Professional Documents
Culture Documents
(216MW)
Contents
1. Introduction ..................................................................................................................................... 04
2. Purpose ............................................................................................................................................ 04
6. Mixing .............................................................................................................................................. 06
Page 3 of 10
UPPER TRISHULI-1 HEP
(216MW)
1. Introduction
CSGR method is a new technique proposed for Roller Compacted Concrete. The creation of "CSGR"
technology, which has the goals of enhanced safety, rapid construction, reduced construction costs,
and improved environmental protection, is one of many technologies that have been created to
construct dams. The CSGR construction method is, “Spreading CSGR with a bulldozer and
compacting it with a vibrating roller to form a structure.”CSGR Concrete is best described as a zero-
slump concrete that is placed with standard or high-density paving equipment and
consolidated/compacted using steel-drum or rubber-tired rollers to achieve the required strength and
durability.
2. Purpose
The cemented sand-gravel and rock (CSGR) mixtures are widely used for the fast and economical
construction of embankments such as dams/cofferdams. This would ensure an effective consolidation
which is crucial for achieving satisfactory density, strength, smoothness, and surface texture. The
CSGR concrete is constructed without joints, formwork, finishing, steel reinforcement, or dowels.
These characteristics make CSGR concrete simple, fast, and economical. CSGR concrete owes much
of its economy to high-volume, high-speed construction methods. It is applied for the construction
and rehabilitation of dams/cofferdams, roads, airfields, parking lots, power plants, road shoulders,
storage facilities, military facilities, and other industrial complexes and it’s dependingon the desired
thickness. “CSGR” is a concrete, which can be considered as roller compacted concrete, cement, and
cementitious material like fly ash for slow setting and reducing the heat of hydration of mass concrete
with tunnel muck material that can be obtained easily from sites, then the mixing it briefly with the
simple equipment like excavator, loaderand spreading over a designated layer thereafter
rolling/compaction with the rollers.
3. Surface preparation
Well-prepared flat ground surfaces, uniformly compacted to the specified densities will properly
support the loads imposed on the concrete above. In addition, by controlling water content in the
ground over time, soils won't shrink or expand. Proper foundation preparation is very important to the
performance of a project. This includes the removal of weak materials from the surface, sub-grade
evaluation, the selection of suitable materials for use as fill, proper compaction, control of moisture,
and providing flat uniform surfaces for CSGR concrete placement.
Page 4 of 10
UPPER TRISHULI-1 HEP
(216MW)
4. Construction Procedure
Tunnel Mucking
Transportation
Foundation Clearance
Mixing
Material Spreading
Roller Compaction
Page 5 of 10
UPPER TRISHULI-1 HEP
(216MW)
• Using equipment that is adequate in size and number to meet the construction requirements.
• Provide required equipment at the construction site.
• Sequence construction operation, for instance, access and routing for equipment, air and water
support system, foundation preparation and joint treatment, setting of forms or precast work,
setting of line and grade control, placement of conventional concrete at contacts or in facings,
and placement of bedding mortar. These operations should be carried out with minimum
interference with the placement, spreading, and compaction works of CSGR.
6. Mixing
The CSGR method changes the production-controlling elements of mass-concrete placements from
the rate of placement for conventional mass concrete to the output of the concrete plant and delivery
system for CSGR. Rapid and continuous delivery of CSGR is important to mass applications. The
tunnel muck material shall be sieved by a 150mm sieve and 150mm passing muck material, Cement,
and other ingredients according to the mix design ratio shall be properly mixed with appropriate
volume by the Excavator. Mixture uniformity should be maintained at all production rates that will be
used. Continuous mixers typically work efficiently above a minimum production rate, and up to
production levels that are two to three times that of the minimum rate.
CSGR Concrete is a type of concrete that can support a roller during its unhardened state while it is
being compacted. The placement and compaction of CSGR is a rapid construction process and
therefore its success relies on the pre-construction planning and coordination of all interrelated
activities. The CSGR concrete should be as fresh as possible at the time of placement to compact it
Page 6 of 10
UPPER TRISHULI-1 HEP
(216MW)
At the time of compaction, CSGR concrete mixture should still be fresh to get the best compaction
results. The bond between different lifts of CSG concrete should be ensured by performing lift surface
cleaning, maintaining surface moisture, and utilizing a bonding mixture like fluid bedding mortar or
concrete. The concrete mixture should be compacted when placed and spread in a uniform lift
thickness. Normally, rolling procedures start with a static pass to even out the loosely placed concrete,
and then the vibratory roller is applied.
The minimum number of passes for a given vibrating roller to achieve specified compaction depends
primarily on the CSGR mixture workability and lift thickness. The compacted thickness of any CSGR
lift should be at least 3 times the diameter of the NMSA. The concrete placement should correlate the
number of passes to obtain the designated density for the mixture within a given moisture content
range.
Page 7 of 10
UPPER TRISHULI-1 HEP
(216MW)
9. Quality Control
While quality control is customarily considered to be an activity performed during CSGR concrete
placement, it is also essential that quality control be considered during design, planning, and the initial
phases of construction of a CSGR concrete. After, the compaction of concrete the DT (Density Test)
shall be performed by the sand replacement method in accordance with standard code ASTM D 4914.
Routine quality control tests shall be performed to determine whether the concrete made for use on
the job attains the requisite properties. The Temperature shall be tested and cubes will be made for
compressive strength test, cured, stored, and tested in accordance with ASTM Standards under
ambient climatic conditions. From each shift, three specimens (cubes) will be made for testing
(compressive strength) at 7 days, three specimens for testing at 28 days, and three specimens for
testing at 90 days for control purposes. For the compressive strength test of the core sample, the
preferred minimum core diameter is three times the nominal maximum size of coarse aggregate, but it
should be at least two times the nominal maximum size of coarse aggregate. The NMSA of CSGR
concrete is 150mm thus the core sample shall not be taken.
A structure should be designed with consideration of what measures will be required during
construction to ensure that the required quality is attained. It is obvious that the design of projects
where little quality control is anticipated should be more conservative than the design of a project
where a very effective quality-control program will be implemented. In addition to testing, a quality-
control program should consider the various construction operations basic to CSGR and how they are
performed. Preparation and advance planning are key to the success of quality construction.
Preconstruction meetings, preconstruction testing, and preconstruction evaluations such as test
sections, are critical parts of the quality program. Once CSGR placement is underway, the quality-
control program should include continuous evaluations that quickly resolve quality variations.
Page 8 of 10
UPPER TRISHULI-1 HEP
(216MW)
Manpower
Site QC Engineer 6
Foreman 2
Welder 2
Electrician 2
Yardman 2
Page 9 of 10
UPPER TRISHULI-1 HEP
(216MW)
Page 10 of 10