. No.: SAPL-III / QSP /0703
SAPL-III Revision No 01
Vendor Selection & Control Date 03.11.2015
Page No 13 to 13
6.0 RECORDS
6.1 Vendor Evaluation SAPL III/F/12 / or Customer specific audit (VDA 6.3)
Reviewed By : Approved By :
Date : Date :